98-5944. Texas Utilities Electric; Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing  

  • [Federal Register Volume 63, Number 45 (Monday, March 9, 1998)]
    [Notices]
    [Pages 11458-11460]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-5944]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket Nos. 50-445 and 50-446]
    
    
    Texas Utilities Electric; Notice of Consideration of Issuance of 
    Amendment to Facility Operating License, Proposed No Significant 
    Hazards Consideration Determination, and Opportunity for a Hearing
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an amendment to Facility Operating License Nos. 
    NPF-87 and NPF-89, issued to Texas Utilities Electric Company, (TU 
    Electric, the licensee), for operation of the Comanche Peak Steam 
    Electric Station, Units 1 and 2, located in Somervell County, Texas.
        The proposed amendment would be a temporary change to the Technical 
    Specifications to remove the requirement to demonstrate the load 
    shedding feature of MCC XEB4-3 as part of Surveillance Requirements 
    (SRs) 4.8.1.1.2f.4)(a) and 4.8.1.1.2f.6)(a) until the plant startup 
    subsequent to the next refueling outage or until the next outage 
    greater than 24 hours in duration for each respective unit. This 
    temporary change is requested as a result of the failure to confirm the 
    load shedding feature of MCC XEB4-3 during the performance of these SRs 
    for the Unit 1 and Unit 2 train B diesel generators (DGs). This was 
    reported promptly to the NRC at the time of discovery and prompt action 
    to remedy the situation was taken.
        The licensee requested a Notice of Enforcement Discretion (NOED) by 
    letter dated February 20, 1998. The NRC orally issued the NOED at 4:49 
    pm EST on February 20, 1998, to allow the facility to continue 
    operation while the TS is processed. Pursuant to the NRC's policy 
    regarding exercise of discretion for an operating facility, set out in 
    Section VII.c, of the ``General Statement of Policy and Procedures for 
    NRC Enforcement Actions'' (Enforcement Policy), NUREG-1600, the letter 
    documenting the issuance of the NOED was dated February 24, 1998. The 
    NOED was to be effective for the period of time it takes the NRC staff 
    to process the proposed change to the TSs on an exigent bases.
        Before issuance of the proposed license amendment, the Commission 
    will have made findings required by the Atomic Energy Act of 1954, as 
    amended (the Act) and the Commission's regulations.
        Pursuant to 10 CFR 50.91(a)(6) for amendments to be granted under 
    exigent circumstances, the NRC staff must determine that the amendment 
    request involves no significant hazards consideration. Under the 
    Commission's regulations in 10 CFR 50.92, this means that operation of 
    the facility in accordance with the proposed amendment would not (1) 
    Involve a significant increase in the probability or consequences of an 
    accident previously evaluated; or (2) create the possibility of a new 
    or different kind of accident from any accident previously evaluated; 
    or (3) involve a significant reduction in a margin of safety. As 
    required by 10 CFR 50.91(a), the licensee has provided its analysis of 
    the issue of no significant hazards consideration, which is presented 
    below:
    
        1. Do the proposed changes involve a significant increase in the 
    probability or consequences of an accident previously evaluated?
        The only potential impact of operating without having 
    demonstrated the load shedding feature of MCC XEB4-3 is the 
    potential that the train B DG for either CPSES Unit 1 or Unit 2 will 
    not be able to perform its safety function following a postulated 
    accident or event. TU Electric has evaluated the potential load 
    added to the DGs if this bus does not shed and has concluded that 
    the DGs remain fully capable of performing their safety function. As 
    a result, there is no significant increase in the probability or 
    consequences of an accident previously evaluated.
        2. Do the proposed changes create the possibility of a new or 
    different kind of accident from any accident previously evaluated?
    
