2022-06806. Daniel N. Evans; James Bocell; Notice of Transfer of Exemption  

  • Start Preamble

    1. On February 24, 2022, Daniel N. Evans, exemptee for the 288-Kilowatt Caroleen Mills Hydroelectric Project No. 7679, filed a letter notifying the Commission that the project was transferred from Daniel N. Evans to James Bocell. The exemption from licensing was originally issued on December 4, 1984.[1] The project is located on the Second Broad River in Rutherford County, North Carolina. The transfer of an exemption does not require Commission approval.

    James Bocell is now the exemptee of the Caroleen Mills Hydroelectric Project No. 7679. All correspondence must be forwarded to: Mr. James Bocell, c/o Deal First Inc., 4600 Greenville, Suite 288, Dallas, TX 75206, Phone: 913-424-4576, Email: bo@cgitx.com .

    Start Signature
    Start Printed Page 18785

    Dated: March 25, 2022.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    Footnotes

    1.   Clearwater Hydro Company, 29 FERC ¶ 62,224 (1984). Subsequently, the project was transferred to Daniel N. Evans, 106 FERC ¶ 62,116 (2004).

    Back to Citation

    [FR Doc. 2022-06806 Filed 3-30-22; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
03/31/2022
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2022-06806
Pages:
18784-18785 (2 pages)
Docket Numbers:
Project No. 7679-009
PDF File: