99-8029. Vermont Yankee Nuclear Power Corporation; Correction Notice  

  • [Federal Register Volume 64, Number 62 (Thursday, April 1, 1999)]
    [Notices]
    [Pages 15835-15836]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-8029]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-271]
    
    
    Vermont Yankee Nuclear Power Corporation; Correction Notice
    
        On February 25, 1999, the NRC published (64 FR 9360) ``issuance of 
    Director's Decision Under 10 CFR 2.206.'' The text of the actual 
    Director's Decision should have followed the notice but did not. The 
    text of ``Director's Decision Pursuant to 10 CFR 2.206'' (DD-99-04) 
    follows this notice.
    
        Dated at Rockville, Maryland this 25th day of March 1999.
    
        For the Nuclear Regulatory Commission.
    Elinor G. Adensam,
    Director, Project Directorate 1-2, Division of Licensing Project 
    Management Office of Nuclear Reactor Regulation.
    
    Office of Nuclear Reactor Regulation, Samuel J. Collins, Director
    
    In the Matter of Vermont Yankee Nuclear Power Corporation (Vermont 
    Yankee Nuclear Power Station)
    
    Docket No. 50-271
    
    License No. DPR-28
    
    (10 CFR 2.206)
    
     Director's Decision Pursuant to 10 CFR 2.206
    
    I. Introduction
    
        By a Petition submitted pursuant to 10 CFR 2.206 on April 9, 1998, 
    Michael J. Daley, on behalf of the New England Coalition on Nuclear 
    Pollution, Inc., (Petitioner), requested that the U.S. Nuclear 
    Regulatory Commission (NRC) take immediate action with regard to the 
    Vermont Yankee Nuclear Power Station (VYNPS) operated by the Vermont 
    Yankee Nuclear Power Corporation (licensee or Vermont Yankee).
        The Petitioner requested that the NRC issue an order requiring that 
    the licensee's administrative limits, which were in effect at the time 
    and precluded VYNPS from operating with a torus water temperature above 
    80  deg.F or with a service water injection temperature greater than 50 
     deg.F, shall remain in force until certain conditions are met. The 
    conditions listed include a complete reconstitution of the licensing 
    basis for the maximum torus water temperature, submittal to the NRC of 
    a technical specifications (TSs) amendment request establishing the 
    correct maximum torus water temperature, and completion of NRC's review 
    of the amendment request.
        On May 13, 1998, the Director of the Office of Nuclear Reactor 
    Regulation informed the Petitioner that he was denying the request for 
    immediate action at VNYPS, that the Petition was being evaluated under 
    10 CFR 2.206 of the Commission's regulations, and that action would be 
    taken in a reasonable time.
        The NRC staff's review of the Petition is now complete. For the 
    reasons set forth below, the Petitioner's remaining requests have been 
    approximately addressed. The conditions associated with the 
    Petitioner's request have been completed, including establishment of 
    the correct licensing basis for the maximum torus temperature, 
    submittal of a TS amendment request establishing the correct maximum 
    torus water temperature limit, and completion of the NRC's review of 
    the amendment request.
    
    [[Page 15836]]
    
    II. Background
    
        In support of these requests, the Petitioner raised concerns about 
    the licensee being unable to demonstrate an ability to either justify 
    the operational limits for the maximum torus water temperature or to 
    maintain operations within existing administrative limits (torus water 
    temperature is critical to the proper functioning of the containment). 
    The Petitioner asserted that since 1994, events have caused the 
    licensee to question VYNPS's maximum torus water temperature limits 
    four times, leading to the self-imposed administrative limits 
    previously noted. The Petitioner stated that the NRC must move from a 
    ``wait and see'' posture to active intervention, with immediate 
    imposition of the order recommended by the Petitioner as a first step.
        The staff notes that the limits proposed by the Petitioner were in 
    effect at VYNPS on an interim basis while the licensee determined the 
    correct maximum torus water temperature limits since it was determined 
    that the TS limit of 100  deg.F was incorrect. The licensee 
    subsequently completed the analysis and determined that the correct 
    limit for the maximum torus water temperature is 90  deg.F. This 
    administrative limit was then established at 90  deg.F and a TS 
    amendment request was submitted to establish this as the maximum torus 
    water temperature.
    
