94-5142. Boulder Canyon Project Notice of Rate Order No. WAPA-58-1

  • [Federal Register Volume 59, Number 44 (Monday, March 7, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-5142]
    
    
    [[Page Unknown]]
    
    [Federal Register: March 7, 1994]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    Western Area Power Administration
    
     
    
    Boulder Canyon Project Notice of Rate Order No. WAPA-58-1
    
    AGENCY: Western Area Power Administration, DOE.
    
    ACTION: Notice of rate order--Boulder Canyon Project annual power rate 
    adjustment.
    
    -----------------------------------------------------------------------
    
    SUMMARY: Notice is given of the approval by the Administrator of 
    Western Area Power Administration (Western) of Rate Order No. WAPA-58-1 
    and Rate Schedule BCP-F4/2 placing the proposed decreased power rates 
    for the Boulder Canyon Project (BCP) into effect.* The methodology 
    utilized in Rate Order WAPA-58 requires that Western modify the BCP 
    rates, either an increase or decrease, on an annual basis. These BCP 
    rates will remain in effect until they are superseded.
    ---------------------------------------------------------------------------
    
        *WAPA's Administrator has been empowered as part of DOE's 1992 
    rate filing with FERC to approve the annual rates. See, 57 FR 61076; 
    December 23, 1992 and 57 FR 62318 December 30, 1992.
    ---------------------------------------------------------------------------
    
        The proposed rates for BCP power are based on a composite rate of 
    12.62 mills per kilowatthour (mills/kWh). The composite rate consists 
    of an energy charge of 6.31 mills/kWh and a capacity charge of $1.07 
    per kilowatt per month ($/kW/month).
        The Assistant Secretary, Conservation and Renewable Energy, United 
    States Department of Energy, approved the existing BCP rate methodology 
    on an interim basis, effective on January 1, 1993 [57 FR 61074; 
    December 23, 1992]. The Federal Energy Regulatory Commission (FERC) 
    approved the methodology for the BCP rate on a final basis by Order 
    dated November 3, 1993.
        A comparison of the existing and annual BCP rates follows: 
    
    ------------------------------------------------------------------------
                                                      Existing      Annual  
                                                     rates (FY    rates (FY 
                                                       1993)        1994)*  
    ------------------------------------------------------------------------
    Rate Schedule.................................     BCP-F4/1     BCP-F4/2
    Composite Rate (mills/kWh)....................        14.56        12.62
    Energy Rate (mills/kWh).......................         7.28         6.31
    Capacity Rate ($/kW/month)....................        $1.28       $1.07 
    ------------------------------------------------------------------------
    *The ratesetting methodology is in effect from January 1, 1993, through 
      September 30, 1997. The BCP rates will be reviewed annually.          
    
    DATES: Rate Schedule BCP-F4/2 will be placed into effect beginning on 
    February 1, 1994.
    
    FOR FURTHER INFORMATION CONTACT:
    
    Mr. J. Tyler Carlson, Acting Area Manager, Phoenix Area Office, 
    Western Area Power Administration, P.O. Box 6457, Phoenix, AZ 85005-
    6457 (602) 352-2521.
    Ms. Deborah Linke, Chief, Rates and Statistics Branch, Western Area 
    Power Administration, P.O. Box 3402, Golden, CO 80401-0098, (303) 
    275-1618.
    Mr. Joel Bladow, Assistant Administrator for Washington Liaison, 
    Western Area Power Administration, Power Marketing Liaison Office, 
    Room 8G-027, Forrestal Building, 1000 Independence Avenue SW., 
    Washington, DC 20585-0001, (202) 586-5581.
    
    SUPPLEMENTARY INFORMATION: By Amendment No. 3 to Delegation Order No. 
    0204-108, published November 10, 1993 (58 FR 59716), the Secretary of 
    Energy delegated: (1) The authority to develop long-term power and 
    transmission rates on a nonexclusive basis to the Administrator of 
    Western; (2) the authority to confirm, approve, and place power rates 
    into effect on an interim basis to the Deputy Secretary of Energy; and 
    (3) the authority to confirm, approve, and place into effect on a final 
    basis, to remand, or to disapprove power rates to FERC.
        These power rates are established pursuant to the DOE Organization 
    Act (42 U.S.C. 7101 et seq.), the Reclamation Act of 1902 (43 U.S.C. 
    372 et seq.), as amended and supplemented by subsequent enactments, 
    particularly section 9(c) of the Reclamation Project Act of 1939 (43 
    U.S.C. 485h(c)), the Colorado River Basin Project Act of 1968 (43 
    U.S.C. 1501 et seq.), the Colorado River Storage Project Act of 1956 
    (43 U.S.C. 620 et seq.), the Boulder Canyon Project Act of 1928 (43 
    U.S.C. 617 et seq.), the Boulder Canyon Project Adjustment Act of 1940 
    (43 U.S.C. 618 et seq.), the Hoover Power Plant Act of 1984 (43 U.S.C. 
    619 et seq.), the General Regulations for Power Generation, Operation, 
    Maintenance, and Replacement at the Boulder Canyon Project, Arizona/
    Nevada (43 CFR Part 431) published in the Federal Register at 51 FR 
    23960 on July 1, 1986, and the General Regulations for the Charges for 
    the Sale of Power from the Boulder Canyon Project, Final Rule (10 CFR 
    Part 904) published in the Federal Register at 51 FR 43124 on November 
    28, 1986, the procedures for public participation in rate adjustments 
    for power and transmission service marketed by Western (10 CFR Part 
    903) published in the Federal Register at 50 FR 37835 on September 18, 
    1985, and the DOE financial reporting policies, procedures, and 
    methodology (DOE Order No. RA 6120.2 dated September 20, 1979).
        During the 90-day comment period, Western received nine written 
    comments. In addition, six speakers commented during the August 31, 
    1993, public comment forum. All comments and responses are addressed in 
    the rate order.
        Rate Order No. WAPA-58-1 (Rate Schedule BCP-F4/2) approving and 
    placing the BCP proposed rates into effect is issued and approved on a 
    final basis.
    
        Issued in Golden, CO, February 4, 1994.
    William H. Clagett,
    Administrator.
    
    Order Approving and Placing the Boulder Canyon Project Power Rates 
    Into Effect
    
        In the matter of Western Area Power Administration Annual Rate 
    Adjustment for Phoenix Area Office Boulder Canyon Project.
    
    [Rate Order No. WAPA-58-1]
    
    February 4, 1994.
        Pursuant to section 302(a) of the Department of Energy (DOE) 
    Organization Act, 42 U.S.C. 7152(a), the power marketing functions of 
    the Secretary of the Interior and the Bureau of Reclamation under the 
    Reclamation Act of 1902, 43 U.S.C. 372 et seq., as amended and 
    supplemented by subsequent enactments, particularly section 9(c) of the 
    Reclamation Project Act of 1939, 43 U.S.C. 485h(c), and other acts 
    specifically applicable to the projects involved, were transferred to 
    and vested in the Secretary of Energy (Secretary) acting by and through 
    the Administrator of the Western Area Power Administration (Western).
        By Amendment No. 3 to Delegation Order No. 0204-108, published 
    November 10, 1993 (58 FR 59716), the Secretary of Energy delegated: (1) 
    The authority to develop long-term power and transmission rates on a 
    nonexclusive basis to the Administrator of Western; (2) the authority 
    to confirm, approve, and place power rates into effect on an interim 
    basis to the Deputy Secretary of Energy; and (3) the authority to 
    confirm, approve, and place into effect on a final basis, to remand, or 
    to disapprove power rates to the Federal Energy Regulatory Commission. 
    Existing DOE procedures for public participation in power rate 
    adjustments (10 CFR part 903) became effective on September 18, 1985 
    (50 FR 37835).
        The ratesetting methodology used in this rate order was approved 
    and confirmed on a final basis by the Federal Energy Regulatory 
    Commission on November 3, 1993, in WAPA-58. Western is required to 
    modify the Boulder Canyon Project power rate, either an increase or a 
    decrease, on an annual basis. This ratesetting methodology uses an 
    approved rate formula, along with an annual public participation 
    process, for the Boulder Canyon Project through September 30, 1997. As 
    long as Western adheres to this rate formula and public process, as 
    outlined in WAPA-58, there is no requirement to seek additional 
    approval from the Federal Energy Regulatory Commission.
    
    Acronyms and Definitions
    
        As used in this rate order, the following acronyms and definitions 
    apply:
    
