95-8601. Acid Rain Program: Permits  

  • [Federal Register Volume 60, Number 69 (Tuesday, April 11, 1995)]
    [Rules and Regulations]
    [Pages 18462-18471]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-8601]
    
    
    
    
    [[Page 18461]]
    
    _______________________________________________________________________
    
    Part IV
    
    
    
    
    
    Environmental Protection Agency
    
    
    
    
    
    _______________________________________________________________________
    
    
    
    Clean Air Act: Acid Rain Program Permits; Final Rule and Proposed Rule
    
    Federal Register / Vol. 60, No. 69 / Tuesday, April 11, 1995 / Rules 
    and Regulations 
    [[Page 18462]] 
    
    ENVIRONMENTAL PROTECTION AGENCY
    
    40 CFR Part 72
    
    [FRL-5186-3]
    RIN 2060-AE59
    
    
    Acid Rain Program: Permits
    
    AGENCY: Environmental Protection Agency (EPA).
    
    ACTION: Direct final rule.
    
    -----------------------------------------------------------------------
    
    SUMMARY: Title IV of the Clean Air Act (the Act), as amended by the 
    Clean Air Act Amendments of 1990, authorizes the Environmental 
    Protection Agency (EPA or Agency) to establish the Acid Rain Program. 
    The program sets emissions limitations to reduce acidic deposition and 
    its serious, adverse effects on natural resources, ecosystems, 
    materials, visibility, and public health. On January 11, 1993, the 
    Agency promulgated final rules under title IV. Several parties filed 
    petitions for review of the rules. On January 10, 1995, EPA and the 
    parties signed a settlement agreement addressing reduced utilization 
    issues.
        Based on a review of the record, the Agency concludes that the 
    January 11, 1993 regulations concerning reduced utilization should be 
    revised. The overall effect of the revisions is to reduce the reporting 
    and recordkeeping burden on utilities. The regulations require that, 
    unless certain requirements are met, the designated representative of a 
    unit in Phase I of the program whose annual utilization of fuel is less 
    than its average annual utilization in 1985-1987 must submit a reduced 
    utilization plan. The regulations also require designated 
    representatives to submit end-of-year compliance reports that estimate 
    the sulfur dioxide emissions resulting from any underutilization of 
    Phase I units and to surrender allowances for the estimated emissions. 
    The Agency is revising the regulations to simplify the criteria for 
    determining if a reduced utilization plan must be submitted: Where the 
    end-of-year reporting and allowance surrender requirements are met, 
    such a plan is not required. Further, the Agency is revising the 
    formulas for estimating emissions resulting from underutilization to 
    correct errors, clarify certain provisions, and take account of and 
    facilitate compliance by Phase I units with multiple owners or whose 
    owners are required by law to purchase electricity from non-utility 
    power production facilities.
        The rule revision is being issued as a direct final rule because it 
    is consistent with the January 10, 1995 settlement and no adverse 
    comment is expected.
    
    EFFECTIVE DATE: This direct final rule will be effective on May 22, 
    1995 unless significant, adverse comments are received by May 11, 1995. 
    If significant, adverse comments are timely received on any portion of 
    the direct final rule, that portion of the direct final rule will be 
    withdrawn through a notice in the Federal Register.
    
    ADDRESSES: All written comments must be identified with the appropriate 
    docket number and must be submitted in duplicate to: EPA Air Docket 
    Section (LE-131), Waterside Mall, Room 1500, 1st floor, 401 M St., 
    S.W., Washington DC 20460.
        Docket No. A-93-40, containing supporting information used to 
    develop the proposal, copies of all comments received, and responses to 
    comments, is available for public inspection and copying from 8:30 a.m. 
    to 12:00 p.m. and 1:00 p.m. to 3:30 p.m., Monday through Friday, 
    excluding legal holidays, at EPA's Air Docket Section, Waterside Mall, 
    Room 1500, 1st floor, 401 M St., S.W., Washington, DC 20460. A 
    reasonable fee may be charged for copying.
    
    FOR FURTHER INFORMATION CONTACT: Dwight C. Alpern, Attorney-advisor, at 
    (202) 233-9151, Acid Rain Division (6204J), U.S. Environmental 
    Protection Agency, 401 M St., S.W., Washington, DC 20460, or the Acid 
    Rain Hotline at (202) 233-9620.
    
    SUPPLEMENTARY INFORMATION: All public comment received on any portion 
    of this direct final rule on which significant, adverse comments are 
    timely received will be addressed in a subsequent final rule. That 
    final rule will be based on the relevant portion of the rule revision 
    that is noticed as a proposed rule in the Proposed Rules Section of 
    this Federal Register and that is identical to this direct final rule. 
    The contents of the preamble to the direct final rule are as follows:
    
    I. Background: Purposes of Reduced Utilization Plans and Allowance 
    Surrender for Underutilization of Phase I Units
    II. Reduced Utilization Plan
    III. Dispatch System
        A. Utility System and Identification of Dispatch System
        B. Apportionment of Phase I Units
    IV. Emissions Rate
        A. Non-Utility Generators
        B. Dispatch System Emissions Rate
        C. NERC Emissions Rate
    V. Administrative Requirements
        A. Executive Order 12866
        B. Unfunded Mandates Act
        C. Paperwork Reduction Act
        D. Regulatory Flexibility Act
        E. Miscellaneous
    
