99-7982. Notice of Extension of Time To File Comments, Recommendations, Terms and Conditions, and Prescriptions for License Application  

  • [Federal Register Volume 64, Number 62 (Thursday, April 1, 1999)]
    [Notices]
    [Pages 15740-15741]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-7982]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    
    
    Notice of Extension of Time To File Comments, Recommendations, 
    Terms and Conditions, and Prescriptions for License Application
    
    March 26, 1999.
        Take notice that the time limit for filing comments, 
    recommendations, terms and conditions, and prescriptions for the 
    following hydroelectric license applicaiton has been extended from 
    March 26, 1999 to May 26, 1999. The extension was requested by the 
    Vermont Department of Environmental Conservation to continue pursuing 
    consensus of all the parties on measures needed to protect the 
    environment, and no party has objected to a 60-day extension:
        a. Type of Application: New Major License.
        b. Project No.: 2731-020.
        c. Date Filed: May 27, 1998.
        d. Applicant: Central Vermont Public Service Corporation.
        e. Name of Project: Weybridge Project.
        f. Location: On Otter Creek, at river mile 19.5 from the confluence 
    with Lake Champlain, in Addison County, Vermont. There are no federal 
    lands located within the project area.
        g. Filed Pursuant to: Fedral Power Act 16 U.S.C. 791(a)-825(r).
        h. Applicant Contact: Mr. John C. Greenan, P.E., Central Vermont 
    Public Service Corporation, 77 Grove Street, Rutland, Vermont 05701, 
    (802) 747-5707.
         i. FERC Contact: Any questions on this notice should be addressed 
    to Jack Duckworth, E-mail address, jack.duckworth@ferc.fed.us, or 
    telephone (202) 219-2818.
        j. Deadline for comments, recommendations, terms and conditions, 
    and prescriptions: May 26, 1999.
        All documents (original and eight copies) should be filed with: 
    David P. Boergers, Secretary, Federal Energy Regulatory Commission, 888 
    First Street, NE, Washington, DC 20426.
        The Commission's Rules of Practice and Procedure require all 
    intervenors filing documents with the Commission to serve a copy of 
    that document on each person whose name appears on the official service 
    list for the project. Further, if an intervenor files comments or 
    documents with the Commission relating to the merits of an issue that 
    may affect the responsibilities of a particular resource agency, they 
    must also serve a copy of the document on that resource agency.
        k. Status of environmental analysis: This application has been 
    accepted for filing and is ready for environmental analysis at this 
    time.
        l. Description of the Project: The project consists of the 
    following existing facilities: (1) a 30-foot-high, 302.6-foot-long 
    concrete gravity dam consisting of two spillway sections, a 150-ft-long 
    west spillway section, topped with a 6-foot-high hinged steel 
    flashboard, and abutted by a 20-foot-wide and 10-foot-high Taintor 
    gate, and a 116-foot-long east spillway section topped with an 
    automatically inflated rubber weir; (2) a 1.5-mile-long, 62-acre 
    impoundment with a normal water surface elevation of 174.3 feet above 
    mean sea level (msl); (3) a powerhouse integral with the dam containing 
    a single turbine generator with an installed capacity of 3,000 
    kilowatts (kW); (4) transmission facilities; and (5) appurtenant 
    facilities.
        m. Locations of the Application: A copy of the application is 
    available for inspection and reproduction at the Commission's Public 
    Reference Room, located at 888 First Street, NE, Room 2A, Washington, 
    DC 20426, or by calling (202) 208-1371. The application may be viewed 
    on the web at www.ferc.fed.us. Call (202) 208-2222 for assistance. A 
    copy is also available for inspection and reproduction at the address 
    shown in item h.
        n. This notice also consists of the following standard paragraph: 
    D10.
        D10. Filing and Service of Responsive Documents--The application is 
    ready for environmental analysis at this time,
    
    [[Page 15741]]
    
    and the Commission is requesting comments, reply comments, 
    recommendations, terms and conditions, and prescriptions.
        The Commission directs, pursuant to section 4.34(b) of the 
    Regulations (see Order No. 533 issued May 8, 1991, 56 FR 23108, May 20, 
    1991) that all comments, recommendations, terms and conditions and 
    prescriptions concerning the application be filed with the Commisison 
    within 60 days from the issuance date of this notice. All reply 
    comments must be filed with the Commisison within 105 days from the 
    date of this notice.
        Anyone may obtain an extension of time for these deadlines from the 
    Commission only upon a showing of good cause or extraordinary 
    circumstances in accordance with 18 CFR 385.2008.
        All filings must (1) bear in all capital letters the title 
    ``COMMENTS'', ``REPLY COMMENTS'', RECOMMENDATIONS,'' ``TERMS AND 
    CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the 
    name of the applicant and the project number of the application to 
    which the filing responds; (3) furnish the name, address, and telephone 
    number of the person submitting the filing; and (4) otherwise comply 
    with the requirements of 18 CFR 385.2001 through 385.2005. All 
    comments, recommendations, terms and conditions or prescriptions must 
    set forth their evidentiary basis and otherwise comply with the 
    requirements of 18 CFR 4.34(b). Agencies may obtain copies of the 
    application directly from the applicant. Any of these documents must be 
    filed by providing the original and the number of copies required by 
    the Commission's regulations to: The Secretary, Federal Energy 
    Regulatory Commission, 888 First Street, NE, Washington, DC 20426. An 
    additional copy must be sent to Director, Division of Project Review, 
    Office of Hydropower Licensing, Federal Energy Regulatory Commisison, 
    at the above address. Each filing must be accompanied by proof of 
    service on all persons listed on the service list prepared by the 
    Commisison in this proceeding, in accordance with 18 CFR 4.34(b), and 
    385.2010.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 99-7982 Filed 3-31-99; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
04/01/1999
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
99-7982
Pages:
15740-15741 (2 pages)
PDF File:
99-7982.pdf