NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-317 and 50-318]
Baltimore Gas and Electric Company; Notice of Consideration of
Issuance of Amendments To Facility Operating Licenses, Proposed No
Significant Hazards Consideration Determination, and Opportunity for a
Hearing
On Friday, January 31, 1997, a Federal Register Notice (62 FR 4816)
[[Page 11313]]
was published stating that the U.S. Nuclear Regulatory Commission (the
Commission) is considering issuance of an amendment to Facility
Operating License Nos. DPR-53 and DPR-69 issued to the Baltimore Gas
and Electric Company (BGE or the licensee) for operation of the Calvert
Cliffs Nuclear Power Plant, Unit Nos. 1 and 2, located in Calvert
County, Maryland.
The proposed amendments requested by the licensee in a letter dated
December 4, 1996, would represent a full conversion from the current
Technical Specifications (TSs) to a set of TS based on NUREG-1432,
Revision 1, ``Standard Technical Specifications, Combustion Engineering
Plants dated April 1995. Since that time, the Commission has received
supplements to the application dated March 27, June 9, June 18, July
21, August 19, September 10, October 6, October 20, October 23,
November 5, 1997, and January 12 and 28, 1998. Therefore, issues not
fully discussed in (62 FR 4816) are presented below.
The proposed amendment includes the following:
1. The licensee is proposing to add a new surveillance requirement
(SR) 3.4.9.2 to the Improved Technical Specifications (ITS) which will
require verification that the capacity of each required bank of
pressurizer heaters is equal to or greater than 150 kW every 24 months.
This is a more restrictive change.
2. The licensee has proposed a change to the current TS
applicability for the pressurizer safety valves which require that both
safety valves be operable in Modes 1, 2, and 3 and that one safety
valve be operable in Modes 4 and 5. The ITS will modify these
applicability requirements for Mode 3 to specify that two safety valves
shall be operable with all reactor coolant system (RCS) cold leg
temperature >365 deg.F for Unit 1 and >301 deg.F for Unit 2. This is
a less restrictive change.
3. The licensee proposes that the power-operated relief valve
(PORVs) be demonstrated operable by performance of a channel test once
per 92 days as part of the conversion to the ITS. The current TS
require that the PORVs be demonstrated operable by performance of a
Channel Function Test once per 31 days. This a less restrictive change.
4. Current TS 3.4.6 2.C specifies that the RCS shall be limited to
``1 gpm total primary--to secondary leakage through all steam
generators and 100 gallon-per-day through any one steam generator.''
The proposed ITS LCO 3.4.1.3 eliminates the limit of 1 gpm total
primary-to-secondary leakage through all steam generators and thus will
only require a limit of 100 gallon per day through any one steam
generator. This is an administrative change.
5. Current TS SR 4.5.2.f.2 requires verifying at least once per
Refueling Interval, during shutdown, that the high-pressure safety
injection pump and low-pressure safety injection pump (LPSI) start
automatically upon receipt of a safety injection actuation test signal.
Proposed ITS SR 3.5.2.6 retains this same requirement with a specified
frequency of 24 months, which is equivalent to the refueling interval.
The proposed ITS will add a new SR 3.5.2.7 which requires verification
that each LPSI pump stops on an actual or simulated actuation signal.
This a more restrictive change.
6. The proposed amendment regarding the control room emergency
ventilation system (CREVS) changes the surveillance from 18 months to
24 months (each refueling cycle) for the following SR. Current TS SR
4.7.6.1.e.2 requires that each train of CREVS is demonstrated operable
at least once every 18 months by verifying that on a control room high
radiation test signal, the system automatically switches into a
recirculation mode of operation with flow through the HEPA filters and
charcoal adsorber banks and that both of the isolation valves in each
duct and common exhaust duct, and isolation valve in the toilet exhaust
area duct, close. The above change is less restrictive.
7. The proposed amendment regarding the control room emergency
temperature system (CRETS) changes the surveillance interval from 62
days on a staggered basis (one train every 31 days) to 24 months (each
refueling interval) for the following SR:
Current TS SR 4.7.6.1.a requires demonstrating that each CRETS
train is operable at least once every 62 days, on a staggered test
basis (one train every 31 days) by: (1) Deenergizing the backup
Control Room air conditioner; and (2) verifying that the emergency
Control Room air conditioners maintain the air temperature [less
than or equal to] 104 deg.F for at least 12 hours when in the
recirculation mode.
SR 4.7.6.1.a changes to ITS SR 3.7.9.1 to require demonstrating
operability of CRETS at least every 24 months by verifying each CRETS
train has the capability to maintain control room temperature within
limits. The above changes are less restrictive.
8. The proposed amendment regarding the spent fuel pool exhaust
ventilation system (SFPEVS) will change the surveillance interval from
18 months to 24 months (each refueling interval) for the following SR.
This is a less restrictive change.