    [[Page 11459]]
    
        Operation without having tested the load shedding feature of bus 
    XEB4-3 does not effect the operation or design of the Units and 
    therefore cannot create the possibility of a new or different kind 
    of accident from any accident previously evaluated.
        3. Do the proposed changes involve a significant reduction in a 
    margin of safety?
        Because the diesel generators remain fully capable of performing 
    their safety functions without having demonstrated the load shedding 
    feature of MCC XEB4-3, there is no significant reduction in a margin 
    of safety.
    
        The NRC staff has reviewed the licensee's analysis and, based on 
    this review, it appears that the three standards of 10 CFR 50.92(c) are 
    satisfied. Therefore, the NRC staff proposes to determine that the 
    amendment request involves no significant hazards consideration.
        The Commission is seeking public comments on this proposed 
    determination. Any comments received within 14 days after the date of 
    publication of this notice will be considered in making any final 
    determination.
        Normally, the Commission will not issue the amendment until the 
    expiration of the 14-day notice period. However, should circumstances 
    change during the notice period, such that failure to act in a timely 
    way would result, for example, in derating or shutdown of the facility, 
    the Commission may issue the license amendment before the expiration of 
    the 14-day notice period, provided that its final determination is that 
    the amendment involves no significant hazards consideration. The final 
    determination will consider all public and State comments received. 
    Should the Commission take this action, it will publish in the Federal 
    Register a notice of issuance. The Commission expects that the need to 
    take this action will occur very infrequently.
        Written comments may be submitted by mail to the Chief, Rules and 
    Directives Branch, Division of Administrative Services, Office of 
    Administration, U.S. Nuclear Regulatory Commission, Washington, DC 
    20555-0001, and should cite the publication date and page number of 
    this Federal Register notice. Written comments may also be delivered to 
    Room 6D59, Two White Flint North, 11545 Rockville Pike, Rockville, 
    Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. Copies of 
    written comments received may be examined at the NRC Public Document 
    Room, the Gelman Building, 2120 L Street, NW., Washington, DC.
        The filing of requests for hearing and petitions for leave to 
    intervene is discussed below.
        By April 8, 1998, the licensee may file a request for a hearing 
    with respect to issuance of the amendment to the subject facility 
    operating license and any person whose interest may be affected by this 
    proceeding and who wishes to participate as a party in the proceeding 
    must file a written request for a hearing and a petition for leave to 
    intervene. Requests for a hearing and a petition for leave to intervene 
    shall be filed in accordance with the Commission's ``Rules of Practice 
    for Domestic Licensing Proceedings'' in 10 CFR Part 2. Interested 
    persons should consult a current copy of 10 CFR 2.714 which is 
    available at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document room located at the University of Texas at Arlington Library, 
    Government Publications/Maps, 702 College, P.O. Box 19497, Arlington, 
    TX 76019. If a request for a hearing or petition for leave to intervene 
    is filed by the above date, the Commission or an Atomic Safety and 
    Licensing Board, designated by the Commission or by the Chairman of the 
    Atomic Safety and Licensing Board Panel, will rule on the request and/
    or petition; and the Secretary or the designated Atomic Safety and 
    Licensing Board will issue a notice of hearing or an appropriate order.
        As required by 10 CFR 2.714, a petition for leave to intervene 
    shall set forth with particularity the interest of the petitioner in 
    the proceeding, and how that interest may be affected by the results of 
    the proceeding. The petition should specifically explain the reasons 
    why intervention should be permitted with particular reference to the 
    following factors: (1) The nature of the petitioner's right under the 
    Act to be made a party to the proceeding; (2) the nature and extent of 
    the petitioner's property, financial, or other interest in the 
    proceeding; and (3) the possible effect of any order which may be 
    entered in the proceeding on the petitioner's interest. The petition 
    should also identify the specific aspect(s) of the subject matter of 
    the proceeding as to which petitioner wishes to intervene. Any person 
    who has filed a petition for leave to intervene or who has been 
    admitted as a party may amend the petition without requesting leave of 
    the Board up to 15 days prior to the first prehearing conference 
    scheduled in the proceeding, but such an amended petition must satisfy 
    the specificity requirements described above.
        Not later than 15 days prior to the first prehearing conference 
    scheduled in the proceeding, a petitioner shall file a supplement to 
    the petition to intervene which must include a list of the contentions 
    which are sought to be litigated in the matter. Each contention must 
    consist of a specific statement of the issue of law or fact to be 
    raised or controverted. In addition, the petitioner shall provide a 
    brief explanation of the bases of the contention and a concise 
    statement of the alleged facts or expert opinion which support the 
    contention and on which the petitioner intends to rely in proving the 
    contention at the hearing. The petitioner must also provide references 
    to those specific sources and documents of which the petitioner is 
    aware and on which the petitioner intends to rely to establish those 
    facts or expert opinion. Petitioner must provide sufficient information 
    to show that a genuine dispute exists with the applicant on a material 
    issue of law or fact. Contentions shall be limited to matters within 
    the scope of the amendment under consideration. The contention must be 
    one which, if proven, would entitle the petitioner to relief. A 
    petitioner who fails to file such a supplement which satisfies these 
    requirements with respect to at least one contention will not be 
    permitted to participate as a party.
        Those permitted to intervene become parties to the proceeding, 
    subject to any limitations in the order granting leave to intervene, 
    and have the opportunity to participate fully in the conduct of the 
    hearing, including the opportunity to present evidence and cross-
    examine witnesses.
        If the amendment is issued before the expiration of the 30-day 
    hearing period, the Commission will make a final determination on the 
    issue of no significant hazards consideration. If a hearing is 
    requested, the final determination will serve to decide when the 
    hearing is held.
        If the final determination is that the amendment request involves 
    no significant hazards consideration, the Commission may issue the 
    amendment and make it immediately effective, notwithstanding the 
    request for a hearing. Any hearing held would take place after issuance 
    of the amendment.
        If the final determination is that the amendment request involves a 
    significant hazards consideration, any hearing held would take place 
    before the issuance of any amendment.
        A request for a hearing or a petition for leave to intervene must 
    be filed with the Secretary of the Commission, U.S. Nuclear Regulatory 
    Commission, Washington, DC 20555-0001, Attention: Rulemakings and 
    Adjudications Staff, may be delivered to the Commission's Public 
    Document Room, the Gelman
    