    I. Background: Purposes of Reduced Utilization Plans and Allowance 
    Surrender for Underutilization of Phase I Units
    
        A Phase I unit is underutilized if, in any year in Phase I, the 
    total annual utilization of fuel at the unit is less than its baseline, 
    i.e., its annual average fuel utilization for 1985-1987. The provisions 
    of the Act that relate to reduced utilization or underutilization of 
    Phase I units are found in sections 403(d) and 408(c)(1)(B).
        In dividing the Acid Rain Program into two phases, i.e., Phase I 
    applicable only to larger, dirtier units and Phase II applicable to 
    virtually all utility units, the Congress recognized the potential for 
    circumvention of Phase I emission reduction requirements. A Phase I 
    unit, which receives allowances for its baseline, could simply reduce 
    its utilization below baseline by shifting generation of electricity to 
    a unit that was not covered by Phase I and did not have to use 
    allowances to authorize its SO2 emissions. The Phase I unit would 
    retain the unused allowances but the same amount of SO2 could be 
    emitted by the second unit, which would not use up any allowances. See 
    58 FR 60951 (Nov. 18, 1993). In section 408(c)(1)(B), Congress adopted 
    the solution of requiring submission of a reduced utilization plan by 
    owners and operators of any Phase I unit that plans to reduce the 
    unit's utilization in order to comply with Phase I emissions 
    limitations. The plan must designate the units (referred to as 
    ``compensating units'') to which generation was shifted or account for 
    the reduced utilization through energy conservation or improved unit 
    efficiency. 59 FR 60219 (Nov. 22, 1994).
        Section 403(d) provides that the Acid Rain regulations must permit 
    utilities to continue to operate in an economic and reliable fashion 
    (e.g., through central dispatching that may result in shifting 
    generation from Phase I units to other units or generators). However, 
    section 403(d) also provides that the Acid Rain regulations must 
    require utilities to compensate at the end of the year for emissions 
    resulting from such operations and must facilitate orderly and 
    competitive functioning of the allowance system. 56 FR 63019 (Dec. 3, 
    1991).
        In order to achieve the objectives of both section 403(d) and 
    section 408(c)(1)(B), EPA adopted, in the January 11, 1993 regulations, 
    requirements concerning the submission of reduced utilization plans and 
    allowance surrender for underutilization. The regulations 
    [[Page 18463]] require that the designated representative of any Phase 
    I unit with utilization below baseline apply formulas in Secs. 72.91 
    and 72.92 estimating the emissions (if any) resulting from such 
    underutilization and surrender allowances covering the estimated 
    emissions. In this way, the emissions consequences of shifting 
    generation from Phase I units are accounted for, and Phase I SO2 
    emission reduction goals are preserved, without the designation of 
    specific compensating units.
        In addition, the January 11, 1993 regulations require the 
    submission of a reduced utilization plan for any Phase I unit that is 
    planned to be utilized below baseline as a method of complying with 
    SO2 emissions limitations. However, if the allowance surrender 
    requirements are met and the unit meets criteria in Sec. 72.43(e), a 
    plan is not required. The criteria are broadly drawn. For example, 
    under these criteria, a plan need not be submitted for underutilization 
    caused by economic dispatching that reflected increases in generation 
    costs (e.g., allowance costs) at the unit. The Agency adopted this 
    approach of limiting the plan submission requirement because of concern 
    that, inter alia, economic dispatch and operation of utility systems or 
    power pools might be inhibited because utilities might be unable to 
    designate compensating units. 56 FR 63021.
    
    II. Reduced Utilization Plans
    
        As noted above, Sec. 72.43(e) of the January 11, 1993 regulations 
    sets forth criteria for making retrospective determinations as to 
    whether a Phase I unit was underutilized for the purpose of complying 
    with SO2 emissions limitations. If underutilization was for the 
    purpose of compliance, then the unit must have a reduced utilization 
    plan. If underutilization was incidental to utility operations, no plan 
    is needed. In particular, a plan is not required if the allowance 
    surrender requirements under Secs. 72.91 and 72.92 are met and one of 
    several demonstrations are made. The demonstrations involve showing 
    that the unit's underutilization was caused by a dispatch-system-wide 
    sales decline, a forced outage at the unit, or economic dispatching. If 
    none of these demonstrations can be made, the Agency determines on a 
    case-by-case basis, considering certain indicators set forth in 
    Sec. 72.43(e)(2), whether a plan should have been submitted.
        The Agency has concluded that this approach is unnecessarily 
    complicated and burdensome. Because of concerns that Phase I units 
    would be unable to designate compensating units, the criteria in 
    Sec. 72.43(e) for avoiding submission of a reduced utilization plan 
    were designed to apply broadly. In particular, a plan is not required 
    to the extent underutilization is caused by economic dispatching. 
    Consequently, under these criteria, plan submission is largely optional 
    so long as the allowance surrender requirements are met.
        However, despite their broad scope, the criteria still leave some 
    uncertainty as to whether the Agency will agree that a reduced 
    utilization plan is not required even if allowances are surrendered. 
    Further, owners and operators of Phase I units carry the burden of 
    showing that the criteria are met. In fact, the January 11, 1993 
    regulations require Phase I unit owners and operators to show in their 
    annual compliance certification reports the amounts of underutilization 
    caused by sales decline, forced outage, or economic dispatching. 40 CFR 
    72.92(a)(2) (1993). The annual reports must also include specified 
    information on forced outages at Phase I units. 40 CFR 72.92(a)(3) 
    (1993). Additional submissions are required during the year in the 
    event of a forced outage that will permanently shut down a Phase I unit 
    and result in shifting generation to other units. 40 CFR 72.92(b)(1) 
    (1993). Yet, this uncertainty and burden serve no real purpose if the 
    allowance surrender requirements of Secs. 72.91 and 72.92 are met. The 
    allowance surrender procedures account for the emissions consequences 
    of underutilization and consequent shifting of generation and therefore 
    obviate the need for a reduced utilization plan under section 
    408(c)(1)(B) of the Act. Once underutilization is accounted for under 
    Secs. 72.91 and 72.92, there is no basis for requiring any further 
    accounting through the designation of compensating units or energy 
    conservation or unit efficiency measures.
        The Agency concludes that Sec. 72.43(e) should be revised so that 
    the requirement to submit a reduced utilization plan for an 
    underutilized Phase I unit is eliminated if the allowance surrender and 
    reporting requirements of Secs. 72.91 and 72.92 are met. This is a 
    reasonable way of harmonizing sections 408(c)(1)(B) and 403(d) of the 
    Act. The other criteria in Sec. 72.43(e) are therefore superfluous and 
    are removed. Sections 72.92(a)(2) and (3) and (b)(1) of the January 11, 
    1993 regulations, requiring submission of information in annual and 
    other reports related to the removed criteria in Sec. 72.43(e), are 
    also unnecessary and are removed.1
    
        \1\In addition, Sec. 72.91(a) of the January 11, 1993 
    regulations is revised to make it clear that the reporting 
    requirements in Sec. 72.91 apply only to calendar years in Phase I. 
    Since Sec. 72.92(a) applies to calendar years covered by Sec. 72.91, 
    this limitation applies to reporting under both sections. This 
    reflects the fact that reduced utilization is a problem only in 
    Phase I, when a minority of utility units are subject to Acid Rain 
    SO2 emissions limitations. See 56 FR 63018 and 58 FR 3605.
    ---------------------------------------------------------------------------
    
    III. Dispatch System
    
        The dispatch system of a unit plays an important role in the 
    allowance surrender calculations under Secs. 72.91 and 72.92. For 
    example, if a Phase I unit has a reduced utilization plan, the amount 
    of reduced utilization accounted for under the plan (by a compensating 
    unit, conservation or improved unit efficiency measures, or sulfur-free 
    generators) must be determined. See 40 CFR 72.91(a)(3) (1993) 
    (requiring calculation of ``plan reductions''). The percentage change 
    in the total sales of the dispatch system is a factor in calculating 
    reduced utilization accounted for by a sulfur-free generator. 40 CFR 
    72.91(a)(3)(iii) (1993). As a further example, the total generation 
    produced by the units and generators in a dispatch system during a 
    Phase I calendar year must be used to determine the percentage of total 
    dispatch system sales for the year that was generated by units and 
    generators in the dispatch system. That percentage is used in 
    calculating the emissions rate that is in turn used to determine how 
    many allowances must be surrendered for the year. 40 CFR 
    72.92(c)(2)(v)(A) (1993).
        The Agency is revising Sec. 72.33(a), (b), and (c) to clarify 
    certain matters concerning the determination of a unit's dispatch 
    system. In addition, while Sec. 72.33(f) allowed owners and operators 
    of Phase I units to request that a Phase I unit be apportioned among 
    its owners and their dispatch systems, certain revisions of the 
    provision are needed to make it more workable and to coordinate it with 
    the allowance surrender procedures under Secs. 72.91 and 72.92.
    