    1941 General Regulations: General Regulations for Generation and Sale 
    of Power in Accordance with the Boulder Canyon Project Adjustment Act, 
    May 20, 1941.
    1984 Act: Hoover Power Plant Act of 1984, August 17, 1984 (43 U.S.C. 
    619 et seq.).
    $/kW/month: Monthly charge for capacity (usage--$ per kilowatt per 
    month).
    Additions: A unit of property constructed or acquired which enhances or 
    improves a project or system and which is properly allocated to power 
    or the joint features allocated to power.
    Adjustment Act: Boulder Canyon Project Adjustment Act, July 19, 1940 
    (43 U.S.C. 618 et seq.).
    Annual Rate: A rate revision recommended to the Administrator of 
    Western for approval on an annual basis. The Annual Rate adjustments 
    are approved by the Administrator of Western.
    BCP: Boulder Canyon Project.
    BCP Handout: A document prepared for the public information forum.
    Capacity Rate: Shown in the PRSS as a $/kW/year charge. Billed on a $/
    kW/month basis. Applied each billing period to each kW of rated output 
    to which each contractor is entitled by contract.
    Colorado River Basin Project Act: The Colorado River Basin Project Act, 
    September 30, 1968 (43 U.S.C. 1501 et seq.).
    Colorado River Dam Fund (CRDF): A fund established by section 2 of the 
    Boulder Canyon Project Act of 1928 which is to be used only for the 
    purposes specified in the Boulder Canyon Project Adjustment Act of 
    1940, the Colorado River Basin Project Act of 1968, and the Hoover 
    Power Plant Act of 1984.
    Composite Rate: Combination of an energy rate and a capacity rate, 
    which is expressed in mills/kWh.
    Conformed Criteria: Conformed General Consolidated Power Marketing 
    Criteria or Regulations for Boulder City Area Projects (49 FR 50582, 
    December 28, 1984) beginning on June 1, 1987.
    Cost Evaluation Period (CEP): The first 5 future years in the PRSS, 
    starting with the first future year of costs and revenue estimates.
    Contractors: The Boulder Canyon Project Power customers.
    Crosswalk: A reconciliation between a project PRSS and the Western and 
    Reclamation financial statements.
    CSRS: Civil Service Retirement System.
    Current PRSS: The PRSS included in this rate order based on the 
    existing BCP rates.
    DOE: Department of Energy.
    DOE Order No. RA 6120.2: An order dealing with power marketing 
    administration financial reporting.
    E&OC: Engineering and Oversight Committee consisting of members from 
    BCP Contractors, Western, and Reclamation. Their function is to 
    establish a regular review process of Western's and Reclamation's 
    planned O&M, additions, and replacements.
    EIS: Environmental Impact Statement.
    Energy Rate: Expressed in mills per kWh. Applied to each kWh made 
    available to each Contractor.
    FY 1992 Ratebase PRSS: FY 1992 Revised PRSS.
    FERC: Federal Energy Regulatory Commission.
    FY: Fiscal year.
    Guide Service: This is service provided to the visitors for tours at 
    the Hoover Dam site.
    GWh: Gigawatthour.
    Hoover Dam: The dam on the Colorado River which forms Lake Mead.
    Hoover Rates Committee: The Hoover Power Rates Methodology Review 
    Standing Committee made up of BCP Contractors, Western, and Reclamation 
    who developed the new proposed ratesetting methodology (Settlement 
    Agreement).
    Interior: U.S. Department of the Interior.
    kW: Kilowatt.
    kW/month: The greater of (1) the highest 30-minute demand measured 
    during the month, not to exceed the contract obligation, or (2) the 
    contract rate of delivery.
    kWh: Kilowatthour.
    LCRBDF: Lower Colorado River Basin Development Fund--a fund established 
    by the Colorado River Basin Project Act of 1968.
    Master Schedule: This is an 18-month schedule of projected BCP 
    hydrology.
    mills/kWh: Mills per kilowatthour.
    Multiproject Costs: These are costs for facilities being charged to one 
    project that benefit other projects.
    MW: Megawatt.
    MWh: Megawatthour.
    NEPA: National Environmental Policy Act of 1969 (42 U.S.C. 4321 et 
    seq.).
    OMB: Office of Management and Budget.
    O&M: Operations and maintenance.
    P-DP: Parker-Davis Project.
    Project Act: The Boulder Canyon Project Act authorizing the 
    construction of Boulder Canyon Project dated December 21, 1928 (43 
    U.S.C. 617 et seq.).
    PRSS: Power Repayment Spreadsheet Study.
    Reclamation: Bureau of Reclamation, U.S. Department of the Interior.
    Reclamation's 1986 General Regulations: General Regulations for Power 
    Generation, Operation, Maintenance, and Replacement at BCP, Arizona/
    Nevada 43 CFR Part 431 (51 FR 23960, July 1, 1986).
    Replacements: A unit of property constructed or acquired as a 
    substitute for an existing unit of property for the purpose of 
    maintaining the power features of a project or the joint features 
    properly allocated to power.
    Replacement Study: The cyclical analysis of replacement service lives. 
    A high level of replacement activity for a few consecutive years will 
    reoccur in future years at a similar high level with years in between 
    tending to be at lesser level of replacement.
    Secretary: Secretary of Energy.
    Schedule A: Boulder Canyon Project Contractors that receive capacity 
    and energy. Contractors are Arizona Power Authority (APA), Boulder 
    City, Burbank, Colorado River Commission of Nevada (CRC), Glendale, Los 
    Angeles Department of Water and Power, Metropolitan Water District of 
    Southern California, Pasadena, and Southern California Edison.
    Schedule B: Boulder Canyon Project Contractors that receive Hoover 
    capacity and energy and who also advanced the funds for the Uprating 
    Program. These Contractors include Anaheim, APA, Azusa, Banning, 
    Burbank, CRC, Colton, Glendale, Pasadena, Riverside, and Vernon.
    Schedule C: Both the Schedule A and Schedule B Contractors (All 
    Contractors).
    Settlement Agreement: See Hoover Rates Committee.
    Treasury: Secretary of the Department of the Treasury.
    Uprating Contractors: Contractors who contributed to advance of funds 
    for financing the upgrading of the BCP system (see Schedule B 
    definition).
    Uprating Credits: The payments/credits that are returned to the 
    Uprating Contractors in repayment for the advancement of funds.
    Uprating Program: Non-federally financed work to increase the capacity 
    of the existing generating and associated electrical equipment at the 
    BCP.
    Western: Western Area Power Administration, DOE.
    Western's 1986 General Regulations: General Regulations for the Charges 
    for the Sale of Power from the Boulder Canyon Project, 10 CFR Part 904 
    (51 FR 43124, November 28, 1986).
    Working Capital Fund: Reserve of funds contributed by the Contractors 
    to be used when the Colorado River Dam Fund has no money available.
    
    Effective Date
    
        The existing approved ratesetting methodology is effective January 
    1, 1993, through September 30, 1997.
        The rates in Rate Schedule BCP-F4/2 will be in effect on a final 
    basis beginning February 1, 1994. The methodology utilized in WAPA-58 
    requires that Western modify the BCP rate, either an increase or 
    decrease, on an annual basis. For all other FYs of the ratesetting 
    methodology approval period (through 1997) the rates will be set in 
    accordance with the approved ratesetting methodology and placed into 
    effect by the Administrator of Western.
    
    Public Notice and Comment
    
        The Procedures for Public Participation in Power and Transmission 
    Rate Adjustments and Extensions, 10 CFR part 903, have been followed by 
    Western in the development of the power rates. It is a major rate 
    adjustment as defined at 10 CFR 903.2(e) and 903.2(f)(1). The 
    distinction between a minor and a major rate adjustment is used only to 
    determine the public procedures for the rate adjustment.
        The following summarizes the steps Western took to ensure 
    involvement of interested parties in the rate process:
        1. A Federal Register notice was published on August 17, 1993 (58 
    FR 43631), officially announcing the proposed annual BCP power rate 
    adjustment, initiating the public consultation and comment period, 
    announcing the public information and public comment forums, and 
    presenting procedures for public participation.
        2. A letter was mailed to all BCP customers and other interested 
    parties on August 10, 1993, providing a copy of the BCP PRSS and 
    Supporting Schedules and announcing a public information forum and a 
    public comment forum.
        3. At the public information forum held on August 31, 1993, Western 
    and Reclamation representatives explained the need for the BCP rate 
    adjustment in greater detail and answered questions.
        4. The public comment forum was also held on August 31, 1993, to 
    give the public an opportunity to comment for the record. Six people 
    representing customers and customer groups made oral comments.
        5. On September 29, 1993, a Federal Register notice was published 
    (58 FR 50916) formally announcing that the consultation and comment 
    period would be extended through October 18, 1993, for the proposed 
    Annual Rate review process for the BCP.
        6. Due to the need for additional time to respond to some of the 
    questions asked by the BCP customers in the August 31, 1993, public 
    information forum, Western again extended the consultation and comment 
    period. On October 26, 1993, a Federal Register notice was published 
    (58 FR 57598) formally announcing that the consultation and comment 
    period would be extended through November 15, 1993.
        7. A letter was mailed to all BCP customers and other interested 
    parties on October 18, 1993, providing a copy of the BCP revised PRSS 
    and Supporting Schedules and announcing an informal customer meeting. 
    The informal meeting was held on November 4, 1993, in Phoenix, Arizona. 
    At this informal meeting, Western and Reclamation representatives 
    discussed the revised PRSS, Supporting Schedules, and summary of the 
    changes.
        8. Nine written comment letters were received during the 90-day 
    consultation and comment period. The consultation and comment period 
    ended November 15, 1993.
    
    Project History
    
        The BCP was authorized for construction by the Project Act. The 
    Project Act provided for a dam to be built in the Black Canyon located 
    on the Colorado River adjacent to the Arizona/Nevada border. The dam 
    was built for the express purposes of: (1) Controlling the flooding in 
    the lower regions of the Colorado River drainage system; (2) improving 
    navigation of the Colorado River and its tributaries; (3) regulating 
    the Colorado River, while providing storage and delivery of the stored 
    water for the reclamation of public lands; and (4) generating 
    electrical energy as a means of making the BCP a self-supporting and 
    financially solvent undertaking. Congress authorized Treasury to 
    advance up to $165 million to the Secretary of the Interior to provide 
    for the construction of the dam, powerplant, and related features; $25 
    million of the $165 million were allocated to flood control.
        Construction of the Hoover Dam, formerly known as Boulder Dam, 
    began in 1930, and the first generating unit of the power plant went 
    into service in 1937. Upon completion of the project facilities, power 
    sales commenced, in accordance with the provisions of the Project Act, 
    to Contractors in the States of Arizona, California, and Nevada.
        The Project Act was modified in 1940 by the Adjustment Act. The 
    Adjustment Act, among other things, authorized the Secretary of the 
    Interior to promulgate and to put into effect power rates based upon a 
    repayment period from June 1, 1937, to May 31, 1987; to reduce the 
    interest rate from 4 percent to 3 percent per annum on unpaid Treasury 
    advances; to require annual payments to the States of Arizona and 
    Nevada in lieu of taxes levied; and to defer without interest until 
    June 1, 1987, the repayment of the $25 million allocated to flood 
    control.
        Subsequently and pursuant to the Adjustment Act, the Secretary of 
    the Interior published and implemented the 1941 General Regulations for 
    the period ending May 31, 1987.
        As the end of the 50-year term of the original contracts 
    approached, controversy developed among the BCP Contractors over 
    renewal rights to BCP power, and litigation resulted. Compromises were 
    reached and embodied in the 1984 Act.
        The 1984 Act authorized an increase in the capacity of the existing 
    generating and associated electrical equipment at the BCP. The work to 
    accomplish this increase, referred to as the Uprating Program, was to 
    be funded initially by advances from certain BCP Contractors to 
    Reclamation. Funds advanced would be returned to these Contractors 
    through credits on their monthly power bills. The 1984 Act provided for 
    advances from the Treasury for the improvement of visitor facilities at 
    the BCP. The 1984 Act also required that an additional charge of 4.5 
    mills/kWh be assessed on energy sales to Arizona and an additional 
    charge of 2.5 mills/kWh be assessed on energy sales to California and 
    Nevada; all revenue resulting from the additional charge is to be 
    transferred to the LCRBDF.
        Under the 1984 Act, BCP's power was sold to 15 Contractors located 
    in the States of Arizona, California, and Nevada, in accordance with 
    the Conformed Criteria.
        Due to the numerous requirements set out in the 1984 Act and the 
    earlier division of the Federal responsibilities relating to Hoover Dam 
    between Reclamation and Western, both agencies published new 
    regulations governing their respective responsibilities at the BCP 
    after June 1, 1987. These regulations are cited herein as Reclamation's 
    1986 General Regulations and Western's 1986 General Regulations, and 
    they supersede the 1941 General Regulations, which terminated on May 
    31, 1987.
    