Current TS SR 4.9.12.d requires demonstrating that the SFPEVS is
operable at least once per 18 months by: (1) Verifying that the
pressure drop across the combined HEPA filters and charcoal adsorber
banks are <4 inches="" water="" gauge="" while="" operating="" the="" ventilation="" system="" at="" a="" flow="" rate="" of="" 32,000="" cfm="" plus="" or="" minus="" 10%;="" and="" (2)="" verifying="" that="" each="" exhaust="" fan="" maintains="" the="" spent="" fuel="" storage="" pool="" at="" a="" measurable="" negative="" pressure="" relative="" to="" the="" outside="" atmosphere="" during="" system="" operation.="" sr="" 4.9.12.d="" will="" change="" to="" its="" sr="" 3.7.11.3="" to="" require="" demonstrating="" that="" the="" sfpevs="" is="" operable="" at="" least="" once="" per="" 24="" months="" by="" verifying="" that="" each="" exhaust="" fan="" maintains="" the="" spent="" fuel="" pool="" at="" a="" measurable="" negative="" pressure="" relative="" to="" the="" outside="" atmosphere="" during="" system="" operation.="" 9.="" the="" proposed="" amendment="" regarding="" the="" penetration="" room="" exhaust="" ventilation="" system="" (prevs)="" changes="" the="" surveillance="" interval="" from="" 18="" months="" to="" 24="" months="" (each="" refueling="" interval="" for="" the="" following="" sr:="" current="" ts="" sr="" 4.6.6.1.d.2="" requires="" demonstrating="" that="" each="" prevs="" train="" is="" operable="" at="" least="" once="" per="" 18="" months="" by="" verifying="" that="" the="" filter="" train="" starts="" on="" a="" containment="" isolation="" test="" signal.="" sr="" 4.6.6.1.d.2="" changes="" to="" its="" sr="" 3.7.12.3="" to="" require="" demonstrating="" operability="" of="" the="" prevs="" at="" least="" once="" every="" 24="" months="" by="" verifying="" each="" prevs="" train="" starts="" on="" an="" actual="" or="" simulated="" actuation="" signal.="" the="" above="" change="" is="" less="" restrictive.="" before="" issuance="" of="" the="" proposed="" license="" amendment,="" the="" commission="" will="" have="" made="" findings="" required="" by="" the="" atomic="" energy="" act="" of="" 1954,="" as="" amended="" (the="" act)="" and="" the="" commission's="" regulations.="" the="" commission="" has="" made="" a="" proposed="" determination="" that="" the="" amendment="" request="" involves="" no="" significant="" hazards="" consideration.="" under="" the="" commission's="" regulations="" in="" 10="" cfr="" 50.92,="" this="" means="" that="" operation="" of="" the="" facility="" in="" accordance="" with="" the="" proposed="" amendment="" would="" not="" (1)="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated;="" or="" (2)="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated;="" or="" (3)="" involve="" a="" significant="" reduction="" in="" a="" margin="" of="" safety.="" as="" required="" by="" 10="" cfr="" 50.91(a),="" the="" licensee="" has="" provided="" its="" analysis="" of="" the="" issue="" of="" no="" significant="" hazards="" consideration,="" which="" is="" presented="" below.="" basis="" for="" proposed="" no="" significant="" hazards="" determination:="" as="" required="" by="" 10="" cfr="" 50.91(a),="" the="" licensee="" has="" provided="" its="" analysis="" of="" the="" issue="" of="" no="" [[page="" 11314]]="" significant="" hazards="" consideration="" which="" is="" presented="" below="" for="" the="" above="" items.="" item="" 1="" and="" item="" 5--more="" restrictive="" changes="" 1.="" does="" the="" change="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated?="" the="" proposed="" changes="" provide="" more="" stringent="" requirements="" than="" previously="" existed="" in="" the="" technical="" specifications.="" each="" change="" was="" evaluated="" and="" it="" was="" determined="" that="" these="" more="" stringent="" requirements="" do="" not="" result="" in="" operation="" that="" will="" increase="" the="" probability="" of="" initiating="" an="" analyzed="" event.="" if="" anything,="" the="" new="" requirements="" may="" decrease="" the="" probability="" or="" consequences="" of="" an="" analyzed="" event="" by="" incorporating="" the="" more="" restrictive="" changes="" discussed="" above.="" the="" proposed="" changes="" do="" not="" alter="" assumptions="" relative="" to="" mitigation="" of="" an="" accident="" or="" transient.="" the="" more="" restrictive="" requirements="" continue="" to="" ensure="" process="" variables,="" structures,="" systems,="" and="" components="" are="" maintained="" consistent="" with="" the="" safety="" analyses="" and="" licensing="" basis.="" the="" proposed="" changes="" do="" not="" significantly="" affect="" initiators="" or="" mitigation="" of="" analyzed="" events,="" and="" therefore="" do="" not="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated.="" 2.="" does="" the="" change="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated?="" the="" proposed="" changes="" provide="" more="" stringent="" requirements="" than="" previously="" existed="" in="" the="" technical="" specifications.="" the="" changes="" will="" not="" involve="" a="" significant="" change="" in="" design="" or="" operation="" of="" the="" plant.="" no="" hardware="" is="" being="" added="" to="" the="" plant="" as="" part="" of="" the="" proposed="" changes.="" the="" proposed="" changes="" will="" not="" introduce="" any="" new="" accident="" initiators.="" the="" changes="" do="" impose="" different="" requirements.="" however,="" these="" changes="" are="" consistent="" with="" the="" assumptions="" in="" the="" safety="" analyses="" and="" licensing="" basis.="" therefore,="" the="" changes="" do="" not="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated.="" 3.="" does="" this="" change="" involve="" a="" significant="" reduction="" in="" margin="" of="" safety?