    III. Discussion
    
        As indicated in the May 13 letter, Petitioner's request for 
    immediate action was denied. Although the NRC identified concerns 
    regarding the licensee's handling of the torus water temperature issue 
    in the past, as evidenced by the NRC's enforcement action (Notice of 
    Violation and Proposed Imposition of Civil Penalty of $55,000 dated 
    April 14, 1998), there was insufficient basis for concluding that the 
    limits proposed by the Petitioner must be imposed on the licensee while 
    the NRC reviewed the associated TS amendment request. The NRC took 
    several actions in this area, including performing a design inspection 
    and conducting several meetings with the licensee on this issue. The 
    NRC concluded that the licensee's actions to resolve this issue were 
    acceptable.
        In May and June 1997, the NRC performed a design inspection to 
    evaluate the capability of selected systems to perform their intended 
    safety function as described in design-basis documentation. Also, the 
    NRC assessed the licensee's adherence to its design and licensing basis 
    for selected systems, and the consistency of the as-built configuration 
    and system operations with the final safety analysis report. The team 
    concluded that although some concerns were identified, the systems 
    evaluated were capable of performing their intended functions and the 
    design engineers had excellent knowledge and capabilities. The report 
    findings were documented in NRC Inspection Report Number 50-271/97-201, 
    which was provided with our May 13 letter to the Petitioner.
        One of the concerns identified during the inspection was associated 
    with the licensee's previous handling of the torus water temperature 
    issue and resulted in enforcement action being taken on April 14, 1998, 
    because of a failure to (1) properly translate the design basis of the 
    plant into specifications, procedures, and instructions and (2) 
    promptly correct design deficiencies once they were identified. 
    However, credit was warranted for corrective actions because NRC 
    considered the licensee's actions, once the violations were identified, 
    to be prompt and comprehensive.
        At the NRC's request, several public meetings were conducted to 
    discuss issues, including the licensee's analysis to determine the 
    appropriate torus water temperature limit. As a result of discussions 
    with the licensee during public meetings on March 5, March 24, and 
    April 7, 1998, the NRC concluded that the licensee was taking the 
    appropriate actions to resolve this issue and to ensure that the 
    appropriate maximum torus water temperature was specified in the TS and 
    administratively controlled while the TS amendment was being reviewed 
    by the NRC. During the April 7 meeting, the licensee committed to 
    submit the TS amendment request to limit the torus water temperature to 
    90  deg.F, which is an input value to the containment analysis 
    calculations, before restart. The calculations supporting the amendment 
    request were subjected to the licensee's formal quality process for 
    assuring accuracy and completeness and provided additional assurance 
    that the 90  deg.F limit is correct. The more restrictive 
    administrative limits (80  deg.F torus water temperature and 50  deg.F 
    service water injection water temperature) were put in place by the 
    licensee, while the detailed analysis was performed to verify that 90 
    deg.F was the correct limit.
        The licensee proposed a TS amendment to establish a maximum torus 
    water temperature limit of 90  deg.F by letter dated May 8, 1998, as 
    supplemented on July 10 and October 2, 1998. The NRC reviewed the 
    licensee's analysis and concluded, for the reasons specified in the 
    safety evaluation, that the appropriate maximum torus water temperature 
    is 90  deg.F. Therefore, imposition of the more restrictive 
    administrative limits specified in the Petition are not necessary.
    
    IV. Conclusion
    
        The NRC staff has evaluated the information provided by the 
    Petitioner as its basis for the actions requested. As indicated in the 
    May 13 letter to the Petitioner, the NRC has concluded that issuing an 
    immediate order, as requested, was unnecessary since the licensee took 
    appropriate actions to determine the proper limit on torus water 
    temperature, sought a TS amendment to impose the correct torus water 
    temperature, and administratively implemented the limit while the NRC 
    reviewed the analysis in support of the TS amendment. Although the NRC 
    denied Petitioner's request to take immediate action to issue an order 
    imposing certain limits on VYNPS, the conditions associated with the 
    request have been completed, including establishment of the correct 
    licensing basis for the maximum torus temperature, submittal of a TS 
    amendment request establishing the correct maximum torus water 
    temperature limit, and completion of the NRC's review of the amendment 
    request.
        Since the conditions listed in the Petition have been met and the 
    NRC had previously addressed Petitioner's immediate request for 
    imposition of an order, all actions associated with the request are 
    complete. For the reasons contained in the safety evaluation, we have 
    concluded that the appropriate limit for maximum torus water 
    temperature is 90 deg.F, making the limits requested in the Petition 
    unnecessary. Accordingly, the staff has addressed the issues raised by 
    the Petitioner and has completed its actions relating to the Petition.
        As provided in 10 CFR 2.206(c), a copy of this Decision will be 
    filed with the Secretary of the Commission for the Commission's review. 
    This Decision will constitute the final action of the Commission 25 
    days after issuance unless the Commission, on its own motion, 
    institutes review of the Decision within that time.
    
        Dated at Rockville, Maryland, this 10th day of February 1999.
    
        For the Nuclear Regulatory Commission.
    Samuel J. Collins,
    Director, Office of Nuclear Reactor Regulation.
    [FR Doc. 99-8029 Filed 3-31-99; 8:45 am]
    BILLING CODE 7590-01-M
    
    
    

Document Information

Published:
04/01/1999
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
99-8029
Pages:
15835-15836 (2 pages)
Docket Numbers:
Docket No. 50-271
PDF File:
99-8029.pdf