    Power Repayment Spreadsheet Studies
    
        PRSS are prepared each FY to determine if power revenues will be 
    sufficient to pay, within the prescribed time periods, all costs 
    assigned to the power function. Repayment criteria are based on law, 
    policies, and authorizing legislation. DOE Order No. RA 6120.2, section 
    12.b, states:
    
        In addition to the recovery of the above costs (operations and 
    maintenance and interest expenses) on a year-by-year basis, the 
    expected revenues are at least sufficient to recover: (1) Each 
    dollar of power investment at Federal hydroelectric generating 
    plants within 50 years after they become revenue producing, except 
    as otherwise provided by law; plus, (2) each annual increment of 
    Federal transmission investment within the average service life of 
    such transmission facilities or within a maximum of 50 years, 
    whichever is less; plus, (3) the cost of each replacement of a unit 
    of property of a Federal power system within its expected service 
    life up to a maximum of 50 years; plus, (4) each dollar of assisted 
    irrigation investment within the period established for the 
    irrigation water users to repay their share of construction costs; 
    plus, (5) other costs such as payments to basin funds, participating 
    projects or States.
    
    Existing and Annual Rates
    
        A comparison of the existing and annual BCP rates follows: 
    
    ------------------------------------------------------------------------
                                                      Existing      Annual  
                                                     rates (FY    rates (FY 
                                                       1993)        1994)   
    ------------------------------------------------------------------------
    Power Rate Schedule...........................     BCP-F4/1    BCP-F4/2*
    Composite Rate (mills/kWh)....................        14.56        12.62
    Energy Rate (mills/kWh).......................         7.28         6.31
    Capacity Rate ($/kW/month)....................        $1.28       $1.07 
    ------------------------------------------------------------------------
    *The ratesetting methodology is in effect from January 1, 1993, through 
      September 30, 1997. The BCP rates will be reviewed annually.          
    
    Certification of Rates
    
        Western's Administrator has certified that the BCP rates placed 
    into effect herein are the lowest possible consistent with sound 
    business principles, pursuant to the ratesetting methodology agreed to 
    by the BCP Contractors, Western, and Reclamation. The BCP rates have 
    been developed in accordance with administrative policies and 
    applicable laws.
    
    Discussion
    
        The proposed BCP rates have been updated from the BCP rates 
    originally proposed in the customer package sent out on August 10, 
    1993, and Federal Register notice dated August 17, 1993. The changes to 
    the FY 1993 Ratebase PRSS are as follows:
    
    --The actual figures for FY 1992 were used rather than the projected 
    figures. The adjustments for FY 1992 that had been reflected in FY 1994 
    were removed.
    --FY 1994 Working Capital Fund was adjusted to zero. It was reduced 
    because of the current year CRDF carry-over balance.
    --The most recent uprater credit schedules received from the 
    Contractors were used for FY 1994 and out years.
    --FY 1993 figures have been adjusted to actual.
    --The Visitor Facilities completion date was moved to FY 1996.
    --Circular reference in the supporting schedule LOANS10F.WK1 
    eliminated. No change to output.
    --The projected Total Energy Sales (MWh) for FY 1999 through the end of 
    the study were changed to a constant of 4,527,001 MWh.
    --Title on PRSS changed from ``Boulder Canyon Project FY 1993 Power 
    Repayment Study Spreadsheet'' to ``* * * Spreadsheet Study.''
    --Corrected Column 14 formula for FY 1994 and out-years. It did not 
    change any figures.
    --Deleted working column to far right of spreadsheet. It did not change 
    any figures.
    --Corrected the energy and capacity and the FY 1992 adjustment in 
    ``Other Revenue'' to reconcile with the crosswalk numbers for FY 1992.
    --On Supporting Schedule ACTFINAL.WK1 (E-1, E-2), added summary pages 
    of principal payments. This will serve as an easy-to-read tool of what 
    is being paid off in any particular year.
    --On Supporting Schedule LOANS10F.WK1, added an adjustment (page F-1). 
    Also, the amortization period was changed back to 10 years instead of 9 
    years.
    --On Supporting Schedule REQFINAL.WK1 (G-1), the principal payment in 
    FY 1993 was corrected and now ties with the PRSS.
    --In column 27 in FY 2017, the $5,045,030 adjustment (PRSS to CRDF) was 
    credited. (This is reflected in FY 2018 in column 14.) This was done to 
    repay the customers at the end of their contract.
    --In columns 21 and 25, the formula used to determine the Annual Rate 
    for this rate adjusts the rate for FY 1994 over the remainder of FY 
    1994. This is assuming the effective date of the rate is February 1, 
    1994.
    --Changed the file reference title at the bottom of the PRSS to 
    [RATEBASE.WK1].
    --Revised the CSRS costs as submitted in memorandum dated September 7, 
    1993.
    
        The existing and FY 1994 annual revenue requirements for the BCP 
    are as follows: 
    
    ------------------------------------------------------------------------
                                                   Revenue requirements     
                                             -------------------------------
                                               Existing BCP     Annual BCP  
                                                 rates (FY       rates (FY  
                                                  1993)           1994)*    
    ------------------------------------------------------------------------
    Revenue Requirements....................     $49,992,504    $47,894,340 
    ------------------------------------------------------------------------
    *The proposed BCP rates are to be in effect beginning February 1, 1994. 
    
        The methodology utilized in WAPA-58 requires that Western modify 
    the BCP rate, either an increase or decrease, on an annual basis.
    
    Statement of Revenue and Related Expenses
    
        The following table provides a summary of revenue and expense data 
    through the 5-year proposed rate approval period. 
    
      Boulder Canyon Project Comparison of 5-Year Rate Period (FY 1994-98)  
                              Revenues and Expenses                         
                                    [$1,000]                                
    ------------------------------------------------------------------------
                                         FY 1992      FY 1993               
                                        PRSS 1994-   PRSS 1994-  Difference 
                                           98           98                  
    ------------------------------------------------------------------------
    Revenues:                                                               
        Energy Sales.................     $138,790     $133,803     ($4,987)
        Capacity Sales...............      138,790      133,803      (4,987)
        Water Sales..................        2,250        2,250            0
        Other Revenue................        6,360       13,280        6,920
        CRDF Carry-Over Balance......            0        2,803        2,803
                                      --------------------------------------
            Total Revenues...........      286,190      285,939        (251)
    Revenue Distribution:                                                   
        Operation & Maintenance......      108,525      113,072        4,547
        Payment to States............        3,000        3,000            0
        Other Expenses...............        9,634       16,488        6,854
        Annual Uprating Payments.....       89,741       80,491      (9,250)
        Annual Replacement...........       17,655       22,740        5,085
        Interest.....................       43,139       39,168      (3,971)
        Principal Payments...........       11,661       11,468        (193)
        Working Capital Fund.........        2,835        (488)      (3,323)
            Total....................      286,190      285,939       (251) 
    ------------------------------------------------------------------------
    
    Basis for Rate Development--BCP
    
        The FY 1994 annual BCP rates are designed to maintain a 50/50 split 
    between revenue earned from energy and capacity rates. The cost to 
    individual customers will vary, because of differences in their 
    supplies and loads.
        The BCP Annual Rate consists of a 6.31 mills/kWh energy rate and 
    $1.07/kW/month capacity rate effective February 1, 1994. The 
    ratesetting methodology approval period is through September 30, 1997.
    
    Comments
    
        During the 90-day comment period, Western received nine written 
    comments. In addition, six speakers commented at the August 31, 1993, 
    public comment forum. All comments were reviewed and considered in the 
    preparation of this rate order.
        Written comments were received from the following sources:
    
    Arizona Municipal Power Users' Association (Arizona)
    Arizona Power Authority (Arizona)
    Vernon, City of (California)
    Colorado River Commission of Nevada (Nevada)
    Irrigation & Electrical Districts' Assoc. of Arizona (Arizona)
    Los Angeles, City of, Department of Water and Power (California)
    Metropolitan Water District of Southern California (California)
    Overton Power District No. 5 (Nevada)/Valley Electric Association 
    (Nevada)
    Utility Resource Services (Arizona)
    
        Representatives of the following organizations made oral comments:
    
    Arizona Power Authority (Arizona)
    Colorado River Commission of Nevada (Nevada)
    Los Angeles, City of, Department of Water and Power (California)
    Irrigation & Electrical Districts Association of Arizona (Arizona)
    Overton Power District No. 5/Valley Electric Assoc. (Nevada)
    Pioneer Chlor Alkali Company (Nevada)
    
        Most of the comments received at the public meetings and in 
    correspondence dealt with the PRSS, capitalized investments, annual 
    expenses, working capital, other revenue, ratesetting, capitalized 
    deficits, and audits. All comments were considered in developing the 
    proposed BCP rates.
        The comments and responses, paraphrased for brevity, are discussed 
    below. Direct quotes from comment letters are used for clarification 
    where necessary.
    