="" the="" proposed="" changes="" provide="" more="" stringent="" requirements="" than="" previously="" existed="" in="" the="" technical="" specifications.="" an="" evaluation="" of="" these="" changes="" concluded="" that="" adding="" these="" more="" restrictive="" requirements="" either="" increases="" or="" has="" no="" impact="" on="" the="" margin="" of="" safety.="" the="" changes="" provide="" additional="" restrictions="" which="" may="" enhance="" plant="" safety.="" the="" changes="" maintain="" requirements="" within="" the="" safety="" analyses="" and="" licensing="" basis.="" as="" such,="" no="" question="" of="" safety="" is="" involved.="" therefore,="" the="" changes="" do="" not="" involve="" a="" significant="" reduction="" in="" a="" margin="" of="" safety.="" item="" 2--less="" restrictive="" changes="" 1.="" does="" the="" change="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated?="" the="" proposed="" change="" deletes="" the="" mode="" 3="" with="" any="" cold="" leg="" temperature="" [less="" than="" or="" equal="" to]="" 365="" deg.f="" ([less="" than="" or="" equal="" to]="" 301="" deg.f="" for="" unit="" 2)="" and="" the="" mode="" 4="" and="" 5="" applicabilities="" from="" the="" modes="" of="" applicability="" for="" the="" pressurizer="" safety="" valves.="" the="" pressurizer="" safety="" valves="" are="" not="" initiators="" of="" any="" analyzed="" event.="" the="" pressurizer="" safety="" valves="" are="" not="" required="" to="" mitigate="" any="" accidents="" in="" mode="" 3="" with="" cold="" leg="" temperature="" [less="" than="" or="" equal="" to]="" 365="" deg.f="" ([less="" than="" or="" equal="" to]="" 301="" deg.f="" for="" unit="" 2),="" or="" in="" modes="" 4="" or="" 5.="" in="" mode="" 3="" with="" any="" cold="" leg="" temperature="" [less="" than="" or="" equal="" to]="" 365="" deg.f="" ([less="" than="" or="" equal="" to]="" 301="" deg.f="" for="" unit="" 2)="" overpressure="" protection="" is="" provided="" by="" the="" low="" temperature="" overpressure="" protection="" (ltop)="" system.="" the="" change="" will="" not="" alter="" assumptions="" relative="" to="" the="" mitigation="" of="" an="" accident="" or="" transient.="" the="" proposed="" changes="" do="" not="" significantly="" affect="" initiators="" or="" mitigation="" of="" analyzed="" events,="" and="" therefore="" do="" not="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated.="" 2.="" does="" the="" change="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" previously="" evaluated?="" the="" proposed="" change="" deletes="" the="" mode="" 3="" with="" any="" cold="" leg="" temperature="" [less="" than="" or="" equal="" to]="" 365="" deg.f="" ([less="" than="" or="" equal="" to]="" 301="" deg.f="" for="" unit="" 2),="" and="" the="" mode="" 4="" and="" 5="" applicabilities="" from="" the="" modes="" of="" applicability="" for="" the="" pressurizer="" safety="" valves.="" the="" change="" will="" not="" involve="" a="" significant="" change="" in="" design="" or="" operation="" of="" the="" plant.="" no="" hardware="" is="" being="" added="" to="" the="" plant="" as="" part="" of="" the="" proposed="" change.="" the="" proposed="" change="" will="" not="" introduce="" any="" new="" accident="" initiators.="" therefore,="" the="" change="" does="" not="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated.="" 3.="" does="" this="" change="" involve="" a="" significant="" reduction="" in="" margin="" of="" safety?="" the="" proposed="" change="" deletes="" the="" mode="" 3="" with="" any="" cold="" leg="" temperature="" [less="" than="" or="" equal="" to]="" 365="" deg.f="" ([less="" than="" or="" equal="" to]="" 301="" deg.f="" for="" unit="" 2),="" and="" mode="" 4="" and="" 5="" applicabilities="" from="" the="" modes="" of="" applicability="" for="" the="" pressurizer="" safety="" valves.="" the="" pressurizer="" safety="" valves="" are="" not="" required="" for="" overpressure="" protection="" in="" mode="" 3="" with="" any="" cold="" leg="" temperature="" [less="" than="" or="" equal="" to]="" 365="" deg.f="" ([less="" than="" or="" equal="" to]="" 301="" deg.f="" for="" unit="" 2),="" or="" in="" modes="" 4="" or="" 5.="" the="" overpressure="" protection="" in="" these="" modes="" are="" provided="" by="" the="" ltop="" system.="" therefore,="" the="" change="" does="" not="" involve="" a="" significant="" reduction="" in="" a="" margin="" of="" safety.="" item="" 3--less="" restrictive="" change="" 1.="" does="" the="" change="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated?="" the="" proposed="" change="" decreases="" the="" surveillance="" frequency="" for="" the="" porv="" special="" test="" exception="" from="" 31="" days="" to="" 92="" days.="" decreasing="" the="" porv="" special="" test="" exception="" frequency="" to="" 92="" days="" is="" not="" an="" initiator="" of="" any="" analyzed="" event.="" the="" porv="" shares="" the="" same="" instrumentation="" as="" the="" reactor="" protective="" system="" pressurizer="" high="" function,="" which="" was="" approved="" for="" quarterly="" channel="" functional="" testing="" in="" an="" nrc="" safety="" evaluation="" report,="" dated="" august="" 24,="" 1994.="" a="" plant-specific="" setpoint="" drift="" analysis="" demonstrated="" that="" the="" observed="" changes="" in="" instrument="" uncertainties="" for="" extended="" surveillance="" test="" intervals="" do="" not="" exceed="" the="" current="" 30-day="" setpoint="" assumptions.="" this="" provides="" confidence="" the="" 90-92="" day="" test="" interval="" will="" not="" impact="" the="" ability="" of="" the="" porv="" to="" perform="" its="" safety="" function.="" the="" change="" will="" not="" significantly="" alter="" assumptions="" relative="" to="" the="" mitigation="" of="" an="" accident="" or="" transient.="" the="" proposed="" changes="" do="" not="" significantly="" affect="" initiators="" or="" mitigation="" of="" analyzed="" events,="" and="" therefore="" do="" not="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated.="" 2.="" does="" the="" change="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" previously="" evaluated?="" the="" proposed="" change="" decreases="" the="" surveillance="" frequency="" for="" the="" porv="" channel="" functional="" test="" from="" 31="" days="" to="" 92="" days.="" the="" change="" will="" not="" involve="" a="" significant="" change="" in="" design="" or="" operation="" of="" the="" plant.="" no="" hardware="" is="" being="" added="" to="" the="" plant="" as="" part="" of="" the="" proposed="" change.="" the="" proposed="" change="" will="" not="" introduce="" any="" new="" accident="" initiators.="" therefore,="" the="" change="" does="" not="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated.="" 3.="" does="" this="" change="" involve="" a="" significant="" reduction="" in="" margin="" of="" safety?="" the="" proposed="" change="" decreases="" the="" surveillance="" frequency="" for="" the="" porv="" channel="" functional="" test="" from="" 31="" days="" to="" 92="" days.="" the="" porv="" shares="" the="" same="" instrumentation="" as="" the="" reactor="" protective="" system="" pressurizer="" pressure="" high="" function,="" which="" was="" approved="" for="" quarterly="" channel="" functional="" testing="" in="" an="" nrc="" safety="" evaluation="" report,="" dated="" august="" 24,="" 1994.="" this="" change="" makes="" the="" testing="" frequency="" for="" the="" porv="" consistent="" with="" the="" reactor="" protective="" system="" high="" pressurizer="" function,="" which="" shares="" the="" same="" instrumentation.="" the="" core="" melt="" frequency="" remains="" unchanged.="" also,="" the="" instrument="" drift="" resulting="" from="" the="" proposed="" surveillance="" interval="" is="" less="" than="" the="" instrument="" drift="" presently="" assumed="" for="" the="" current="" surveillance="" interval.="" therefore,="" the="" change="" does="" not="" involve="" a="" significant="" reduction="" in="" a="" margin="" of="" safety.="" item="" 4--administrative="" change="" 1.="" does="" the="" change="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated?="" the="" proposed="" changes="" involve="" reformatting,="" renumbering,="" and="" rewording="" of="" the="" existing="" technical="" specifications,="" along="" with="" the="" incorporation="" of="" current="" plant="" practices="" and="" other="" changes,="" as="" discussed="" above,="" in="" order="" to="" be="" consistent="" with="" nureg-1432.="" these="" changes="" involve="" no="" technical="" changes="" to="" the="" existing="" technical="" specifications.="" specifically,="" there="" will="" be="" no="" change="" in="" the="" requirements="" imposed="" on="" calvert="" cliffs="" due="" to="" these="" changes.="" thus,="" the="" changes="" are="" administrative="" in="" nature="" and="" do="" not="" impact="" initiators="" of="" analyzed="" events.="" the="" proposed="" changes="" do="" not="" significantly="" affect="" initiators="" or="" mitigation="" of="" analyzed="" events,="" and="" therefore="" do="" not="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated.="" 2.="" does="" the="" change="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated?="" the="" proposed="" changes="" involve="" reformatting,="" renumbering,="" and="" rewording="" of="" the="" existing="" technical="" specifications,="" along="" with="" the="" incorporation="" of="" current="" plant="" [[page="" 11315]]="" practices="" and="" other="" changes,="" as="" discussed="" above,="" in="" order="" to="" be="" consistent="" with="" nureg-1432.="" the="" changes="" will="" not="" involve="" a="" significant="" change="" in="" design="" or="" operation="" of="" the="" plant.="" no="" hardware="" is="" being="" added="" to="" the="" plant="" as="" part="" of="" the="" proposed="" change.="" the="" proposed="" changes="" will="" not="" introduce="" any="" new="" accident="" initiators.="" therefore,="" the="" changes="" do="" not="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated.="" 3.="" does="" this="" change="" involve="" a="" significant="" reduction="" in="" margin="" of="" safety?="" the="" proposed="" changes="" involve="" reformatting,="" renumbering,="" and="" rewording="" of="" the="" existing="" technical="" specifications,="" along="" with="" the="" incorporation="" of="" current="" plant="" practices="" and="" other="" changes,="" as="" discussed="" above,="" in="" order="" to="" be="" consistent="" with="" nureg-1432.="" the="" changes="" are="" administrative="" in="" nature="" and="" will="" not="" involve="" any="" technical="" changes.="" the="" changes="" will="" not="" reduce="" a="" margin="" of="" safety="" because="" it="" has="" no="" impact="" on="" any="" safety="" analysis="" assumptions.="" therefore,="" the="" changes="" do="" not="" involve="" a="" significant="" reduction="" in="" a="" margin="" of="" safety.="" item="" 6--less="" restrictive="" changes="" 1.="" does="" the="" change="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated?="" the="" proposed="" change="" decreases="" the="" surveillance="" frequency="" from="" 18="" to="" 24="" months="" for="" verifying="" that="" the="" control="" room="" emergency="" ventilation="" system="" (crevs)="" will="" actuate="" on="" an="" actual="" or="" simulated="" actuation="" signal.="" the="" crevs="" is="" not="" an="" initiator="" to="" any="" accident="" previously="" evaluated="" so="" there="" is="" no="" change="" in="" the="" probability="" of="" an="" accident.="" the="" 24-month="" test="" frequency="" is="" sufficient="" to="" verify="" that="" the="" equipment="" will="" actuate="" if="" needed,="" so="" the="" equipment="" will="" continue="" to="" be="" able="" to="" mitigate="" the="" consequences="" of="" accidents="" previously="" evaluated.