    A. Utility System and Identification of Dispatch System
    
        Under Sec. 72.33, each Phase I unit must be treated as part of a 
    dispatch system for purposes of the allowance surrender 
    procedures,2 and the unit's utility [[Page 18464]] system (as 
    defined in Sec. 72.2) is its dispatch system unless a complete 
    identification of dispatch system including that unit is submitted 
    under Sec. 72.33.
    
        \2\Because the allowance surrender procedures are found in both 
    Sec. 72.91 and Sec. 72.92, Sec. 72.33(a) is revised to refer to both 
    sections. The same change is made, for the same reason, in 
    Sec. 72.33(c)(4) and (e)(2) and Sec. 72.33(f)(2) (iv) and (v). This 
    conforms these provisions with other provisions in the January 11, 
    1993 regulations that cite both sections.
    ---------------------------------------------------------------------------
    
        In the January 11, 1993 regulations, utility system is defined as 
    all interconnected units and generators controlled by the same utility 
    operating company, as reported in the National Allowance Data Base 
    (NADB). The difficulty with this definition is that the NADB was 
    published in final form in March 1993 and necessarily reflects 
    information on utility systems as of that time. The Agency recognizes 
    that the owners and operators of some units have changed since 1993 
    and, particularly in light of increased competition in the electric 
    utility industry, that more changes may occur during Phase I. In order 
    to clarify that designated representatives may submit identifications 
    of dispatch system to correct the utility system in which a unit or 
    generator is listed in the NADB and that is used as its dispatch 
    system, the Agency is revising the utility-system definition. Section 
    72.2 now defines utility system as all interconnected units and 
    generators operated by the same utility company and does not refer to 
    the NADB. Section 72.33(e)(1) is revised to state that unless otherwise 
    provided in an identification of dispatch system, a unit or generator 
    included in the NADB retains, as its dispatch system, the utility 
    system reported in the NADB.
        The NADB lists one utility operating company for each Phase I unit, 
    Phase II unit, and non-affected unit in the database. Section 
    72.33(b)(2) of the January 11, 1993 regulations states that, except as 
    provided under Sec. 72.33(f), no Phase I unit may be listed in more 
    than one identification of dispatch system. Although Sec. 72.33(b) of 
    the January 11, 1993 regulations does not state explicitly that other 
    units or generators also must be confined to a single identification of 
    dispatch system, other provisions of the regulations reflect such a 
    limitation. For example, Sec. 72.33(f) states that, except for the 
    provisions for apportioning Phase I units under Sec. 72.33(f), all 
    provisions of the regulations ``applicable to an affected source or 
    affected unit * * * apply to the entire unit.'' 40 CFR 72.33(f)(6) 
    (1993). By further example, the provisions requiring calculation of the 
    ``total'' generation of the units and generators in a dispatch system 
    are based on entire units and generators and do not provide for 
    division of a unit's or generator's generation among more than one 
    dispatch system, except for Phase I units apportioned under 
    Sec. 72.33(f). 40 CFR 72.92(c)(2)(v)(A) (1993). See also 40 CFR 
    72.91(a)(3)(iii)(A) (1993) (``actual annual'' generation of the sulfur-
    free generator). In addition, dispatch system emissions rate, which is 
    calculated using the actual annual emissions rate of all Phase II units 
    in the dispatch system, is based on the utilization of entire units, 
    and there is no provision allowing apportionment of Phase II units. 40 
    CFR 72.92(c)(2)(v)(C) (1993).
        In order to remove any possible uncertainty concerning the 
    treatment of Phase II units, non-affected units, and generators 
    (including sulfur-free generators and, as discussed below, non-utility 
    generators), the Agency is revising Sec. 72.33(b)(2) to state that, 
    with one exception, a unit or generator can be included in only one 
    dispatch system.3 The only exception is provided in Sec. 72.33(f), 
    under which a petition to apportion a Phase I unit among two or more 
    dispatch systems may be submitted and approved. Section 72.33(f) 
    provides that, if the petition is approved, the portions of the Phase I 
    unit will be treated as separate units under Secs. 72.91 and 72.92, the 
    allowance surrender provisions.
    
        \3\ The units and generators included in a given dispatch system 
    under Sec. 72.33(b) or (e) may be changed under Sec. 72.33(d). A 
    complete identification of dispatch system, reflecting the change, 
    must be submitted for both the dispatch system from which the units 
    or generators are removed and the dispatch system to which the units 
    or generators are added. If the entire dispatch system from which 
    the units or generators are removed is included in the dispatch 
    system to which they are added, then an identification of dispatch 
    system is necessary only for the latter dispatch system.
    ---------------------------------------------------------------------------
    
        Several other revisions are made here to the provisions concerning 
    identification of dispatch system. While the January 11, 1993 
    regulations require a complete identification of dispatch system to 
    include a list of all units and sulfur-free generators in the dispatch 
    system, the revised rule expands that list to include all generators, 
    including sulfur-free generators and non-utility generators. The 
    January 11, 1993 regulations also require that if the submissions under 
    Secs. 72.91 and 72.92 by all designated representatives of the units in 
    the identified dispatch system do not conform to the system-wide data 
    provided for the dispatch system, the Administrator must reject the 
    identification of dispatch system and all the submissions and require 
    resubmission using the utility system of each unit as that unit's 
    dispatch system. The revised regulations make such rejection optional 
    so that the Agency may instead require corrections of the submissions 
    and allow the identification of dispatch system to remain in effect. 
    Sections 72.33(c)(4) and (e)(2) are revised to implement that change. 
    Finally, Sec. 72.33(b)(3) is revised so that the deadline for providing 
    an identification of dispatch system is the same as for providing a 
    petition to apportion a Phase I unit under Sec. 72.33(f)(1), i.e., 
    submission to EPA by January 30 of the year that the dispatch system is 
    to take effect.
    
