96-5336. Duquesne Light Company, et al.; Electric Rate and Corporate Regulation Filings  

  • [Federal Register Volume 61, Number 46 (Thursday, March 7, 1996)]
    [Notices]
    [Pages 9154-9156]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-5336]
    
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. ER96-1152-000, et al.]
    
    
    Duquesne Light Company, et al.; Electric Rate and Corporate 
    Regulation Filings
    
    March 1, 1996.
        Take notice that the following filings have been made with the 
    Commission:
    
    [[Page 9155]]
    
    1. Duquesne Light Company
    
    [Docket No. ER96-1152-000]
    
        Take notice that on February 23, 1996, Duquesne Light Company (DLC) 
    filed a Service Agreement dated January 26, 1996, with Aqulia Power 
    Corporation under DLC's FERC Coordination Sales Tariff (Tariff). The 
    Service Agreement adds Aqulia Power Corporation as a customer under the 
    Tariff. DLC requests an effective date of February 15, 1996, for the 
    Service Agreement.
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    2. Niagara Mohawk Power Corporation
    
    [Docket No. ER96-1153-000]
    
        Take notice that on February 23, 1996, Niagara Mohawk Power 
    Corporation (Niagara Mohawk), tendered for filing an agreement between 
    Niagara Mohawk and K N Marketing Inc. (K N) dated February 12, 1996 
    providing for certain transmission services to K N.
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    3. PacifiCorp
    
    [Docket No. ER96-1154-000]
    
        Take notice that on February 23, 1996, PacifiCorp, tendered for 
    filing in accordance with 18 CFR Part 35 of the Commission's Rules and 
    Regulations, Service Agreements with AIG Trading Corporation (AIG), 
    Emerald People's Utility District (Emerald), Industrial Energy 
    Applications Inc. (Industrial), City of Gillette (Gillette), Flathead 
    Electric Cooperative Inc. (Flathead), K N Marketing, Inc. (KNMI), 
    Roseville Electric Dept. (Roseville), Valley Electric Association Inc. 
    (Valley) and Wyoming Municipal Power Agency (WMPA) under, PacifiCorp's 
    FERC Electric Tariff, Second Revised Volume No. 3, Service Schedule 
    PPL-3.
        Copies of this filing were supplied to AIG, Emerald, Industrial, 
    Gillette, Flathead, KNMI, Roseville, Valley, WMPA, the Washington 
    Utilities and Transportation Commission and the Public Utility 
    Commission of Oregon.
        A copy of this filing may be obtained from PacifiCorp's Regulatory 
    Administration Department's Bulletin Board System through a personal 
    computer by calling (503) 464,6122 (9600 baud, 8 bits, no parity, 1 
    stop bit).
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    4. Wisconsin Power and Light Company
    
    [Docket No. ER96-1155-000]
    
        Take notice that on February 23, 1996, Wisconsin Power and Light 
    Company (WP&L), tendered for filing an Agreement dated February 19, 
    1996, establishing Tennessee Power Company as a customer under the 
    terms of WP&L's Point-to-Point Transmission Tariff.
        WP&L requests an effective date of February 19, 1996 and 
    accordingly seeks waiver of the Commission's notice requirements. A 
    copy of this filing has been served upon the Public Service Commission 
    of Wisconsin.
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    5. MidAmerican Energy Company
    
    [Docket No. ER96-1157-000]
    
        Take notice that on February 23, 1996, MidAmerican Energy Company 
    (MidAmerican), filed with the Commission Firm Transmission Service 
    Agreements with Louis Dreyfus Electric Power Inc. (Dreyfus) dated 
    January 26, 1996, JPower Inc. (JPower) dated February 5, 1996 and Catex 
    Vitol Electric, L.C.C. (Catex Vitol) dated February 7, 1996; and Non-
    Firm Transmission Service Agreements with Dreyfus dated January 26, 
    1996, JPower dated February 5, 1996 and Catex Vitol dated February 7, 
    1996, entered into pursuant to MidAmerican's Point-to-Point 
    Transmission Service Tariff, FERC Electric Tariff, Original Volume No. 
    4.
        MidAmerican requests an effective date of January 26, 1996, for the 
    Agreements with Dreyfus, February 5, 1996 for the Agreements with 
    JPower, and February 7, 1996, for the Agreements with Catex Vitol, and 
    accordingly seeks a waiver of the Commission's notice requirement. 
    MidAmerican has served a copy of the filing on Dreyfus, JPower, Catex 
    Vitol, the Iowa Utilities Board, the Illinois Commerce Commission and 
    the South Dakota Public Utilities Commission.
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    6. Consolidated Edison Company of New York, Inc.
    
    [Docket No. ER96-1158-000]
    
        Take notice that on February 23, 1996, Consolidated Edison Company 
    of New York, Inc. (Con Edison), tendered for filing an agreement with 
    Morgan Stanley Capital Group, Inc. (MSCGI) to provide for the sale of 
    energy and capacity. For energy the ceiling rate is 100 percent of the 
    incremental energy cost plus up to 10 percent of the SIC (where such 10 
    percent is limited to 1 mill per Kwhr when the SIC in the hour reflects 
    a purchased power resource). The ceiling rate for capacity is $7.70 per 
    megawatt hour. Energy and capacity sold by MSCGI will be at market-
    based rates.
        Con Edison states that a copy of this filing has been served by 
    mail upon MSCGI.
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    7. Tampa Electric Company
    
    [Docket No. ER96-1159-000]
    