    Boulder Canyon Comments
    
    Power Repayment Spreadsheet Study
        Comment: Substitute the real figures for FY 1992 in place of the 
    projected figures. You would then have a true carry-forward figure in 
    FY 1992 and an estimated carry-forward figure at the end of FY 1993. It 
    might have a substantial effect upon the numbers for FY 1994.
        Response: The actual figures for both FY 1992 and FY 1993 have been 
    utilized rather than the projected figures. The adjustments for FY 1992 
    that were reflected in FY 1994 were removed.
        Comment: The customer believes as a result of the discrepancies we 
    saw in the numbers a new PRSS should be run with the best available 
    data.
        Response: A revised PRSS was prepared and mailed to the BCP 
    Contractors on October 18, 1993. Both a printed copy and diskette copy 
    of the PRSS, along with a summary of changes to the original PRSS, were 
    provided. On November 4, 1993, Western held an informal workshop with 
    the BCP Contractors to discuss this revised PRSS.
        Comment: Concern has been expressed that the PRSS does not reflect 
    the most recent budget estimates for BCP operation, maintenance, and 
    replacement expenses.
        Response: The PRSS, upon which this rate adjustment is based, 
    reflects the most current budget estimates for all costs associated 
    with operation, maintenance, and replacement expenses in the BCP.
        Comment: Establish a BCP recordkeeping system to provide a 
    correlation between BCP actual and budgeted expenditures to the data 
    shown in the PRSS.
        Response: Western is in the process of implementing a recordkeeping 
    system to correlate actual expenditures to budgeted expenditures. This 
    system will be in place prior to Western revising rates for FY 1995.
        Comment: In FY 1994, column 7, debt service interest expense, and 
    column 8, capitalized deficit interest expense, did not sum to column 
    9, total interest expense.
        Response: Due to a spreadsheet linking problem, the correct values 
    did not properly transfer to the PRSS only in FY 1994. Western made 
    corrections to the link between the supporting schedules and the PRSS 
    to correct this problem.
        Comment: Some Contractors expressed concern that Western deviated 
    from the 5-year moving window methodology for the BCP. Some stated they 
    believed the new methodology should operate very much like the rate 
    mechanism that was in place prior to June 1, 1987.
        Response: Western believes that it is adhering to the 5-year moving 
    window methodology that was set forth in the September 15, 1992, 
    Settlement Agreement. At the end of each year, differences between 
    projected values and actual values are calculated and reflected in the 
    PRSS. Any net differences, either positive or negative, are carried 
    forward to the next year, as shown in column 14 of the PRSS.
        The PRSS, upon which this rate adjustment is based, embodies all of 
    the principles set forth in the September 15, 1992, Settlement 
    Agreement. The new ratesetting methodology, as set out in this 
    Settlement Agreement, was never intended to operate in the same fashion 
    as the ratesetting process utilized prior to June 1, 1987.
        Comment: There appears to be approximately an $11-million surplus 
    that is pure and simple getting averaged out in the 5-year rate window 
    process. It bears reminding that WAPA-58 represented an attempt to come 
    up with a rate mechanism which was similar to the rate mechanics in the 
    pre-1987 era. It is clear that the rate mechanism in that pre-1987 era 
    trued up the cost immediately. This mechanism bears no resemblance to 
    the pre-1987 process on the true-up mechanics.
        Response: There is no $11-million surplus in the 5-year ratesetting 
    period (cost evaluation period) for this rate process. If there was an 
    under- or over-collection of revenues in any year, this would be 
    carried forward to the next year. Thus, this under/over-collection 
    would be numerically reflected in both the next year's rate 
    calculation, as well as in the 5-year moving window rate calculation. 
    While the WAPA-58 rate mechanism is somewhat similar to the pre-1987 
    rate mechanism, it is significantly different, because the WAPA-58 rate 
    methodology reflects the 5-year moving window concept, as agreed to by 
    the BCP Contractors, Reclamation, and Western in the September 15, 
    1992, Settlement Agreement.
        Comment: A customer believes that annual uprater payments of column 
    3 should reflect the new debt service schedules that follow the 
    uprating bonds used by the Arizona Power Authority and Colorado River 
    Commission. The customer is also not so sure that the correct figures 
    are being used for the Colorado River Commission and for the Southern 
    California Public Power Authority.
        Response: The revised annual uprater schedules are currently 
    reflected in FY 1993 and in the out-years in the latest PRSS.
        Comment: Some Contractors have requested that a new PRSS be run 
    which would reflect the correction of historical data and the 
    correction of mathematical errors.
        Response: The PRSS, upon which this rate adjustment is based, has 
    been corrected to fix these identified problems. These issues were all 
    addressed in the Public Information Forum data requests which were 
    mailed to the BCP Contractors on October 18, 1993. These issues were 
    also addressed at length during the informal workshop held on November 
    4, 1993.
        Comment: A customer is concerned that the FY 1992 true-up, as 
    implemented here, does not reflect the intent of the FY 1992 rate 
    formula, much less meet the lowest possible rate standard, which all 
    such rates are supposed to meet.
        Response: The FY 1992 projected values have been revised to actual 
    values. (The adjustment had previously been shown in FY 1994.)
        Comment: A customer is concerned about the huge variations between 
    projected and actual expenditures, as well as significant differences 
    between the PRSS and various other sources of data, as officially 
    reported by both Reclamation and Western. Also such concerns are 
    heightened by the continued failure of Western to comply with the 
    independent project audit requirements.
        Response: Over the past several years, various Contractors have 
    raised the issue that several actual expenditures (most notably O&M 
    expenses) have continually been less than projected. This is 
    predominately due to the reduced actual hydrology of the BCP. The BCP 
    is an ``available receipts project'' in that it cannot commit or spend 
    money that is not in the Colorado River Dam Fund. Because power 
    revenues are the only source of revenue to the CRDF, if the actual 
    hydrology is less than anticipated, reductions in expenditures are 
    necessary to keep from overspending the CRDF. To a large extent, the 
    only way to reduce expenditures, without deferring the payment of 
    Uprating Credits, is in the reduction of either O&M expenses or in 
    annual replacements.
        In regard to the concern over the significant differences between 
    the PRSS and various sources of data, as reported by both Reclamation 
    and Western, these differences have been explained in the data response 
    mailed to the BCP Contractors on October 18, 1993. Although it appeared 
    that significant differences did exist in the data, reconciliation data 
    sheets that were supplied by Reclamation indicated that all data 
    originated from a common data source and that differences were due to 
    the particular forum the numbers were prepared for, rather than any 
    inherent difference in the data.
        In regard to the concern over the lack of an independent audit, 
    Western is conducting an annual audit on BCP, as part of the Western-
    wide audit process. FERC specifically addressed the audit issue in its 
    Order approving WAPA-58 and found Western's procedures to be in 
    compliance with requirements.
    Rate Process
        Comment: The authority for final confirmation and approval is 
    exclusively reserved for FERC for any proposed change in BCP rates.
        Response: On November 3, 1993, FERC issued an Order Confirming and 
    Approving Rates on a Final Basis for the BCP which stated ``As to the 
    annual rate adjustments, Western's customers should be able to monitor 
    the operation of the formula rate when they take part in Western's 
    annual public participation proceedings held when it proposes Annual 
    Rate adjustments according to the formula. This annual proceeding 
    should provide the customers an opportunity to monitor both compliance 
    with the formula rate as well as to voice any concerns about the 
    magnitude of the rate adjustment.'' Western has indicated to the BCP 
    Contractors that it intends to follow the same rate process as in the 
    past, except that the approval process will conclude with the signature 
    of Western's Administrator. Informational copies of the BCP rate order 
    package will be submitted to DOE and to FERC. The current rate formula 
    is approved through September 30, 1997. For BCP rates to become 
    effective on or after October 1, 1997, Western will have to seek 
    further approval of DOE and FERC.
        Comment: A customer requests acknowledgement that the Annual Rate 
    adjustments process is one of a number of issues which is subject to 
    resolution by the BCP Implementation Agreement being negotiated.
        Response: The Annual Rate adjustment process is one of the issues 
    which is subject to resolution by the BCP Implementation Agreement 
    being negotiated. The rate adjustment process filed in WAPA-58 and 
    accepted by FERC resulted from the Settlement Agreement of September 
    15, 1992, among the BCP Contractors, Reclamation and Western. This same 
    group of Contractors is again back at the negotiating table, attempting 
    to resolve certain related issues which, if resolved, will possibly 
    require modification of the rate methodology implemented in WAPA-58.
        Comment: A customer supports a postponement in the rate process.
        Comment: Desire to delay implementation of a 5-percent rate 
    reduction for the BCP.
        Response: As a result of comments made during the August 31, 1993, 
    public information forum and public comment forum, Western extended the 
    comment and consultation period and has postponed implementation of the 
    Annual Rates until February 1, 1994.
        Comment: A customer recommends that Western strictly adhere to the 
    requirements of 10 CFR Part 903 by noticing the place, time, and date 
    of the required public comment forum in the Federal Register at least 
    30 days in advance of the meeting.
        Comment: The customer suggests for future Annual Rate adjustments 
    and thereafter, Western should provide a public comment period that is 
    longer than 30 days, as presented in the August 17, 1993, Federal 
    Register notice. The customer suggests a 90-day public comment period 
    for all future Annual Rate adjustments.
        Response: Western acknowledges that the BCP Contractors were 
    provided only 21 days advance written notice of the public comment 
    forum that concerned the BCP rate process. However, the BCP Contractors 
    were orally informed on July 30, 1993, of the proposed August 31, 1993, 
    BCP public comment forum. This announcement was made and the proposed 
    meeting date was discussed with the BCP Contractors at a BCP Settlement 
    Negotiations meeting in Las Vegas at McCarran Airport. Representatives 
    of all the BCP Contractors were in attendance.
        Western is in the process of preparing a schedule of all the 
    various activities that comprise a rate process, along with the timing 
    of said events. This schedule is targeted for completion in early 1994 
    and will be provided to all Western's customers when completed. Because 
    the BCP rates will be modified on an annual basis, at least until 
    September 30, 1997, the BCP Contractors will know well in advance when 
    various activities concerning the BCP rate process will occur.
        Comment: A customer suggests that public information forums and 
    public comment forums for future Annual Rate adjustments not be 
    scheduled on the same day.
        Response: In the future, Western will not conduct public 
    information forums and public comment forums on the same day.
        Comment: A customer requests that Western prepare a decision 
    document summarizing all comments received during the public comment 
    period and Western's and Reclamation's responses to those comments. 
    This decision document should be distributed to all BCP Contractors and 
    interested parties before implementing the proposed Annual Rate 
    adjustment.
        Response: As part of Western's rate process, a rate order package 
    is prepared which, among other items, contains a summary of all of the 
    comments received during both the public comment forum and the 
    consultation and comment period. Western's responses to these comments 
    are also part of this rate order package. This package is presented to 
    Western's Administrator, and to DOE and FERC for informational 
    purposes. This information is also published in the Federal Register 
    and a copy of the material is sent by Western to its customers. This 
    entire process takes place prior to implementation of the revised 
    rates. In the future, distribution to the BCP Contractors will take 
    place once Western's Administrator approves the annually revised rates, 
    which will normally be prior to the implementation of said rates.
    Ratesetting
        Comment: A uniform, predictable program for the development of 
    databases and rate studies in support of Annual Rate adjustments should 
    be prepared, complete with the dates by which specific information will 
    be provided to the Contractors, with reference to the specific sources 
    of information to be used for all data presented in the power repayment 
    study.
        Response: As previously indicated, Western is in the process of 
    preparing a schedule of all the various activities that comprise a rate 
    process, along with the timing of said events. This schedule is 
    targeted for completion in early 1994 and will be provided to all 
    Western's customers when completed. Because the BCP rates will be 
    modified on an annual basis, at least until September 30, 1997, the BCP 
    Contractors will know well in advance when various activities 
    concerning the BCP rate process will occur.
        As also previously indicated, Western is in the process of 
    developing a record-keeping system to correlate actual expenditures to 
    budget projections. The combination of the detailed schedule and the 
    proposed record-keeping system should provide both: (i) Advance notice 
    to the BCP Contractors of all BCP rate activity and (ii) continuity and 
    consistency of data.
        Comment: Some Contractors have requested that the rate study be 
    revised to recognize that the rate over the first 4 months of FY 1994 
    was equal to the Rate Order No. WAPA-58 rate, resulting in an increase 
    in forecast revenues in FY 1994.
        Response: Western has revised the rate as appropriate to reflect: 
    (i) A February 1, 1994, implementation date and (ii) the rate 
    methodology specified in WAPA-58. The effect was to further reduce the 
    Annual Rate in recognition of higher revenues for the first 4 months of 
    FY 1994.
        Comment: The third to the last paragraph of the Federal Register 
    notice implies that the Delegation Order No. 0204-108 addresses not 
    only rates but also ratesetting methodology. Western's paraphrase of 
    the delegation order in the Federal Register notice is not correct 
    since the delegation order only uses the word ``rates'' and not the 
    words ``ratesetting methodology.'' Customer raises this point now 
    because of the importance it places on the need to ensure that the 
    process authorized under Delegation Order No. 0204-108 is not construed 
    to constitute a change in regulations governing a setting of rate 
    without being accompanied by appropriate steps which must precede any 
    change of regulations governing the establishments of rates by a power 
    marketing administration.
        Response: The customer is correct in that the words ``ratesetting 
    methodology'' are not specifically referenced in Delegation Order No. 
    0204-108. However, 10 CFR 903.2(l) states that ``rate means the 
    monetary charge or formula for computing such a charge for any electric 
    service provided by the PMA, including but not limited to charges for 
    capacity (or demand), energy, or transmission service; * * *.'' 
    Additionally, in the context of the BCP Settlement Agreement among the 
    BCP Contractors, Reclamation, and Western, the rates being proposed for 
    the BCP are dependent upon the methodology. There has been no change in 
    regulations, or implied change in regulations, concerning the 
    establishment of rates by Western.
        Comment: Some Contractors indicate that because they do not 
    participate in the budget formulation process, they believe that the 
    formalization of the E&OC is necessary to assure them an opportunity to 
    provide input prior to the development of the Western and Reclamation 
    budgets.
        Response: Both Western and Reclamation are committed to work with 
    the Contractors through the E&OC to ensure that all entities are 
    informed and have the opportunity to review budgetary expenditures, 
    along with providing input on the project activities and costs that 
    will impact the BCP rates. Additionally, Western is currently working 
    with the customers in the development of its Ten-Year Engineering Plan. 
    At the December 15, 1993, Ten-Year Engineering Plan meeting, 
    Reclamation's representative indicated she would recommend that a 
    similar process be initiated by Reclamation's management.
        Comment: One customer is concerned that BCP rates are not the 
    lowest possible rate to consumers consistent with sound business 
    practice as required under the prescribed standards. And the use of 
    such a formulary rate adjustment mechanism will not provide, and has 
    not provided, the proper incentives to assure efficient and economic 
    operation of the project. This formulary rate adjustment mechanism is 
    similar to the prior pinch-point methodology, which also did not 
    provide incentive for efficient and economic operations at the BCP.
        Response: As indicated in a response to a similar comment in the 
    WAPA-58 Rate Order, Western is of the opinion that the approved rate 
    methodology sets rates at the lowest possible cost consistent with both 
    sound business principles and with the principles outlined by the BCP 
    Settlement Agreement of September 15, 1992. The Annual Rate covered in 
    this rate order reflects a significant decrease in costs and suggests 
    that the Annual Rate process and the EO&C are in fact promoting strong 
    incentives for efficient and economic operations.
        Comment: The subject ratemaking methodology constitutes an 
    automatic adjustment clause within the meaning of and as governed by 
    PURPA and that such automatic adjustment clause has not been 
    implemented in accordance with the very precise and prescribed 
    procedures established by PURPA.
        Response: The Public Utility Regulatory Policies Act of 1978 
    (PURPA) states at 16 U.S.C. 2612(a) that:
    