    B. Apportionment of Phase I Units
    
        The January 11, 1993 regulations only allow for the apportionment 
    of Phase I units, and such apportionment is only for the purpose of 
    applying the allowance surrender procedures of Secs. 72.91 and 72.92. 
    Under Sec. 72.33(f) of the January 11, 1993 regulations, Phase I units 
    with multiple owners may petition to divide up the unit, for allowance 
    surrender, into portions, i.e., one or more individual owners' portions 
    representing the owners' respective percentage ownership interests in 
    the capacity of the unit and the remaining portion of the unit. The 
    petition requests that each individual owner's portion be treated as 
    part of a dispatch system different than the dispatch system of the 
    remaining portion. If the petition is approved, the adjusted 
    utilization (which, if greater than zero, is underutilization) is 
    calculated for the entire unit for the Phase I year governed by the 
    approved petition, and each portion of the unit takes its percentage of 
    the adjusted utilization reflecting the ownership percentage that the 
    portion of the unit represents. Each portion of the unit then uses its 
    share of the entire unit's adjusted utilization in calculating how many 
    allowances (if any) must be surrendered for underutilization of the 
    Phase I units in its respective dispatch system.
        The Agency received public comment expressing concern that 
    requiring the portions of a Phase I unit to divide among them the 
    adjusted utilization calculated for the entire unit fails to reflect 
    differences among the Phase I unit owners' respective utilizations of 
    their shares of the unit. While during the Phase I year one owner might 
    take generation representing more than its percentage share of the 
    baseline of the entire unit, another owner might take generation 
    representing less than its percentage share.
        Section 72.33(f) is revised to require the separate calculation of 
    adjusted utilization under Sec. 72.91 for each portion of the unit for 
    which a petition to apportion is approved and for the remaining portion 
    of the unit. This [[Page 18465]] approach meets the commenters' 
    concerns. The separate calculation of adjusted utilization is made a 
    uniform requirement for all apportioned Phase I units in order to 
    ensure that overall there is no net adverse environmental impact from 
    apportionment and to avoid the potential confusion and administrative 
    burden of having two entirely different approaches for calculating 
    reduced utilization of apportioned units.
        Public comment has also been directed at the requirement that 
    apportionment be based exclusively on the owners' percentage ownership 
    interest in the capacity of the Phase I unit. According to commenters, 
    unit owners in some cases have entered into private agreements to 
    divide up the allowances allocated to the unit based on percentage 
    ownership of capacity during 1985-1987 while owners in other cases have 
    agreed to divide up allocated allowances based on each owner's 
    percentage share of utilization of the unit during 1985-1987. 
    Commenters have requested that the regulations allow the basis for unit 
    apportionment for purposes of allowance surrender to be consistent with 
    the basis for dividing up the unit's allowance allocation.
        The Agency is willing to meet these concerns and accommodate 
    underlying private agreements among unit owners so long as the 
    resulting regulatory provisions are not too complex and do not appear 
    to cause overall any net adverse environmental impact. This is 
    consistent with the Agency's general approach of avoiding interfering 
    with existing relationships among owners and operators. See 58 FR 3598. 
    Consequently, the revised Sec. 72.33(f) allows the designated 
    representative to elect in the apportionment petition one of two 
    methods for apportioning the Phase I unit: the first method is based on 
    the average of the owner's percentage ownership of the capacity of the 
    unit for each year in 1985-1987; and the second method is based on the 
    average of the unit's annual utilization that is attributed to the 
    owner for 1985-1987. In order to avoid gaming by changing the 
    apportionment method to minimize allowance surrender each year, the 
    regulations make the selection of the apportionment method a one-time 
    election for each Phase I unit. The same apportionment method must be 
    used for all portions of the units for all years in Phase I for which 
    any petition to apportion is approved and in effect.
        Further, the Agency is concerned that, whichever apportionment 
    method is elected, the baselines and actual utilizations for the 
    portions of the unit must not double-count or undercount any of the 
    baseline and actual utilization for the entire unit. Consequently, the 
    revised regulations require that the sum of the baselines of the 
    portions of the unit (including the individual owners' portions and the 
    remaining portion of the unit) equal 100% of the baseline of the entire 
    unit. Similarly, for each Phase I year, the sum of the actual 
    utilizations of the portions must equal 100% of the entire unit's 
    actual utilization. In order to ensure that the attribution of a unit's 
    utilization (whether baseline or actual utilization) to specific owners 
    is not arbitrary, the regulations require that the same accounting 
    procedures used to attribute the unit's fuel costs among the owners be 
    used for attributing utilization. This is reasonable because fuel costs 
    at a unit are directly related to the unit's utilization (i.e., the 
    mmBtu of fuel consumed).
        The revised Sec. 72.33(f) establishes the requirements for the 
    contents of a complete petition to apportion and provides that the 
    Administrator may prescribe a format. In addition to the requirements 
    in the January 11, 1993 regulations, the petition must include the 
    election of apportionment method and a list of the units and generators 
    and apportioned units to be included in the dispatch system proposed 
    for each portion of the unit covered by the petition. The designated 
    representative is not required to submit with the petition the 
    documentation supporting the baselines for the portions of the unit or 
    the dispatch systems proposed for each portion of the unit. The Agency 
    maintains that this is a sound approach in light of: the certifications 
    by the designated representatives that the information in the petition 
    is true, accurate, and complete; the Agency's ability to require 
    submission of additional information before acting on the petition or 
    at any other time; and the potential for after-the-fact spot audits.
        The January 11, 1993 regulations require that, with regard to the 
    dispatch system proposed for each owner's portion of the unit, the 
    dispatch system must be a group of all units and generators that are 
    interconnected and centrally dispatched and that are included in the 
    same utility system, holding company, or power pool. The difficulty 
    with this requirement is that a Phase I unit to be apportioned has 
    multiple owners and only one owner may be the operator. A non-operating 
    owner's portion of the unit cannot be in the ``utility system'' of the 
    non-operating owner's other units and generators because, as defined in 
    Sec. 72.2, only units and generators with the same operator comprise a 
    ``utility system''. In order to avoid this problem, the revised 
    regulations require that the proposed dispatch system for each owner's 
    portion of the unit include all units and generators that are 
    interconnected and centrally dispatched by a single utility system, the 
    service company of a single holding company, or a single power pool.
        Upon approval of an apportionment petition and the proposed 
    dispatch systems, the allowance surrender formulas are applied to each 
    portion of the Phase I unit and its respective dispatch system. The 
    designated representative of the apportioned unit must surrender all 
    allowances required for surrender by each portion of the unit.
        There is no provision in the January 11, 1993 regulations for 
    termination of an approved apportionment of a Phase I unit. The Agency 
    is concerned that after approval of an apportioned Phase I unit, 
    circumstances may change so that the apportionment is no longer 
    appropriate. For example, the owner of one portion of the apportioned 
    unit could sell its entire interest in the unit and stop dispatching 
    that portion of the unit. The dispatch system that, because of the 
    approved apportionment, includes that portion of the unit would now 
    include a portion of the unit that was no longer centrally dispatched 
    along with the other units and generators in the dispatch system. That 
    aspect of the approved apportionment (and the designated 
    representative's certification concerning the continued central 
    dispatching of the dispatch system) would no longer be accurate and the 
    apportionment should be terminated. Of course, a new apportionment 
    reflecting the new composition of ownership interests in the Phase I 
    unit could be submitted for approval. Even without any change in 
    ownership or dispatching, the owners of the Phase I unit might 
    determine that an apportionment is no longer desirable. To accommodate 
    changes in circumstance and to provide owners more flexibility, the 
    revised regulations include a procedure for terminating apportionments. 
    If a notice of termination is signed by the designated representatives 
    of all units that could be affected by the termination (i.e., of all 
    units included in all dispatch systems that include any portion of the 
    unit) and submitted by January 30, the apportionment is terminated for 
    that year and all remaining Phase I years.
    