        Take notice that on February 23, 1996, Tampa Electric Company 
    (Tampa Electric), tendered for filing service agreements with the 
    Utilities Commission, City of New Smyrna Beach (New Smyrna Beach) 
    providing for firm transmission service under Tampa Electric's point-
    to-point transmission service tariff.
        Tampa Electric proposes an effective date of March 1, 1996 for the 
    service agreement and therefore requests waiver of the Commission's 
    notice requirements.
        Copies of the filing have been served on New Smyrna Beach and the 
    Florida Public Service Commission.
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    8. Florida Power & Light Company
    
    [Docket No. ER96-1160-000]
    
        Take notice that on February 23, 1996, Florida Power & Light 
    Company (FPL) filed the Contract for Purchases and Sales of Power and 
    Energy between FPL and Valero Power Services Company. FPL requests an 
    effective date of March 4, 1996.
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    9. Boston Edison Company
    
    [Docket No. ER96-1161-000]
    
        Take notice that on February 23, 1996, Boston Edison Company 
    (Edison) of Boston, Massachusetts, filed an All-Requirements Service 
    Agreement dated January 31, 1996 between Edison and the Massachusetts 
    Port Authority (Authority). Under the terms of the Agreement, Edison 
    will provide the Authority all-requirements service as that service is 
    defined in the Agreement. Edison asks that the Agreement be allowed to 
    become effective as a rate schedule as of November 1, 1995, consistent 
    with the Commission's policy as stated in Central Hudson Gas & Electric 
    Corporation, et al., 60 FERC para. 61,106 at 61,338 (August 3, 1992).
        Edison states that this filing has been posted as required by the 
    Commission's Regulations. Edison states that it has
    
    [[Page 9156]]
    
    filed the Agreement with the consent of the Authority as evidenced by 
    the Authority's execution of the Agreement. Edison further states that 
    it has served the filing on the affected customer and upon the 
    Massachusetts Department of Public Utilities.
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    10. New England Power Company
    
    [Docket No. ER96-1162-000]
    
        Take notice that on February 26, 1996, New England Power Company 
    (NEP) submitted for filing a letter agreement to provide non-firm 
    transmission service over NEP's transmission system to KCS Power 
    Marketing, Inc.
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    11. Wisconsin Electric Power Company
    
    [Docket No. ER96-1163-000]
    
        Take notice that on February 26, 1996, Wisconsin Electric Power 
    Company (Wisconsin Electric) tendered for filing an Electric Service 
    Agreement between itself and J Power. The Electric Service Agreement 
    provides for service under Wisconsin Electric's Coordination Sales 
    Tariff.
        Wisconsin Electric requests an effective date of February 1, 1996, 
    to allow for economic transactions and accordingly seeks waiver of the 
    Commission's notice requirements. Copies of the filing have been served 
    on J Power, the Public Service Commission of Wisconsin and the Michigan 
    Public Service Commission.
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    12. UtiliCorp United Inc.
    
    [Docket No. ER96-1164-000]
    
        Take notice that on February 26, 1996, UtiliCorp United Inc., 
    tendered for filing on behalf of its operating division, Missouri 
    Public Service, a Service Agreement under its Power Sales Tariff, FERC 
    Electric Tariff Original Volume No. 10, with Illinois Power Company. 
    The Service Agreement provides for the sale of capacity and energy by 
    Missouri Public Service to Illinois Power Company pursuant to the 
    tariff.
        UtiliCorp also has tendered for filing a Certificate of Concurrence 
    by Illinois Power Company.
        UtiliCorp requests waiver of the Commission's Regulations to permit 
    the Service Agreement to become effective in accordance with its terms.
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    13. Boston Edison Company
    
    [Docket No. ER96-1165-000]
    
        Take notice that on February 26, 1996, Boston Edison Company 
    (Boston Edison), tendered for filing a Service Agreement and Appendix A 
    under Original Volume No. 6, Power Sales and Exchange Tariff (Tariff) 
    for Global Petroleum Corp. (Global). Boston Edison requests that the 
    Service Agreement become effective as of February 1, 1996.
        Edison states that it has served a copy of this filing on Global 
    and the Massachusetts Department of Public Utilities.
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    14. Consolidated Edison Company of New York, Inc. )
    
    [Docket No. ER96-1166-000]
    
        Take notice that on February 26, 1996, Consolidated Edison Company 
    of New York, Inc. (Con Edison), tendered for filing an agreement with 
    Sonat Power Marketing, Inc. (Sonat) to provide for the sale of energy 
    and capacity. For energy the ceiling rate is 100 percent of the 
    incremental energy cost plus up to 10 percent of the SIC (where such 10 
    percent is limited to 1 mill per Kwhr when the SIC in the hour reflects 
    a purchased power resource). The ceiling rate for capacity is $7.70 per 
    megawatt hour. Energy and capacity sold by Sonat will be at market-
    based rates.
        Con Edison states that a copy of this filing has been served by 
    mail upon Sonat.
        Comment date: March 15, 1996, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    Standard Paragraph
    
        E. Any person desiring to be heard or to protest said filing should 
    file a motion to intervene or protest with the Federal Energy 
    Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, 
    in accordance with Rules 211 and 214 of the Commission's Rules of 
    Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such 
    motions or protests should be filed on or before the comment date. 
    Protests will be considered by the Commission in determining the 
    appropriate action to be taken, but will not serve to make protestants 
    parties to the proceeding. Any person wishing to become a party must 
    file a motion to intervene. Copies of this filing are on file with the 
    Commission and are available for public inspection.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 96-5336 Filed 3-6-96; 8:45 am]
    BILLING CODE 6717-01-P
    
    

Document Information

Published:
03/07/1996
Department:
Energy Department
Entry Type:
Notice
Document Number:
96-5336
Dates:
March 15, 1996, in accordance with Standard Paragraph E at the end of this notice.
Pages:
9154-9156 (3 pages)
Docket Numbers:
Docket No. ER96-1152-000, et al.
PDF File:
96-5336.pdf