        This chapter applies to each electric utility in any calendar 
    year, and to each proceeding relating to each electric utility in 
    such year if the total sales of electric energy by such utility for 
    purposes other than resale exceeded 500 million kilowatthours during 
    any calendar year beginning after December 31, 1975, and before the 
    immediately preceding calendar year.
    
        Electric utility is defined to include Federal agencies which sell 
    electric energy. Of the 15 BCP Contractors, the Metropolitan Water 
    District, purchases more than 500 million kWh during any calendar year 
    which is for purposes other than resale. As a result, the BCP is 
    subject to PURPA.
        With regard to automatic adjustment clauses, the PURPA states at 16 
    U.S.C. 2623(b)(2), that ``[n]o electric utility may increase any rate 
    pursuant to an automatic adjustment clause unless such clause meets the 
    requirements of section 2625(e) of this title.''
        Section 2625(e) states that:
    
        (1) An automatic adjustment clause of an electric utility meets 
    the requirements of this subsection if--
        (A) Such clause is determined, not less often than every 4 
    years, by the State regulatory authority (with respect to an 
    electric utility for which it has ratemaking authority) or by the 
    electric utility (in the case of a nonregulated electric utility), 
    after an evidentiary hearing, to provide incentives for efficient 
    use of resources (including incentives for economical purchase and 
    use of fuel and electric energy) by such electric utility, and
        (B) Such clause is reviewed not less often than every 2 years, 
    in the manner described in paragraph (2), by the State regulatory 
    authority having ratemaking authority with respect to such utility 
    (or by the electric utility in the case of a nonregulated electric 
    utility), to insure the maximum economies in those operations and 
    purchases which affect the rates to which such clause applies.
        (2) In making a review under subparagraph (B) of paragraph (1) 
    with respect to an electric utility, the reviewing authority shall 
    examine and, if appropriate, cause to be audited the practices of 
    such electric utility relating to costs subject to an automatic 
    adjustment clause, and shall require such reports as may be 
    necessary to carry out such review (including a disclosure of any 
    ownership or corporate relationship between such electric utility 
    and the seller to such utility of fuel, electric energy or other 
    items).
        (3) As used in this subsection and section 2623(b) of this 
    title, the term ``automatic adjustment clause'' means a provision of 
    a rate schedule which provides for increases or decreases (or both), 
    without prior hearing, in rates reflecting increases or decreases 
    (or both) in costs incurred by an electric utility. Such term does 
    not include an interim rate which takes effect subject to a later 
    determination of the appropriate amount of the rate.
    