    IV. Emissions Rate
    
        The January 11, 1993 regulations require that the emissions 
    consequences [[Page 18466]] of underutilization for a dispatch system 
    be estimated for each Phase I year by multiplying that underutilization 
    (referred to as ``dispatch system adjusted utilization'') by an 
    emissions rate for generation used by the dispatch system to compensate 
    for the underutilization. The emissions rate is composed of an 
    emissions rate for compensating generation produced by non-Phase I 
    units and generators within the dispatch system and another emissions 
    rate for compensating generation produced outside the dispatch system 
    by non-Phase I, non-foreign units and generators and acquired by the 
    dispatch system. To calculate the composite emissions rate, the 
    emissions rate for generation within the dispatch system is weighted by 
    a fraction equal to total generation by the units and generators in the 
    dispatch system divided by total dispatch system sales (i.e., total 
    sales for direct use or resale) of the named utility system, holding 
    company, or power pool that is the dispatch system) for the year. The 
    actual annual emissions rates of the Phase II units in the dispatch 
    system are used as a proxy for the actual emissions rates of all non-
    Phase I units and generators in the dispatch system. Similarly, the 
    emissions rate for generation outside the dispatch system is weighted 
    by the fraction of total dispatch system sales that is accounted for by 
    generation outside the dispatch system. NERC region emissions rates for 
    non-Phase I, non-foreign units for 1985 are used as a proxy for the 
    current emissions rates of non-Phase I, non-foreign units and 
    generators.
        In light of public comment concerning compensating generation from 
    non-utility generators, the calculation of the emissions rate of non-
    Phase I units in the dispatch system, and 1985 NERC emissions rates, 
    the Agency is revising these aspects of the January 11, 1993 
    regulations.
    
    A. Non-Utility Generators
    
        The Agency received public comment that some utilities are required 
    by Federal or State law or by order of their State public utility 
    commission to purchase electricity from non-utility generators. This 
    required purchase of electricity may result in reduced utilization of 
    the utility's own Phase I units. Since non-utility generators may have 
    a different--apparently often lower--emissions rate than that of the 
    utility's Phase II units or the NERC region emissions rate, the 
    commenters urged that the formulas in Sec. 72.92 be revised to take 
    account of this third possible source of compensating generation.
        The allowance surrender procedures in Secs. 72.91 and 72.92 are not 
    intended to result in a precise calculation of the emissions 
    consequences of underutilization of Phase I units. The procedures were 
    adopted to provide an administratively feasible method of developing 
    reasonable estimates of the emissions resulting from generation 
    compensating for underutilization. In light of this goal, the January 
    11, 1993 regulations establish a composite emissions rate based on two 
    general categories of compensating generation. Because some utilities 
    are obligated by law to purchase non-utility generation that may force 
    them to reduce generation at their own units and because non-utility 
    generators tend to have relatively low SO2 emissions, the Agency 
    is revising the regulations to take account of non-utility generation. 
    This change increases somewhat the complexity of the allowance 
    surrender formulas but, as a practical matter, only utilities that must 
    buy from non-utility generators are affected by the change. While the 
    Agency maintains that, on balance, the change is reasonable, the Agency 
    stresses that the allowance surrender formulas are only intended to 
    estimate emissions and that any more refinements that would further 
    complicate the formulas would seem to be counterproductive.
        The provisions incorporating non-utility generators into the 
    allowance surrender procedures are premised on the fact that utilities 
    acquiring non-utility generation have very limited information about 
    the non-utility generators. Utilities contract to purchase non-utility 
    generation but, as a result of not owning or operating these 
    generators, have little or no knowledge about the fuels used by, and 
    the heat rates and emission rates of, the generators. The Agency 
    similarly has limited information about non-utility generators because 
    they are not affected units. Consequently, the revised regulations use 
    the available information on these generators (i.e., their emissions 
    limitations and Kwh sales to utilities) to estimate emissions from 
    compensating generation acquired from them.
        In order to be treated as a non-utility generator, a power 
    production facility cannot be an affected unit or a sulfur-free 
    generator. The facility must use its most stringent federally 
    enforceable or State enforceable SO2 emissions limitation for the 
    Phase I year as the estimate of its actual emissions rate.4 With 
    one exception, if no unit-specific limitation that can be expressed in 
    lbs/mmBtu is applicable to the facility for the year, then the facility 
    cannot be treated as a non-utility generator for that year. The only 
    exception is where a facility without an emissions limitation is 
    authorized by law to use only natural gas as fuel; in that case the 
    most stringent emissions limitation for the facility is deemed to be 
    0.0006 lbs/mmBtu.5
    
        \4\If emissions limitations vary depending on the fuel used, the 
    most stringent emissions limitation must be calculated for each fuel 
    used. The resulting limitation with the highest lbs/mmBtu must be 
    used as the estimate for the actual emissions rate of the non-
    utility generator.
        \5\This default emissions rate is the average SO2 emissions 
    rate for natural gas and was used for purposes of allocating 
    allowances to utility units under section 405 of the Act. See 
    Compilation of Air Pollutant Emission Factors (AP-42), Vol. 1 at 
    1.4-1 through 1.4-3, US EPA (4th ed. 1985).
    ---------------------------------------------------------------------------
    
        As discussed above, the January 11, 1993 regulations calculate a 
    composite emissions rate for a dispatch system reflecting compensating 
    generation from within or from outside the dispatch system. The revised 
    regulations introduce a third category, non-utility generation from 
    non-utility generators, which equals the total generation acquired from 
    non-utility generators that the dispatch system is required to purchase 
    by Federal or State law or order of a utility regulatory commission or 
    under a contract awarded as the result of a power purchase solicitation 
    required by Federal or State law or utility regulatory commission 
    order. To prevent double-counting, such generation is excluded in 
    calculating the fractions of dispatch system sales accounted for by 
    generation within or outside the dispatch system. Total non-utility 
    generation from non-utility generators is used to calculate the 
    fraction of dispatch system sales accounted for by such generators.
        The non-utility generator average emissions rate is calculated 
    using the most stringent emissions limitation (or for natural-gas-only 
    facilities, the default emissions rate) for each non-utility generator 
    from which the dispatch system was required to purchase electricity, 
    weighted by the amount (kwh) of required electricity purchases during 
    the year. The fraction of generation from non-utility generators and 
    the non-utility generator average emissions rate are used, along with 
    the comparable data for generation within and outside the dispatch 
    system, to derive the composite emissions rate multiplied by the 
    underutilization for the dispatch system for the year.6 This 
    yields the total number of allowances [[Page 18467]] that must be 
    surrendered by Phase I units in the dispatch system.
    