="" therefore,="" this="" change="" will="" not="" involve="" an="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated.="" 2.="" does="" the="" change="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated?="" the="" proposed="" change="" decreases="" the="" surveillance="" frequency="" from="" 18="" to="" 24="" months="" for="" verifying="" that="" the="" crevs="" will="" actuate="" on="" an="" actual="" or="" simulated="" actuation="" signal.="" this="" change="" will="" not="" physically="" alter="" the="" plant="" (no="" new="" or="" different="" types="" of="" equipment="" will="" be="" installed).="" the="" change="" does="" not="" require="" any="" new="" or="" unusual="" operator="" actions.="" therefore,="" the="" change="" does="" not="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated.="" 3.="" does="" the="" change="" involve="" a="" significant="" reduction="" in="" a="" margin="" of="" safety?="" the="" proposed="" change="" decreased="" the="" surveillance="" frequency="" from="" 18="" to="" 24="" months="" for="" verifying="" that="" the="" crevs="" will="" actuate="" on="" an="" actual="" or="" simulated="" actuation="" signal.="" a="" review="" of="" previously="" performed="" surveillances="" determined="" that="" no="" failures="" have="" been="" found="" during="" the="" performance="" of="" this="" sr="" once="" per="" 18="" months.="" given="" the="" performance="" history,="" there="" is="" no="" reason="" to="" believe="" that="" a="" frequency="" of="" 24="" months="" would="" result="" in="" reduced="" reliability="" of="" the="" system.="" therefore,="" this="" change="" does="" not="" involve="" a="" significant="" reduction="" in="" the="" margin="" of="" safety.="" item="" 7--less="" restrictive="" change="" 1.="" does="" the="" change="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated?="" the="" proposed="" change="" will="" decrease="" the="" frequency="" from="" 62="" days="" on="" a="" staggered="" test="" basis="" (one="" train="" every="" 31="" days)="" to="" 24="" months="" for="" verifying="" that="" the="" crets="" can="" maintain="" temperature="" in="" the="" control="" room="" at="" [less="" than="" or="" equal="" to]="" 104="" deg.f.="" this="" change="" will="" not="" significantly="" increase="" the="" possibility="" of="" an="" accident="" previously="" evaluated.="" the="" crets="" is="" not="" an="" initiator="" of="" any="" analyzed="" event.="" this="" change="" will="" not="" significantly="" increase="" the="" consequences="" of="" an="" accident.="" the="" crets="" will="" still="" be="" tested="" at="" a="" frequency="" that="" will="" show="" it="" can="" maintain="" control="" room="" temperature.="" review="" of="" the="" past="" 10="" years="" of="" data="" has="" shown="" that="" during="" this="" period="" the="" test="" has="" never="" failed.="" this="" change="" will="" not="" significantly="" affect="" the="" assumptions="" relative="" to="" the="" mitigation="" of="" accidents="" or="" transients.="" therefore,="" the="" change="" does="" not="" involve="" a="" significant="" increase="" in="" the="" probability="" of="" consequence="" of="" an="" accident="" previously="" evaluated.="" 2.="" does="" the="" change="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated?="" the="" proposed="" change="" will="" decrease="" the="" frequency="" from="" 62="" days="" on="" a="" staggered="" test="" basis="" (one="" train="" every="" 31="" days)="" to="" 24="" months="" for="" verifying="" that="" the="" crets="" can="" maintain="" temperature="" in="" the="" control="" room="" at="" [less="" than="" or="" equal="" to]="" 104="" deg.f.="" this="" change="" does="" not="" involve="" a="" significant="" change="" in="" the="" design="" or="" operation="" of="" the="" plant.="" no="" hardware="" is="" being="" added="" to="" the="" plant="" as="" part="" of="" the="" proposed="" change.="" the="" proposed="" change="" will="" not="" introduce="" any="" new="" accident="" initiators.="" therefore,="" the="" change="" does="" not="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated.="" 3.="" does="" the="" change="" involve="" a="" significant="" reduction="" in="" a="" margin="" of="" safety?="" the="" proposed="" change="" will="" decrease="" the="" frequency="" from="" 62="" days="" on="" a="" staggered="" test="" basis="" (one="" train="" every="" 31="" days)="" to="" 24="" months="" for="" verifying="" that="" the="" crets="" can="" maintain="" temperature="" in="" the="" control="" room="" at="" [less="" than="" or="" equal="" to]="" 104="" deg.f.="" the="" margin="" of="" safety="" is="" not="" significantly="" affected="" by="" this="" change.="" the="" surveillance="" will="" still="" be="" performed="" at="" an="" interval="" which="" will="" prove="" the="" crets="" remains="" operable="" based="" on="" an="" evaluation="" of="" past="" surveillance="" history.="" also,="" increasing="" the="" surveillance="" interval="" will="" prevent="" inadvertent="" wear="" and="" tear="" on="" the="" system="" due="" to="" over="" testing,="" which="" can="" possibly="" lead="" to="" premature="" failures.="" therefore,="" the="" proposed="" change="" does="" not="" involve="" a="" significant="" reduction="" in="" a="" margin="" of="" safety.="" item="" 8--less="" restrictive="" change="" 1.="" does="" the="" change="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated?="" the="" proposed="" change="" decreases="" the="" surveillance="" frequency="" from="" 18="" months="" to="" 24="" months="" for="" verifying="" that="" the="" sfpevs="" can="" maintain="" a="" measurable="" negative="" pressure="" in="" the="" spent="" fuel="" pool="" area="" of="" the="" auxiliary="" building.="" this="" change="" will="" not="" affect="" the="" probability="" of="" an="" accident.="" the="" sfpevs="" is="" not="" an="" initiator="" of="" any="" analyzed="" event.