        The current formula for sales from the BCP was agreed to by all of 
    the Contractors, Western, and Reclamation in a Settlement Agreement 
    dated September 15, 1992. The methodology set out in this Agreement was 
    approved by FERC on November 3, 1993.
        The stated PURPA purpose of automatic adjustment clauses in 
    sections 2625(e)(1) (A) and (B) is to provide incentives for efficient 
    use of resources (including incentives for economical purchase and use 
    of fuel and electric energy) by such electric utility, and to insure 
    the maximum economies in those operations and purchases which affect 
    the rates to which such clause applies. In this particular case, the 
    initial reason that annual review and adjustment was determined to be 
    the preferred methodology was that the Contractors wanted Western to be 
    able to react on an annual basis to any over- or under-collections of 
    revenues. The methodology set out in the September 15, 1992, Settlement 
    Agreement establishes that Western look at the higher of the 5-year 
    average or the first year of revenue requirements on an annual basis 
    and make appropriate adjustments. As a result, sections 2625(e)(1) (A) 
    and (B) do not apply in our case.
        Section 2625(e)(3) applies in cases where an increase or decrease 
    comes about without prior hearing. In our case, there have been 
    numerous information and comment forums allowing for the presentation 
    of both written and oral comments. BCP Contractors were provided an 
    opportunity to be heard and many of their comments caused Western to 
    make changes to some of the calculations that were used in determining 
    the rate. Paragraph (3) does not require an evidentiary hearing as does 
    paragraph (e)(1)(A). As a result, section 2625(e)(3) is inapplicable, 
    because the BCP Annual Rate adjustment is not an automatic adjustment 
    pursuant to an ``automatic adjustment clause''.
        FERC stated in its Order Confirming and Approving Rates on a Final 
    Basis that ``[r]ather than rely on a stated rate to recover the costs 
    projected in a power repayment study, Western now proposes a formula 
    rate which will compute project costs annually and revise the BCP 
    capacity and energy charges accordingly. In implementing the formula 
    rate, Western will present annually to Reclamation and the BCP power 
    purchasers (Contractors) * * * its analysis of the revenue that the 
    then-effective BCP capacity and energy charges would produce for the 
    next FY as compared to the forecasted annual revenue requirement for 
    the next FY. If such revenues are greater or less than the forecasted 
    annual revenue requirement, Western will adjust the capacity and energy 
    charges * * *. Western will hold public participation proceedings prior 
    to implementing any rate adjustment required by these annual reviews.''
        In summary, the annual adjustment clause of the new methodology was 
    negotiated among Western, Reclamation, the Contractors, and other 
    interested parties; the Settlement Agreement and the new methodology 
    were approved by FERC with comment by the Contractors and other 
    interested parties; and Western has had and will continue to have 
    annual public processes which allow for review and input by the 
    Contractors and other interested parties prior to implementation of any 
    Annual Rate adjustments. PURPA is not applicable to the BCP annual 
    adjustment because the purpose of the adjustment is not the purpose 
    established by PURPA, and the Contractors and the public at large have 
    been provided with the opportunity to be heard.
    WAPA-58 Concerns/Issues
        Comment: One customer requests that its intervention protest in 
    WAPA-58 be a continuation of preservation of those issues in this 
    proceeding.
        Response: These comments have been responded to in the record for 
    WAPA-58.
        Comment: A customer would like its oral comments made on September 
    10, 1992, its written comments submitted on September 25, 1992, and its 
    motion to intervene and protest filed under Docket EF 93-5091-000 
    considered a part of these comments today as if set out here in full.
        Response: These comments have been responded to in the record for 
    WAPA-58.
        Comment: A concern was expressed that the August PRSS contained 
    some data which had changed since the PRSS was prepared in support of 
    Rate Order WAPA-58. Specifically, the August PRSS shows a significant 
    reduction in the projected generation output for the BCP.
        Response: Reclamation prepares a generation forecast each year to 
    be used in support of the BCP PRSS. The generation forecast prepared 
    for the 5-year ratesetting period is based upon the most current 
    hydrological information available at the time the forecast is made. 
    The data presented in the August PRSS reflects the impact upon project 
    generation resulting from the water release limitation imposed as a 
    result of the flooding in Arizona and the most recent water scheduling 
    changes for the Central Arizona Project. The average annual generation 
    for the 5-year ratesetting period reported in the PRSS prepared in 
    support of Rate Order WAPA-58 was 4,083 GWh. The average annual 
    generation for the 5-year ratesetting period reported in the August 
    PRSS was 4,033 GWh. This represents an annual reduction of 
    approximately 50 GWh per year, or about 1 percent.
    Capitalized Deficit
        Comment: Some Contractors have requested Western to amortize the 
    capitalized deficit expense over the remainder of the current contract 
    period, which ends in FY 2017, rather than over the 10-year period 
    utilized in the PRSS.
        Response: Western addressed this issue in Rate Order WAPA-58. In 
    that rate order response, Western noted that standard practice is to 
    repay capitalized deficits over a 5-year period. Due to the size of the 
    deficit, Western believed it was appropriate to extend the payment over 
    a 10-year period.
        In FERC's Order confirming and approving WAPA-58 it stated:
    
        The agreement speaks broadly about ``item(s) of debt'' and does 
    not speak directly to capitalized deficits. Thus, the claim that 
    Western has violated the terms of the agreement does not appear to 
    be justified. * * * The choice of the Administrator to amortize 
    capitalized deficits over ten years is a reasonable approach to 
    accommodate a phase-in of the formula rate that Western has proposed 
    here.
    Hydrology--S
        Comment: Western has continued to fail to account for unloaded 
    synchronized generation. Customer believes that is a component that 
    needs to be addressed at some point and would like to see that included 
    in the PRSS.
        Response: Western addressed this issue in the WAPA-58 Rate Order. 
    Both Western and Reclamation believe that unloaded synchronized 
    generation has been properly addressed in the PRSS. Both Western and 
    Reclamation are agreeable to meeting with the Contractors to resolve 
    this issue.
    Capitalized Investments
        Comment: A Contractor inquired about the repayment period 
    associated with the flood control debt, in light of the fact that a 
    Bureau of Reclamation Inspector General audit report recommended use of 
    a repayment period of 30 years.
        Response: For the purposes of this PRSS, and pending the final 
    resolution of Reclamation audit recommendations, Western believes the 
    repayment period for flood control should remain at 50 years.
        Comment: Some Contractors have indicated that they believe Western 
    has erred in the application of revenue toward the repayment of 
    investment, specifically with regard to the repayment of the highest 
    interest bearing investments.
        Response: The application of revenue toward repayment of the 
    highest interest bearing debt, as portrayed in the PRSS, is in complete 
    agreement with the ratesetting methodology established by the September 
    15, 1992, Settlement Agreement.
        During the development of the ratesetting methodology, the 
    Contractors were adamant about the amount of investment to be repaid 
    and the order in which these investments were to be repaid. As a 
    result, amortization schedules were developed for each investment which 
    depicted the portion of the investment to be repaid by the end of the 
    current contract period FY 2017. To satisfy the concern expressed by 
    the Contractors that they would not pay more than their share of each 
    specific investment, it was agreed that repayment would be limited to 
    the amount shown on the amortization schedule. Therefore, repayment was 
    to be accomplished by applying revenues toward the retirement of the 
    highest interest bearing investment, up to the limit established by the 
    amortization schedule for the investment.
        In FERC's Order confirming and approving WAPA-58 it stated:
    
        Western adopted the formula rate at the behest of its customers, 
    whose rights to Boulder Canyon Project power expire in 2017. The 
    formula rate is designed to ensure that these customers pay only 
    their fair share of the cost of the facilities whose service lives 
    extend past that year. Rather than prioritize repayment by interest 
    rate, the formula rate amortizes repayment of each financial 
    obligation over the service life of its associated facility. Western 
    and the Contractors state, and we agree, that this method assures 
    intergenerational equity, whereas repayment by interest rate alone 
    could result in the entirety of some Federal investments being paid 
    by pre-2017 customers.
    