        \6\The dispatch-system-wide data related to non-utility 
    generators must be included in the dispatch system data report under 
    Sec. 72.92(b).
    ---------------------------------------------------------------------------
    
    B. Dispatch System Emissions Rate
    
        The January 11, 1993 regulations use the actual annual emissions 
    rate for a dispatch system's Phase II units to estimate the emissions 
    rate for the dispatch system's non-Phase I units. In the December 3, 
    1991 proposed regulations, the Agency proposed to weight the actual 
    annual emissions rate for each Phase II unit by the amount of the Phase 
    II unit's increase in utilization for the year over baseline. 56 FR 
    63147-48 (Dec. 3, 1991). The January 11, 1993 regulations adopted a 
    simpler approach of weighting actual annual emissions rates by each 
    Phase II unit's total utilization for the year. 58 FR 3685.
        However, the Agency has received public comments suggesting that 
    weighting by the increase over baseline provides a more realistic 
    estimate. It seems reasonable to treat a utilization reduction since 
    1985-1987 of one unit in a dispatch system as being compensated for by 
    a utilization increase since 1985-1987 of another unit in that dispatch 
    system. Further, this approach is similar to that taken with regard to 
    sulfur-free generators. Compensating generation claimed to be acquired 
    from sulfur-free generators under a reduced utilization plan cannot 
    exceed the amount of electricity produced by the sulfur-free generator 
    in excess of the average annual amount produced by the generator in 
    1985-1987. See 58 FR 3682. For these reasons, the Agency is revising 
    the provisions for calculating dispatch system emissions rate to weight 
    Phase II units' actual emissions rates by each unit's increased 
    utilization over baseline. However, the Agency recognizes that it is 
    possible that no Phase II unit in a dispatch system has increased 
    utilization over baseline. In that case, non-affected units are 
    providing the compensating generation but, because of the lack of 
    emissions data from such units, the Phase II unit emissions rate must 
    still be used as a proxy for non-affected units' emissions rates. The 
    revised regulations therefore provide that if no Phase II unit is used 
    above baseline, an average rate must be calculated using the Phase II 
    units' annual actual emissions rates weighted by each unit's total 
    utilization. Moreover, if a dispatch system has no Phase II unit 
    emissions rate for the year, the NERC region emissions data will be 
    used instead.
    
    C. NERC Region Emissions Rate
    
        The January 11, 1993 regulations use 1985 NERC data to establish 
    the non-Phase I, non-foreign emissions rate for each NERC region. The 
    1985 emissions rate for units in the NERC region is multiplied by the 
    fraction of non-Phase I, nonforeign units in the NERC region in order 
    to exclude generation and resulting emissions from Phase I units and 
    all foreign units and generators.
        The Agency has learned through public comment that the figures in 
    the regulations for the fraction of non-Phase I, non-foreign generation 
    contained inadvertent errors and failed to actually exclude foreign 
    generation. The Agency has recalculated the fractions of non-Phase I, 
    non-foreign generation for each NERC region. Table 1 of the revised 
    regulations includes the corrected figures so that foreign generation 
    is excluded as intended.7
    
        \7\The definition of ``sulfur-free generation'' is revised to 
    make it clear that only facilities in the 48 contiguous states in 
    the United States or the District of Columbia may qualify as sulfur-
    free generators under reduced utilization plans. All foreign 
    generation (including foreign generation that involves no SO2 
    emissions) that offset underutilization is already excluded from 
    allowance surrender in the revised Table 1. Allowing foreign 
    facilities to be designated as sulfur-free generators and the 
    generation acquired from them to be used to offset underutilization 
    would double-count such generation.
    ---------------------------------------------------------------------------
    
    VI. Administrative Requirements
    
    A. Executive Order 12866
    
        Under Executive Order 12866, 58 FR 51735 (Oct. 4, 1993), the 
    Administrator must determine whether the regulatory action is 
    ``significant'' and therefore subject to Office of Management and 
    Budget (OMB) review and the requirements of the Executive Order. The 
    Order defines ``significant regulatory action'' as one that is likely 
    to result in a rule that may:
        (1) Have an annual effect on the economy of $100 million or more or 
    adversely affect in a material way the economy, a sector of the 
    economy, productivity, competition, jobs, the environment, public 
    health or safety, or State, local, or tribal governments or 
    communities;
        (2) create a serious inconsistency or otherwise interfere with an 
    action taken or planned by another agency;
        (3) materially alter the budgetary impact of entitlements, grants, 
    user fees, or loan programs or the rights and obligations of recipients 
    thereof; or
        (4) raise novel legal or policy issues arising out of legal 
    mandates, the President's priorities, or the principles set forth in 
    the Executive Order.
        Pursuant to the terms of Executive Order 12866, it has been 
    determined that this rule is a ``significant regulatory action'' 
    because the rule seems to raise novel legal or policy issues. As such, 
    this action was submitted to OMB for review. Any written comments from 
    OMB to EPA, any written EPA response to those comments, and any changes 
    made in response to OMB suggestions or recommendations are included in 
    the docket. The docket is available for public inspection at the EPA's 
    Air Docket Section, which is listed in the ADDRESSES section of this 
    preamble.
    
    B. Unfunded Mandates Act
    
        Section 202 of the Unfunded Mandates Reform Act of 1995 (``Unfunded 
    Mandates Act'') (signed into law on March 22, 1995) requires that the 
    Agency prepare a budgetary impact statement before promulgating a rule 
    that includes a Federal mandate that may result in expenditure by 
    State, local, and tribal governments, in aggregate, or by the private 
    sector, of $100 million or more in any one year. Section 203 requires 
    the Agency to establish a plan for obtaining input from and informing, 
    educating, and advising any small governments that may be significantly 
    or uniquely affected by the rule.
        Under section 205 of the Unfunded Mandates Act, the Agency must 
    identify and consider a reasonable number of regulatory alternatives 
    before promulgating a rule for which a budgetary impact statement must 
    be prepared. The Agency must select from those alternatives the least 
    costly, most cost-effective, or least burdensome alternative that 
    achieves the objectives of the rule, unless the Agency explains why 
    this alternative is not selected or the selection of this alternative 
    is inconsistent with law.
        Because this direct final rule is estimated to result in the 
    expenditure by State, local, and tribal governments or the private 
    sector of less than $100 million in any one year, the Agency has not 
    prepared a budgetary impact statement or specifically addressed the 
    selection of the least costly, most cost-effective, or least burdensome 
    alternative. Because small governments will not be significantly or 
    uniquely affected by this rule, the Agency is not required to develop a 
    plan with regard to small governments. However, as discussed in this 
    preamble, the rule has the net effect of reducing the burden of part 72 
    of the Acid Rain regulations on regulated entities, including both 
    investor-owned and municipal utilities.
    