="" the="" change="" will="" not="" affect="" the="" consequences="" of="" an="" accident.="" the="" 24-="" month="" frequency="" is="" sufficient="" to="" ensure="" that="" the="" sfpevs="" can="" maintain="" a="" measurable="" negative="" pressure="" in="" the="" spent="" fuel="" pool="" area.="" the="" change="" will="" not="" alter="" assumptions="" relative="" to="" the="" mitigation="" of="" an="" accident="" or="" transient.="" therefore,="" the="" change="" will="" not="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequence="" of="" an="" accident="" previously="" evaluated.="" 2.="" does="" the="" change="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated?="" the="" proposed="" change="" decreases="" the="" surveillance="" frequency="" from="" 18="" months="" to="" 24="" months="" for="" verifying="" that="" the="" sfpevs="" can="" maintain="" a="" measurable="" negative="" pressure="" in="" the="" spent="" fuel="" pool="" area="" of="" the="" auxiliary="" building.="" this="" change="" will="" not="" physically="" alter="" the="" plant="" (no="" new="" or="" different="" type="" of="" equipment="" will="" be="" installed).="" the="" change="" does="" not="" require="" any="" new="" or="" unusual="" operator="" actions.="" therefore,="" the="" change="" does="" not="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated.="" 3.="" does="" the="" change="" involve="" a="" significant="" reduction="" in="" a="" margin="" of="" safety?="" the="" proposed="" change="" decreases="" the="" surveillance="" frequency="" from="" 18="" to="" 24="" months="" for="" verifying="" that="" the="" sfpevs="" can="" maintain="" a="" measurable="" negative="" pressure="" in="" the="" spent="" fuel="" pool="" area="" of="" the="" auxiliary="" building.="" the="" margin="" of="" safety="" is="" not="" significantly="" affected="" by="" this="" change.="" the="" failure="" history="" for="" this="" sr="" has="" shown="" that="" no="" failures="" have="" occurred="" in="" the="" previous="" ten="" years.="" the="" proposed="" frequency="" will="" continue="" to="" prove="" that="" the="" sfpevs="" will="" maintain="" a="" negative="" pressure="" in="" the="" spent="" fuel="" pool="" area.="" therefore,="" the="" change="" does="" not="" involve="" a="" significant="" reduction="" in="" a="" margin="" of="" safety.="" item="" 9--less="" restrictive="" change="" 1.="" does="" the="" change="" involve="" a="" significant="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated?="" the="" proposed="" change="" decreases="" the="" surveillance="" frequency="" from="" 18="" to="" 24="" months="" for="" verifying="" that="" the="" penetration="" room="" emergency="" ventilation="" system="" (prevs)="" will="" actuate="" on="" an="" actual="" or="" simulated="" actuation="" signal.="" the="" prevs="" is="" not="" an="" initiator="" to="" any="" accident="" previously="" evaluated="" so="" there="" is="" no="" change="" in="" the="" probability="" of="" an="" accident.="" the="" 24-month="" test="" frequency="" is="" sufficient="" to="" verify="" that="" the="" equipment="" will="" actuate="" if="" needed="" so="" the="" equipment="" will="" continue="" to="" be="" able="" to="" mitigate="" the="" consequences="" of="" accidents="" previously="" evaluated.="" therefore,="" this="" change="" will="" not="" involve="" an="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated.="" 2.="" does="" the="" change="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated?="" the="" proposed="" change="" decreases="" the="" surveillance="" frequency="" from="" 18="" to="" 24="" months="" for="" verifying="" that="" the="" prevs="" will="" actuate="" on="" an="" actual="" or="" simulated="" actuation="" signal.="" this="" change="" will="" not="" physically="" alter="" the="" plant="" (no="" new="" or="" different="" types="" of="" equipment="" will="" be="" installed).="" the="" change="" does="" not="" require="" any="" new="" or="" unusual="" operator="" actions.="" therefore,="" this="" change="" does="" not="" create="" the="" possibility="" of="" a="" new="" or="" different="" kind="" of="" accident="" from="" any="" accident="" previously="" evaluated.="" [[page="" 11316]]="" 3.="" does="" the="" change="" involve="" a="" significant="" reduction="" in="" a="" margin="" of="" safety?="" the="" proposed="" change="" decreases="" the="" surveillance="" frequency="" from="" 18="" to="" 24="" months="" for="" verifying="" that="" the="" prevs="" will="" actuate="" on="" an="" actual="" or="" simulated="" actuation="" signal.="" a="" review="" of="" previously="" performed="" surveillances="" determined="" that="" no="" failures="" have="" been="" found="" during="" the="" performance="" of="" this="" sr="" once="" per="" 18="" months.="" given="" the="" performance="" history,="" there="" is="" no="" reason="" to="" believe="" that="" a="" frequency="" of="" 24="" months="" would="" result="" in="" reduced="" reliability="" of="" the="" system.="" therefore,="" this="" change="" will="" not="" involve="" an="" increase="" in="" the="" probability="" or="" consequences="" of="" an="" accident="" previously="" evaluated.="" the="" nrc="" staff="" has="" reviewed="" the="" licensee's="" analyses="" and,="" based="" on="" this="" review,="" it="" appears="" that="" the="" three="" standards="" of="" 10="" cfr="" 50.92(c)="" are="" satisfied.="" therefore,="" the="" nrc="" staff="" proposes="" to="" determine="" that="" the="" amendment="" request="" involves="" no="" significant="" hazards="" consideration,="" regarding="" the="" matters="" discussed="" above.="" the="" commission="" is="" seeking="" public="" comments="" on="" this="" proposed="" determination.="" any="" comments="" received="" within="" 30="" days="" after="" the="" date="" of="" publication="" of="" this="" notice="" will="" be="" considered="" in="" making="" any="" final="" determination.