        Both Western and Reclamation believe that the application of 
    principal is consistent with the language contained in the Settlement 
    Agreement. Following development of the PRSS, which was based upon the 
    language contained in the Settlement Agreement, Western made a 
    presentation to the BCP Contractors which included a point-by-point 
    analysis of each item in the Settlement Agreement and how the item had 
    been implemented in the PRSS. The application of principal was 
    thoroughly discussed and agreed to. The only disagreement to the 
    application methodology was expressed by a consultant to the Arizona 
    Power Authority (APA)--who was not present during the settlement 
    negotiations (other representatives of the APA who were present during 
    these discussions were in agreement with the methodology proposed by 
    Western).
        Comment: Some Contractors have expressed concern that the increase 
    in the weighted average interest for the Visitor Facilities is in 
    error.
        Response: Reclamation has verified that the weighted average 
    interest rate used for the Visitor Facilities is correct.
        Comment: A customer requests leveling expenditures as much as 
    possible.
        Response: Both Western and Reclamation believe that expenditures 
    should be levelized to the extent possible. Reclamation has taken an 
    extensive look at its O&M and replacements program and in the future 
    will be proposing a more levelized expenditure for these two items. 
    Also, as indicated previously, Reclamation is investigating utilization 
    of a process similar to Western's Ten-Year Engineering Plan process to 
    allow more participative input from the BCP Contractors.
    Programmable Master Supervisory Control System
        Comment: Some Contractors have expressed a concern over the 
    methodology used to allocate the costs associated with the programmable 
    master supervisory control installed at Hoover.
        Response: Optimization modeling studies conducted by Reclamation 
    indicated that the majority of the improvement in operating efficiency 
    will benefit the Contractors at Hoover. Generators at Parker-Davis (P-
    DP) are rarely, if ever, used for load following; therefore, there will 
    be only a moderate improvement in the efficiency of the P-DP system. 
    The major share of plant improvement will benefit Hoover. The 
    allocation of costs among Hoover, Parker, and Davis is reflective of 
    the benefits received at each installation.
    Annual Expense--O&M
        Comment: Some Contractors have requested an explanation of 
    Reclamation's cost item captioned A&GE (nonutility water).
        Response: The Administrative and General Expense budget line 
    includes such items as general expenses (i.e., salaries, surcharges, 
    travel, materials, and supplies); some Regional and Denver 
    administrative charges; services; a portion of security charges; union 
    activities; and equal employment opportunity activities. These items 
    are all associated with BCP administrative activities.
        Comment: Some Contractors expressed concern over the apparent 
    discrepancy in the data presented in the August PRSS, the April 15, 
    1993, letter by Reclamation, and in material presented to the E&OC.
        Response: These issues have been discussed in-depth by Western in 
    its public information data responses. The nature of the documents are 
    such that they cannot be directly comparable. For example, the O&M 
    figures used in the April 15th letter do not include the Civil Service 
    Retirement costs. However, the April 15th letter does include the 
    undelivered orders associated with O&M. The information presented at 
    the E&OC does not include these costs as they are necessary for 
    repayment purposes only, but are not the type of data normally 
    presented for E&OC purposes.
        Comment: Some Contractors have expressed concern that the O&M 
    budget estimates are consistently higher than the actual cost incurred.
        Response: Reclamation has reduced the budget line for Operation by 
    approximately $1 million beginning in FY 1994. This reduction was made 
    because of a reanalysis of historical costs and future requirements. 
    All line items included in the estimated O&M budget will be closely 
    monitored and adjusted, if necessary.
        Comment: An interested party requested an explanation of the 
    reallocation of O&M costs by Reclamation as they relate to the security 
    costs at Hoover.
        Response: This issue was dealt with in detail in the data response 
    prepared following the public information forum. Briefly, that response 
    indicated that all security costs had historically been charged to 
    operations. As a result of the reallocation, beginning in FY 1992, 
    security costs were distributed to Uprating, Visitor Facilities, and 
    Guide Service. The reallocation of the expense associated with the 
    security cost occurred in FY 1992 and therefore, had no impact on any 
    other historical year. The effect of the reallocation has been included 
    in the budget documents which support the FY 1993 PRSS.
    Annual Expense--Replacements
        Comment: Some Contractors have expressed concern over the variation 
    in the projected replacement costs presented in the PRSS.
        Response: This issue has been discussed with the Contractors in 
    detail at both the public information forum and at the most recent E&OC 
    meeting. This issue was also addressed in Rate Order WAPA-58. In 
    addition, both Reclamation and Western are making every effort to 
    stabilize fluctuations in projected replacement costs for the 5-year 
    moving window (cost evaluation period). The constant replacement cost 
    shown after the 5-year window reflects an average of all replacement 
    costs forecasted by Western's replacement study through the end of FY 
    2045.
        Western and Reclamation have agreed to use the replacements study 
    average for the out years in the PRSS. The replacement study represents 
    higher replacement costs at the beginning and end of the repayment 
    period with the in-between years having lower replacement costs.
        Comment: A question was asked as to why undelivered orders for 
    replacements were included in the PRSS and excluded for operations.
        Response: Actual FY 1992 expenditures for the Replacement Program 
    were $5,884,561. For purposes of the PRSS, it was necessary to add the 
    change in Undelivered Orders of $1,651,592 for a total of $7,536,153. 
    The recording of Undelivered Orders (costs incurred with the completion 
    of a material, supplies or services contract, which have not totally 
    been billed to or paid by Reclamation) is consistent with standard 
    governmental accounting practices. When the Undelivered Orders are 
    satisfied, any over/under expenditure of funds will be reflected as a 
    change in future years' Undelivered Orders amount. This process assures 
    that the costs subject to repayment remain accurate without the 
    potential for duplication or omission.
        Comment: The question was asked why contributions for replacements 
    of $659,000 were removed from PRSS revenues and effectively capitalized 
    when actual expenditures for replacements are expensed and not 
    capitalized.
        Response: Because the historical years' data displayed in the PRSS 
    reflects actual generation, revenues, and costs, Reclamation and 
    Western are continuing to correlate the data reflected in the 
    historical years with the actual financial data. As this process has 
    continued, certain adjustments have been and are being made either to 
    the financial records, the PRSS, or to both, to accomplish this 
    correlation. This process is commonly referred to as the ``Crosswalk.'' 
    The adjustment to the PRSS reflects Reclamation's and Western's 
    continuing effort to correlate the data reflected in the historical 
    years to the actual historical financial records.
        Comment: One Contractor indicated that for the purposes of 
    projecting the annual cost associated with future replacements, Western 
    should assume that Reclamation is successful in receiving 
    appropriations, and that the annual cost for replacements should be 
    equal to the amortized cost of replacements beginning with FY 1995.
        Response: With the exception of the investment made for ``air 
    slots,'' Reclamation has historically been unable to obtain 
    appropriations for replacements. To assume that such appropriations 
    could be obtained in the future, when they could not be obtained in the 
    past, would not reflect prudent fiscal responsibility on the part of 
    either Western or Reclamation. Western is required to establish rates 
    which will assure the repayment to Treasury of all costs which are 
    incurred by the project. Therefore, until instructed otherwise by 
    Reclamation, Western will continue to portray the costs associated with 
    replacements as an annual expense.
        Comment: One Contractor submitted a report to Reclamation 
    specifically addressing the levelization of replacement spending at the 
    BCP by Reclamation.
        Response: Reclamation discussed the issue of stabilizing 
    replacement costs at the most recent E&OC meeting held during November 
    1993. Reclamation and Western are making every effort to stabilize the 
    fluctuations in the projected replacement costs.
    Expenses--Other Expenses
        Comment: Some Contractors requested further explanation of the 
    increases from the prior PRSS in both Other Revenues, column 16, and 
    Other Expenses, column 3.
        Response: Other Revenues, column 16, reflects revenues collected 
    through the guide service (tours), and must be sufficient to recover 
    the costs of providing that service. On January 1, 1993, Reclamation 
    increased the fee for guide service from $1 to $2. Further increases in 
    guide service fees are anticipated in conjunction with the new Visitor 
    Facilities.
        Other Expenses, column 3, also reflect the costs of unfunded Civil 
    Service Retirement, multiproject costs, as well as increased costs in 
    providing the guide service. Considerable detail has been provided to 
    the BCP Contractors on all of these issues. In addition, the issue of 
    multiproject costs is one of the items being discussed in the current 
    draft Settlement Agreement negotiations. As part of the Settlement 
    Agreement, which is yet unsigned, Western has agreed to prepare 
    detailed procedures for the calculation of multiproject costs and to 
    prepare and present to the BCP E&OC all revisions to multiproject 
    costs, prior to their insertion into future PRSS. In addition, 
    Western's Phoenix Area Office (PAO), as part of a quality improvement 
    initiative, formed a Process Improvement Team which has recently 
    prepared a report on the multiproject cost process. Once the report has 
    been reviewed by the PAO Quality Council, any accepted recommendations 
    will be reflected in future calculations of multiproject costs.
        Comment: A Contractor contends that multiproject costs for FY 1993 
    and FY 1994 should be removed from the revenue requirements for the BCP 
    because agreed-upon procedures, analyses, and justification have yet to 
    be developed. Also, new rates for the other projects have not been 
    implemented to reflect additional revenues from BCP and the financial 
    records for the BCP do not indicate that monies collected were actually 
    transferred to P-DP or Pacific-Northwest Pacific-Southwest Intertie 
    Project in FY 1993.
        Comment: Regarding column 3, Other Revenues, a Contractor believes 
    Western's estimate of multiproject costs of $442,016 for FY 1993 should 
    be deleted since the P-DP and the Pacific-Northwest Pacific-Southwest 
    Intertie Project will not begin to reflect multiproject benefits in 
    their rates until FY 1994.
        Response: Column 3 is entitled Other Expenses, not Other Revenues. 
    Western believes that the FY 1993 expenditure of $442,016 is proper, 
    because the current P-DP and Pacific-Northwest Pacific-Southwest 
    Intertie Project's rate studies reflect revenue transfers of this 
    amount from BCP in FY 1993. The appropriate revenue transfers have been 
    made in all three projects, beginning in FY 1993.
    Working Capital
        Comment: In Rate Order No. WAPA-58, Western and Reclamation agreed 
    to make the sum of column 6, Working Capital, and the carry-over 
    balance of FY 1992, equal to $7.5 million. The sum of Working Capital 
    and the carry-over balance in the August PRSS equals $7,846,238. The 
    customer believes that a $346,238 reduction is in order.
        Comment: Several questions have been raised with regard to the 
    issue of working capital already recovered by Western and Reclamation.
        Comment: Several Contractors asked if the working capital fund 
    would be returned to the Contractors at the end of the contract period. 
    They also requested that the $5 million PRSS to CRDF adjustment be 
    treated as part of the working capital balance.
        Response: Western will make adjustments to the PRSS to ensure that 
    the sum of the ``carry-over balance'' and ``working capital'' equals 
    $7.5 million. Western has always intended that all working capital 
    would be returned to the BCP Contractors and the PRSS has been revised 
    accordingly.
        While Western and Reclamation are not in agreement with the BCP 
    Contractors that the $5 million PRSS to CRDF adjustment is part of the 
    working capital balance, they are both in agreement that any monies 
    left over in the Colorado River Dam Fund at the end of the current 
    contract period will be refunded to the current BCP Contractors. The 
    issue related to this adjustment should tend to resolve itself as the 
    lag between the delivery of power and subsequent billing and collection 
    for the power sale is reduced. The adjustment is necessary to prevent 
    the PRSS from applying revenues toward repayment which are not 
    available to the CRDF as a result of the lag in collection. This 
    adjustment is unrelated to the working capital fund.
        Comment: A working capital allowance is not needed to operate the 
    project.
        Response: The February 13, 1992, letter sent to Western and 
    Reclamation by the Colorado River Commission of Nevada, on behalf of 
    all the BCP Contractors indicated that a working capital fund of $7.5 
    million should be created. Western and Reclamation created a mechanism 
    whereby this fund would be created through rates in 1993 and 1994. This 
    mechanism was modified by the BCP Contractors, Western, and Reclamation 
    and incorporated into Rate Order WAPA-58, which recently received 
    approval from FERC.
    Engineering and Oversight Committee
        Comment: Several Contractors maintain that it is critical that the 
    E&OC continue to function and thrive and that Western, Reclamation, and 
    the BCP Contractors continue to strengthen the communication processes 
    of the E&OC in order to provide the BCP Contractors the opportunity and 
    means to provide input to Western and Reclamation on issues relating to 
    BCP.
        Response: Western and Reclamation agree that the E&OC should 
    continue to function and provide a meaningful communication process 
    among the BCP Contractors, Reclamation and Western. The continuation of 
    the E&OC, along with an expansion of functions to be undertaken by the 
    E&OC, is one of the issues being negotiated in the Settlement Agreement 
    negotiations among the BCP Contractors, Western and Reclamation.
        Comment: A Contractor has indicated that the E&OC could be a forum 
    to discuss ways to handle Hoover's resources in a changing operating 
    environment and that a real effort could be made towards developing 
    principles of a rate process that are mutually agreeable to all 
    parties.
        Response: Several BCP Contractors have made statements, both at 
    rate forums and E&OC meetings, that the E&OC is not meant to be a 
    substitute for the review of data in a rate process. While Western and 
    Reclamation support the efforts of the E&OC and are willing to work 
    with the BCP Contractors to improve the operation and to lower the 
    costs of the BCP, they are both in agreement that the efforts of the 
    E&OC should be complementary and supportive to the rate process, and 
    not a part of the rate process.
    Uprating Credits
        Comment: The proposed PRSS does not address the credit carry 
    forward incurred after May 19, 1992. The mechanism for repaying such 
    credit carry forward should be established and expressed in the PRSS. 
    (In reference to amount financed by the APA bond issue * * *) Western 
    will be paying interest on the APA bond issue which covered credit 
    carry forward. It would be inequitable to pay such interest to APA and 
    not to the other Schedule B Contractors.
        Response: The proposed PRSS does address the credit carry forward 
    incurred after May 19, 1992. The ``Group 3'' debt that was created in 
    order to pay ``Group 1'' and ``Group 2'' debt is reflected in the 
    Uprating Credits for FY 1995, 1996, and 1997. One third of this ``Group 
    3'' debt will be recovered in each of the years 1995, 1996, and 1997. 
    The ``Group 4'' debt, which is the amount of Uprating Credits that 
    certain of the Schedule B Contractors cannot take because their billed 
    amount for electric service is less than their Uprating Credits, is 
    reflected in the annual Uprating Credit amounts. (The amount of 
    Uprating Credits shown in column 4 of the PRSS is exactly equal to the 
    total of all the Uprating Credit schedules submitted by the Schedule B 
    Contractors--which is exactly equal to the Uprating Credits applied to 
    power bills plus monies retained by Reclamation to satisfy ``Group 4'' 
    debt.)
        In regard to the amount financed by the APA bond issue, or any 
    other bond issue, Western is bound by contract to issue credits in the 
    amounts submitted by the Contractors for Uprating Credits. While it is 
    true that Western is in effect paying interest on credit-carry-forward 
    debt for APA and not for other Schedule B Contractors, the other 
    Schedule B Contractors who issued bonds could go through the same 
    refinancing process that APA did and obtain interest on their carry-
    forward debt. The Schedule B Contractors who did not issue bonds could 
    not utilize this mechanism to obtain interest on their portion of 
    carry-forward debt.
        In order to obtain and proceed with a unified position, in regard 
    to the payment of interest on credit-carry-forward debt, Western issued 
    a position paper on December 17, 1993, which proposed a methodology for 
    payment of interest on credit-carry-forward debt. Once all BCP 
    Contractors have responded, Western will issue either a final unified 
    position statement (if all BCP Contractors are in agreement) or a 
    summary of position statements (if one or more of the BCP Contractors 
    are not in agreement).
        Comment: Review and make adjustments as appropriate to the future 
    uprate credit payments.
        Response: According to section 6.5.5 of the BCP contracts, by 
    October 1 of each year, the Schedule B Contractors are to provide 
    Western and Reclamation with a credit schedule with respect to each 
    billing period for the remaining term of the contract. The Uprating 
    Credit payments utilized in the PRSS are a summation of the individual 
    schedules sent to Western by the Schedule B Contractors and are the 
    same schedules utilized by Western in determining the credits to apply 
    to the individual monthly power bills.
        Comment: Western should follow through with the establishment of 
    procedures which assure that the determination and application of 
    Uprating Credits is consistent with the electric service contract.
        Response: Western believes that it is currently adhering to the 
    provisions of the electric service contracts in regard to the 
    determination of Uprating Credits, the application of said credits, and 
    the overall administration of the Uprating Credit program.
    Total Energy Sales
        Comment: What is the rationale for the increase from an annual 
    constant of 4,062,000 MWh to 4,552,000 MWh for the period 1999-2045?
        Response: The generation shown during the cost evaluation period is 
    based upon the most current hydrology studies conducted in support of 
    the PRSS. The generation shown beyond the cost evaluation period 
    reflects the contract amount of 4,527,001 MWh. The generation level of 
    4,552,000 MWh was given to Western in error.
    Visitor Facilities
        Comment: A recommendation was made that Reclamation develop and 
    implement plans to obtain additional funds from sources other than the 
    BCP Contractors.
        Response: Reclamation is continuing to explore and evaluate a 
    variety of options which may provide additional revenue that could be 
    used to aid in the repayment of the Visitor Facilities costs.
        Comment: A recommendation was made that the amount included in the 
    estimated completion cost of the Visitor Facilities for anticipated 
    claims by the construction Contractor be removed from the repayment 
    obligation of the BCP Contractor.
        Response: Reclamation instructions require that the total estimated 
    cost of the project be shown. This includes such items as anticipated 
    claims and modifications. Reclamation's Commissioner has requested a 
    full audit of the Visitor Facilities costs. Once that audit is 
    completed, Western will evaluate appropriate changes, if any, to those 
    costs.
    Environmental Evaluation
        In compliance with the National Environmental Policy Act of 1969, 
    42 U.S.C. 4321 et seq.; Council on Environmental Quality Regulations 
    (40 CFR Part 1500-1508); and DOE NEPA Regulations (10 CFR part 1021), 
    Western has determined that this action is categorically excluded from 
    the preparation of an environmental assessment or EIS.
    