    C. Paperwork Reduction Act
    
        The information collection requirements in this rule have been 
    approved by OMB under the Paperwork Reduction Act, 44 U.S.C. 3501, et 
    seq., and have been assigned control number 2060-0258. [[Page 18468]] 
        This collection of information reduces the estimated burden, as 
    compared to the burden under the January 11, 1993 regulations, by an 
    average of 35 hours per response for about 110 responses. These 
    estimates include time for reviewing instructions, searching existing 
    data sources, gathering and maintaining the data needed, and completing 
    and reviewing the collection of information. An Information Collection 
    Request document and estimates of the public reporting burden were 
    prepared in connection with the January 11, 1993 regulations. 56 FR 
    63098; 58 FR 3650.
        Send comments regarding this burden analysis or any other aspect of 
    this collection of information, including suggestions for reducing the 
    burden, to Chief, Information Policy Branch, EPA, 401 M Street, SW. 
    (Mail Code 2136), Washington, DC 20460; and to the Office of 
    Information and Regulatory Affairs, Office of Management and Budget, 
    Washington, DC 20503, marked ``Attention: Desk Officer for EPA.''
    
    D. Regulatory Flexibility Act
    
        The Regulatory Flexibility Act, 5 U.S.C. 601, et seq., requires 
    each federal agency to consider potential impacts of its regulations on 
    small business ``entities.'' Under 5 U.S.C. 604(a), an agency issuing a 
    notice of proposed rulemaking must prepare and make available for 
    public comment a regulatory flexibility analysis. Such an analysis is 
    not required if the head of an agency certifies that a rule will not 
    have a significant economic impact on a substantial number of small 
    entities, pursuant to 5 U.S.C. 605(b).
        In the preamble of the January 11, 1993 regulations, the 
    Administrator certified that those regulations, including the 
    provisions revised by today's final rule, would not have a significant 
    impact. 58 FR 3649. The final rule revisions adopted today are not 
    significant enough to change the economic impact addressed in the 
    January 11, 1993 preamble. Pursuant to the provisions of 5 U.S.C. 
    605(b), I hereby certify that the revised rule will not have a 
    significant, adverse impact on a substantial number of small entities.
    
    E. Miscellaneous
    
        In accordance with section 117 of the Act, issuance of this rule 
    was preceded by consultation with any appropriate advisory committees, 
    independent experts, and federal departments and agencies.
    
    List of Subjects in 40 CFR Part 72
    
        Environmental protection, Acid rain program, Air pollution control, 
    Compliance plans, Electric utilities, Permits, Reporting and 
    recordkeeping requirements, Sulfur dioxide.
    
        Dated: March 31, 1995.
    Carol M. Browner,
    Administrator, U.S. Environmental Protection Agency.
    
        For the reasons set forth in the preamble, chapter I of title 40 of 
    the Code of Federal Regulations is amended as follows.
    
    PART 72--[AMENDED]
    
        1. The authority citation for part 72 continues to read as follows:
    
        Authority: 42 U.S.C. 7601 and 7651, et seq.
    
        2. Section 72.2 is amended by revising the definitions for 
    ``sulfur-free generation'' and ``utility system'' to read as follows:
    
    
    Sec. 72.2  Definitions.
    
    * * * * *
        Sulfur-free generation means the generation of electricity by a 
    process that does not have any emissions of sulfur dioxide, including 
    hydroelectric, nuclear, solar, or wind generation. A ``sulfur-free 
    generator'' is a generator that is located in one of the 48 contiguous 
    States or the District of Columbia and produces ``sulfur-free 
    generation.''
    * * * * *
        Utility system means all interconnected units and generators 
    operated by the same utility operating company.
    * * * * *
        3. Section 72.33 is amended by revising paragraphs (a), (b)(2), 
    (b)(3), (c)(2), (c)(4), (e), and (f) to read as follows:
    
    
    Sec. 72.33  Identification of dispatch system.
    