="" normally,="" the="" commission="" will="" not="" issue="" the="" amendment="" until="" the="" expiration="" of="" the="" 30-day="" notice="" period.="" however,="" should="" circumstances="" change="" during="" the="" notice="" period="" such="" that="" failure="" to="" act="" in="" a="" timely="" way="" would="" result,="" for="" example,="" in="" derating="" or="" shutdown="" of="" the="" facility,="" the="" commission="" may="" issue="" the="" license="" amendment="" before="" the="" expiration="" of="" the="" 30-day="" notice="" period,="" provided="" that="" its="" final="" determination="" is="" that="" the="" amendment="" involves="" no="" significant="" hazards="" consideration.="" the="" final="" determination="" will="" consider="" all="" public="" and="" state="" comments="" received.="" should="" the="" commission="" take="" this="" action,="" it="" will="" publish="" in="" the="" federal="" register="" a="" notice="" of="" issuance="" and="" provide="" for="" opportunity="" for="" a="" hearing="" after="" issuance.="" the="" commission="" expects="" that="" the="" need="" to="" take="" this="" action="" will="" occur="" very="" infrequently.="" written="" comments="" may="" be="" submitted="" by="" mail="" to="" the="" chief,="" rules="" and="" directives="" branch,="" division="" of="" administrative="" services,="" office="" of="" administration,="" u.s.="" nuclear="" regulatory="" commission,="" washington,="" dc="" 20555-0001,="" and="" should="" cite="" the="" publication="" date="" and="" page="" number="" of="" this="" federal="" register="" notice.="" written="" comments="" may="" also="" be="" delivered="" to="" room="" 6d59,="" two="" white="" flint="" north,="" 11545="" rockville="" pike,="" rockville,="" maryland,="" from="" 7:30="" a.m.="" to="" 4:15="" p.m.="" federal="" workdays.="" copies="" of="" written="" comments="" received="" may="" be="" examined="" at="" the="" nrc="" public="" document="" room,="" the="" gelman="" building,="" 2120="" l="" street,="" nw.,="" washington,="" dc.="" the="" filing="" of="" requests="" for="" hearing="" and="" petitions="" for="" leave="" to="" intervene="" is="" discussed="" below.="" by="" april="" 6,="" 1998,="" the="" licensee="" may="" file="" a="" request="" for="" a="" hearing="" with="" respect="" to="" issuance="" of="" the="" amendment="" to="" the="" subject="" facility="" operating="" license="" and="" any="" person="" whose="" interest="" may="" be="" affected="" by="" this="" proceeding="" and="" who="" wishes="" to="" participate="" as="" a="" party="" in="" the="" proceeding="" must="" file="" a="" written="" request="" for="" a="" hearing="" and="" a="" petition="" for="" leave="" to="" intervene.="" requests="" for="" a="" hearing="" and="" a="" petition="" for="" leave="" to="" intervene="" shall="" be="" filed="" in="" accordance="" with="" the="" commission's="" ``rules="" of="" practice="" for="" domestic="" licensing="" proceedings''="" in="" 10="" cfr="" part="" 2.="" interested="" persons="" should="" consult="" a="" current="" copy="" of="" 10="" cfr="" 2.714="" which="" is="" available="" at="" the="" commission's="" public="" document="" room,="" the="" gelman="" building,="" 2120="" l="" street,="" nw.,="" washington,="" dc,="" and="" at="" the="" local="" public="" document="" room="" located="" at="" the="" calvert="" county="" library,="" prince="" frederick,="" maryland="" 20678.="" if="" a="" request="" for="" a="" hearing="" or="" petition="" for="" leave="" to="" intervene="" is="" filed="" by="" the="" above="" date,="" the="" commission="" or="" an="" atomic="" safety="" and="" licensing="" board,="" designated="" by="" the="" commission="" or="" by="" the="" chairman="" of="" the="" atomic="" safety="" and="" licensing="" board="" panel,="" will="" rule="" on="" the="" request="" and/or="" petition;="" and="" the="" secretary="" or="" the="" designated="" atomic="" safety="" and="" licensing="" board="" will="" issue="" a="" notice="" of="" hearing="" or="" an="" appropriate="" order.="" as="" required="" by="" 10="" cfr="" 2.714,="" a="" petition="" for="" leave="" to="" intervene="" shall="" set="" forth="" with="" particularity="" the="" interest="" of="" the="" petitioner="" in="" the="" proceeding,="" and="" how="" that="" interest="" may="" be="" affected="" by="" the="" results="" of="" the="" proceeding.="" the="" petition="" should="" specifically="" explain="" the="" reasons="" why="" intervention="" should="" be="" permitted="" with="" particular="" reference="" to="" the="" following="" factors:="" (1)="" the="" nature="" of="" the="" petitioner's="" right="" under="" the="" act="" to="" be="" made="" party="" to="" the="" proceeding;="" (2)="" the="" nature="" and="" extent="" of="" the="" petitioner's="" property,="" financial,="" or="" other="" interest="" in="" the="" proceeding;="" and="" (3)="" the="" possible="" effect="" of="" any="" order="" which="" may="" be="" entered="" in="" the="" proceeding="" on="" the="" petitioner's="" interest.="" the="" petition="" should="" also="" identify="" the="" specific="" aspect(s)="" of="" the="" subject="" matter="" of="" the="" proceeding="" as="" to="" which="" petitioner="" wishes="" to="" intervene.="" any="" person="" who="" has="" filed="" a="" petition="" for="" leave="" to="" intervene="" or="" who="" has="" been="" admitted="" as="" a="" party="" may="" amend="" the="" petition="" without="" requesting="" leave="" of="" the="" board="" up="" to="" 15="" days="" prior="" to="" the="" first="" prehearing="" conference="" scheduled="" in="" the="" proceeding,="" but="" such="" an="" amended="" petition="" must="" satisfy="" the="" specificity="" requirements="" described="" above.="" not="" later="" than="" 15="" days="" prior="" to="" the="" first="" prehearing="" conference="" scheduled="" in="" the="" proceeding,="" a="" petitioner="" shall="" file="" a="" supplement="" to="" the="" petition="" to="" intervene="" which="" must="" include="" a="" list="" of="" the="" contentions="" which="" are="" sought="" to="" be="" litigated="" in="" the="" matter.