    Executive Order 12866
    
        DOE has determined that this is not a significant regulatory action 
    because it does not meet the criteria of Executive Order 12866, 58 FR 
    51735. Western has an exemption from centralized regulatory review 
    under Executive Order 12866; accordingly, no clearance of this notice 
    by OMB is required.
    
    Availability of Information
    
        Information regarding this rate adjustment, including PRSS, 
    comments, letters, memorandums, and other supporting material made or 
    kept by Western for the purpose of developing the power rates, is 
    available for public review in the Phoenix Area Office, Western Area 
    Power Administration, Office of the Assistant Area Manager for Power 
    Marketing, 615 South 43rd Avenue, Phoenix, Arizona 89009; Western Area 
    Power Administration, Division of Marketing and Rates, 1627 Cole 
    Boulevard, Golden, Colorado 80401; and Western Area Power 
    Administration, Office of the Assistant Administrator for Washington 
    Liaison, Power Marketing Liaison Office, Room 8G-027, Forrestal 
    Building, 1000 Independence Avenue SW., Washington, DC 20585.
    
    Submission to Federal Energy Regulatory Commission
    
        The BCP rates herein are approved and placed into effect by the 
    Administrator of Western. An informational copy will be submitted to 
    FERC.
    
    Order
    
        In view of the foregoing and pursuant to the authority delegated to 
    me by the Secretary, I confirm and approve, effective February 1, 1994, 
    Rate Schedule BCP-F4/2.
    
        Issued in Golden, CO, February 4, 1994.
    William H. Clagett,
    Administrator.
    
        Approved for Legal Sufficiency.
    Michael S. Hacskaylo,
    General Counsel.
    
    Boulder Canyon Project; Schedule of Rates for Power Service
    
        Effective (In accordance with approved ratesetting methodology): 
    February 1, 1994, that being the first day of the February 1994 billing 
    period.
        Available: In the marketing area served by the Boulder Canyon 
    Project (BCP).
        Applicable: To power customers served by the BCP supplied through 
    one meter at one point of delivery, unless otherwise provided by 
    contract.
        Character and Conditions of Service: Alternating current at 60 
    hertz, three-phase, delivered and metered at the voltages and points 
    established by contract.
        Monthly Rate: The base charge capacity rate is $1.07/kW/month for 
    each kW of rated capacity to which each contractor is entitled by 
    contract during the billing period.
        The base charge energy rate is 6.31 mills/kWh for each kWh measured 
    or scheduled at the point of delivery during the billing period, except 
    for purchased power.
        Lower Basin Development Fund Contribution Charge: The Lower Basin 
    Development Fund Contribution Charge is 4.5 mills/kWh for each kWh 
    measured or scheduled to an Arizona purchaser and 2.5 mills/kWh for 
    each kWh measured or scheduled to a California or Nevada purchaser, 
    except for purchased power.
        Billing for Unauthorized Overruns: For each billing period in which 
    there is a contract violation involving an unauthorized overrun of the 
    contractual power obligations, such overruns shall be billed at 10 
    times the above base charge energy and capacity rates. The Lower Basin 
    Development Fund Contribution Charge shall be applied also to each kWh 
    of overrun.
        Adjustments: None.
    
    [FR Doc. 94-5142 Filed 3-4-94; 8:45 am]
    BILLING CODE 6450-01-P
    
    
    

Document Information

Effective Date:
2/1/1994
Published:
03/07/1994
Department:
Western Area Power Administration
Entry Type:
Uncategorized Document
Action:
Notice of rate order--Boulder Canyon Project annual power rate adjustment.
Document Number:
94-5142
Dates:
Rate Schedule BCP-F4/2 will be placed into effect beginning on February 1, 1994.
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: March 7, 1994