    [[Page 11460]]
    
    Building, 2120 L Street, NW., Washington, DC, by the above date. A copy 
    of the petition should also be sent to the Office of the General 
    Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, 
    and to George L. Edgar, Esq., Morgan, Lewis and Bockius, 1800 M Street, 
    N.W., Washington, DC 20036, attorney for the licensee.
        Nontimely filings of petitions for leave to intervene, amended 
    petitions, supplemental petitions and/or requests for hearing will not 
    be entertained absent a determination by the Commission, the presiding 
    officer or the presiding Atomic Safety and Licensing Board that the 
    petition and/or request should be granted based upon a balancing of the 
    factors specified in 10 CFR 2.714(a)(1)(i)-(v) and 2.714(d).
        For further details with respect to this action, see the 
    application for amendment dated February 25, 1998, which is available 
    for public inspection at the Commission's Public Document Room, the 
    Gelman Building, 2120 L Street, NW., Washington, DC, and at the local 
    public document room, located at the University of Texas at Arlington 
    Library, Government Publications/Maps, 702 College, P.O. Box 19497, 
    Arlington, TX 76019.
    
        Dated at Rockville, Maryland, this 3rd day of March 1998.
    
        For the Nuclear Regulatory Commission.
    Timothy J. Polich,
    Project Manager, Project Directorate IV-1, Division of Reactor Projects 
    III/IV, Office of Nuclear Reactor Regulation.
    [FR Doc. 98-5944 Filed 3-6-98; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
03/09/1998
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
98-5944
Pages:
11458-11460 (3 pages)
Docket Numbers:
Docket Nos. 50-445 and 50-446
PDF File:
98-5944.pdf