="" each="" contention="" must="" consist="" of="" a="" specific="" statement="" of="" the="" issue="" of="" law="" or="" fact="" to="" be="" raised="" or="" controverted.="" in="" addition,="" the="" petitioner="" shall="" provide="" a="" brief="" explanation="" of="" the="" bases="" of="" the="" contention="" and="" a="" concise="" statement="" of="" the="" alleged="" facts="" or="" expert="" opinion="" which="" support="" the="" contention="" and="" on="" which="" the="" petitioner="" intends="" to="" rely="" in="" proving="" the="" contention="" at="" the="" hearing.="" the="" petitioner="" must="" also="" provide="" references="" to="" those="" specific="" sources="" and="" documents="" of="" which="" the="" petitioner="" is="" aware="" and="" on="" which="" the="" petitioner="" intends="" to="" rely="" to="" establish="" those="" facts="" or="" expert="" opinion.="" petitioner="" must="" provide="" sufficient="" information="" to="" show="" that="" a="" genuine="" dispute="" exists="" with="" the="" applicant="" on="" a="" material="" issue="" of="" law="" or="" fact.="" contentions="" shall="" be="" limited="" to="" matters="" within="" the="" scope="" of="" the="" amendment="" under="" consideration.="" the="" contention="" must="" be="" one="" which,="" if="" proven,="" would="" entitle="" the="" petitioner="" to="" relief.="" a="" petitioner="" who="" fails="" to="" file="" such="" a="" supplement="" which="" satisfies="" these="" requirements="" with="" respect="" to="" at="" least="" one="" contention="" will="" not="" be="" permitted="" to="" participate="" as="" a="" party.="" those="" permitted="" to="" intervene="" become="" parties="" to="" the="" proceeding,="" subject="" to="" any="" limitations="" in="" the="" order="" granting="" leave="" to="" intervene,="" and="" have="" the="" opportunity="" to="" participate="" fully="" in="" the="" conduct="" of="" the="" hearing,="" including="" the="" opportunity="" to="" present="" evidence="" and="" cross-="" examine="" witnesses.="" if="" a="" hearing="" is="" requested,="" the="" commission="" will="" make="" a="" final="" determination="" on="" the="" issue="" of="" no="" significant="" hazards="" consideration.="" the="" final="" determination="" will="" serve="" to="" decide="" when="" the="" hearing="" is="" held.="" if="" the="" final="" determination="" is="" that="" the="" amendment="" request="" involves="" no="" significant="" hazards="" consideration,="" the="" commission="" may="" issue="" the="" amendment="" and="" make="" it="" immediately="" effective,="" notwithstanding="" the="" request="" for="" a="" hearing.="" any="" hearing="" held="" would="" take="" place="" after="" issuance="" of="" the="" amendment.="" if="" the="" final="" determination="" is="" that="" the="" amendment="" request="" involves="" a="" significant="" hazards="" consideration,="" any="" hearing="" held="" would="" take="" place="" before="" the="" issuance="" of="" any="" amendment.="" a="" request="" for="" a="" hearing="" or="" a="" petition="" for="" leave="" to="" intervene="" must="" be="" filed="" with="" the="" secretary="" of="" the="" commission,="" u.s.="" nuclear="" regulatory="" commission,="" washington,="" dc="" 20555-0001,="" attention:="" rulemakings="" and="" adjudications="" staff,="" or="" may="" be="" delivered="" to="" the="" commission's="" [[page="" 11317]]="" public="" document="" room,="" the="" gelman="" building,="" 2120="" l="" street,="" nw.,="" washington,="" dc,="" by="" the="" above="" date.="" a="" copy="" of="" the="" petition="" should="" also="" be="" sent="" to="" the="" office="" of="" the="" general="" counsel,="" u.s.="" nuclear="" regulatory="" commission,="" washington,="" dc="" 20555-0001,="" and="" to="" jay="" e.="" silberg,="" esquire,="" shaw,="" pittman,="" potts="" and="" trowbridge,="" 2300="" n="" street,="" nw.,="" washington,="" dc="" 20037,="" attorney="" for="" the="" licensee.="" nontimely="" filings="" of="" petitions="" for="" leave="" to="" intervene,="" amended="" petitions,="" supplemental="" petitions="" and/or="" requests="" for="" hearing="" will="" not="" be="" entertained="" absent="" a="" determination="" by="" the="" commission,="" the="" presiding="" officer="" or="" the="" presiding="" atomic="" safety="" and="" licensing="" board="" that="" the="" petition="" and/or="" request="" should="" be="" granted="" based="" upon="" a="" balancing="" of="" the="" factors="" specified="" in="" 10="" cfr="" 2.714(a)(1)(i)-(v)="" and="" 2.714(d).="" for="" further="" details="" with="" respect="" to="" this="" action,="" see="" the="" application="" for="" amendment="" dated="" december="" 4,="" 1996,="" as="" supplemented="" march="" 27,="" june="" 9,="" june="" 18,="" july="" 21,="" august="" 14,="" august="" 19,="" september="" 10,="" october="" 6,="" october="" 20,="" october="" 23,="" november="" 5,="" 1997,="" and="" january="" 12="" and="" january="" 28,="" 1998,="" which="" is="" available="" for="" public="" inspection="" at="" the="" commission's="" public="" document="" room,="" the="" gelman="" building,="" 2120="" l="" street,="" nw.,="" washington,="" dc,="" and="" at="" the="" local="" public="" document="" room="" located="" at="" the="" calvert="" county="" library,="" prince="" frederick,="" maryland="" 20678.="" dated="" at="" rockville,="" maryland,="" this="" 2nd="" day="" of="" march="" 1998.="" for="" the="" nuclear="" regulatory="" commission.="" alexander="" w.="" dromerick,="" senior="" project="" manager,="" project="" directorate="" i-1,="" division="" of="" reactor="" projects--i/ii,="" office="" of="" nuclear="" reactor="" regulation.="" [fr="" doc.="" 98-5809="" filed="" 3-5-98;="" 8:45="" am]="" billing="" code="" 7590-01-p="">4>