        (a) Every Phase I unit shall be treated as part of a dispatch 
    system for purposes of Secs. 72.91 and 72.92 in accordance with this 
    section.
        (b) * * *
        (2) Except as provided in paragraph (f) of this section, each unit 
    or generator may be included in only one dispatch system.
        (3) Any identification of dispatch system must be submitted by 
    January 30 of the first year for which the identification is to be in 
    effect.
        (c) * * *
        (2) The list of all units and generators (including sulfur-free 
    generators) in the dispatch system.
    * * * * *
        (4) The following statement: ``I certify that, except as otherwise 
    required under a petition as approved under 40 CFR 72.33(f), the units 
    and generators listed herein are and will continue to be interconnected 
    and centrally dispatched, and will be treated as a dispatch system 
    under 40 CFR 72.91 and 72.92, during the period that this 
    identification of dispatch system is in effect. During such period, all 
    information concerning these units and generators and contained in any 
    submissions under 40 CFR 72.91 and 72.92 by me and the other designated 
    representatives of these units shall be consistent and shall conform 
    with the data in the dispatch system data reports under 40 CFR 
    72.92(b). I am aware of, and will comply with, the requirements imposed 
    under 40 CFR 72.33(e)(2).''
    * * * * *
        (e) (1) Any unit or generator not listed in a complete 
    identification of dispatch system that is in effect shall treat its 
    utility system as its dispatch system and, if such unit or generator is 
    listed in the NADB, shall treat the utility system reported under the 
    data field ``UTILNAME'' of the NADB as its utility system.
        (2) During the period that the identification of dispatch system is 
    in effect all information that concerns the units and generators in a 
    given dispatch system and that is contained in any submissions under 
    Secs. 72.91 and 72.92 by designated representative of these units shall 
    be consistent and shall conform with the data in the dispatch system 
    data reports under Sec. 72.92(b). If this requirement is not met, the 
    Administrator may reject all such submissions and require the 
    designated representatives to make the submissions under Secs. 72.91 
    and 72.92 (including the dispatch system data report) treating the 
    utility system of each unit or generator as its respective dispatch 
    system and treating the identification of dispatch system as no longer 
    in effect.
        (f)(1) Notwithstanding paragraph (e)(1) of this section or any 
    submission of an identification of dispatch system under paragraphs (b) 
    or (d) of this section, the designated representative of a Phase I unit 
    with two or more owners may petition the Administrator to treat, as the 
    dispatch system for an owner's portion of the unit, the dispatch system 
    of another unit.
        (i) The owner's portion of the unit shall be based on one of the 
    following apportionment methods:
        (A) Owner's share of the unit's capacity in 1985-1987. Under this 
    method, the baseline of the owner's portion of the unit shall equal the 
    [[Page 18469]] baseline of the unit multiplied by the average of the 
    owner's percentage ownership of the capacity of the unit for each year 
    during 1985-1987. The actual utilization of the owner's portion of the 
    unit for a year in Phase I shall equal the actual utilization of the 
    unit for the year that is attributed to the owner.
        (B) Owner's share of the unit's baseline. Under this method, the 
    baseline of the owner's portion of the unit shall equal the average of 
    the unit's annual utilization in 1985-1987 that is attributed to the 
    owner. The actual utilization of the owner's portion of the unit for a 
    year in Phase I shall equal the actual utilization of the unit for the 
    year that is attributed to the owner.
        (ii) The annual or actual utilization of a unit shall be 
    attributed, under paragraph (f)(1)(i) of this section, to an owner of 
    the unit using accounting procedures consistent with those used to 
    determine the owner's share of the fuel costs in the operation of the 
    unit during the period for which the annual or actual utilization is 
    being attributed.
        (iii) Upon submission of the petition, the designated 
    representative may not change the election of the apportionment method 
    or the baseline of the owner's portion of the unit.
        The same apportionment method must be used for all portions of the 
    unit for all years in Phase I for which any petition under paragraph 
    (f)(1) of this section is approved and in effect.
        (2) The petition under paragraph (f)(1) of this section shall be 
    submitted by January 30 of the first year for which the dispatch system 
    proposed in the petition will take effect, if approved. A complete 
    petition shall include the following elements in a format prescribed by 
    the Administrator:
        (i) The election of the apportionment method under paragraph 
    (f)(1)(i) of this section.
        (ii) The baseline of the owner's portion of the unit and the 
    baseline of any other owner's portion of the unit for which a petition 
    under paragraph (f)(1) of this section has been approved or has been 
    submitted (and not disapproved) and a demonstration that the sum of 
    such baselines and the baseline of any remaining portion of the unit 
    equals 100 percent of the baseline of the unit. The designated 
    representative shall also submit, upon request, either:
        (A) Where the unit is to be apportioned under paragraph 
    (f)(1)(i)(A) of this section, documentation of the average of the 
    owner's percentage ownership of the capacity of the unit for each year 
    during 1985-1987; or
        (B) Where the unit is to be apportioned under paragraph 
    (f)(1)(i)(B) of this section, documentation showing the attribution of 
    the unit's utilization in 1985, 1986, and 1987 among the portions of 
    the unit and the calculation of the annual average utilization for 
    1985-1987 for the portions of the unit.
        (iii) The name of the proposed dispatch system and a list of all 
    units (including portions of units) and generators in that proposed 
    dispatch system and, upon request, documentation demonstrating that the 
    owner's portion of the unit, along with the other units in the proposed 
    dispatch system, are a group of all units and generators that are 
    interconnected and centrally dispatched by a single utility company, 
    the service company of a single holding company, or a single power 
    pool.
        (iv) The following statement, signed by the designated 
    representatives of all units in the proposed dispatch system: ``I 
    certify that the units and generators in the dispatch system proposed 
    in this petition are and will continue to be interconnected and 
    centrally dispatched, and will be treated as a dispatch system under 40 
    CFR 72.91 and 72.92, during the period that this petition, as approved, 
    is in effect.''
        (v) The following statement, signed by the designated 
    representatives of all units in all dispatch systems that will include 
    any portion of the unit if the petition is approved: ``During the 
    period that this petition, if approved, is in effect, all information 
    that concerns the units and generators in any dispatch system including 
    any portion of the unit apportioned under the petition and that is 
    contained in any submissions under 40 CFR 72.91 and 72.92 by me and the 
    other designated representatives of these units shall be consistent and 
    shall conform to the data in the dispatch system data reports under 40 
    CFR 72.92(b). I am aware of, and will comply with, the requirements 
    imposed under 40 CFR 72.33(f) (4) and (5).''
        (3) (i) The Administrator will approve in whole, in part, or with 
    changes or conditions, or deny the petition under paragraph (f)(1) of 
    this section within 90 days of receipt of the petition. The 
    Administrator will treat the petition, as changed or conditioned upon 
    approval, as amending any identification of dispatch system that is 
    submitted prior to the approval and includes any portion of the unit 
    for which the petition is approved. Where any portion of a unit is not 
    covered by an approved petition, that remaining portion of the unit 
    shall continue to be part of the unit's dispatch system.
        (ii) In approving the petition, the Administrator will determine, 
    on a case-by-case basis, the proper calculation and treatment, for 
    purposes of the reports required under Secs. 72.91 and 72.92, of plan 
    reductions and compensating generation provided to other units.
        (4) The designated representative for the unit for which a petition 
    is approved under paragraph (f)(3) of this section and the designated 
    representatives of all other units included in all dispatch systems 
    that include any portion of the unit shall submit all annual compliance 
    certification reports, dispatch system data reports, and other reports 
    required under Secs. 72.91 and 72.92 treating, as a separate Phase I 
    unit, each portion of the unit for which a petition is approved under 
    paragraph (f)(3) of this section and the remaining portion of the unit. 
    The reports shall include all required calculations and demonstrations, 
    treating each such portion of the unit as a separate Phase I unit. Upon 
    request, the designated representatives shall demonstrate that the data 
    in all the reports under Secs. 72.91 and 72.92 has been properly 
    attributed or apportioned among the portions of the unit and the 
    dispatch systems and that there is no undercounting or double-counting 
    with regard to such data.
        (i) The baseline of each portion of the unit for which a petition 
    is approved shall be determined under paragraphs (f)(1) (i) and (ii) of 
    this section. The baseline of the remaining portion of such unit shall 
    equal the baseline of the unit less the sum of the baselines of any 
    portions of the unit for which a petition is approved.
        (ii) The actual utilization of each portion of the unit for which a 
    petition is approved shall be determined under paragraphs (f)(l) (i) 
    and (ii) of this section. The actual utilization of the remaining 
    portion of such unit shall equal the actual utilization of the unit 
    less the sum of the actual utilizations of any portions of the unit for 
    which a petition is approved. Upon request, the designated 
    representative of the unit shall demonstrate in the annual compliance 
    certification report that the requirements concerning calculation of 
    actual utilization under paragraph (f)(1)(ii) and any requirements 
    established under paragraph (f)(3) of this section are met.
        (iii) Except as provided in paragraph (f)(5) of this section, the 
    designated representative shall surrender for deduction the number of 
    allowances calculated using the formula in Sec. 72.92(c) and treating, 
    as a separate Phase I unit, each portion of unit for which a petition 
    is approved under paragraph (f)(3) of this section and the remaining 
    portion of the unit.
        (5) In the event that the designated representatives fail to make 
    all the proper attributions, apportionments, 
    [[Page 18470]] calculations, and demonstrations under paragraph (f)(4) 
    of this section and Secs. 72.91 and 72.92, the Administrator may 
    require that:
        (i) All portions of the unit be treated as part of the dispatch 
    system of the unit in accordance with paragraph (e)(1) of this 
    paragraph and any identification of dispatch system submitted under 
    paragraph (b) or (d) of this section;
        (ii) The designated representatives make all submissions under 
    Secs. 72.91 and 72.92 (including the dispatch system data report), 
    treating the entire unit as a single Phase I unit, in accordance with 
    paragraph (e)(1) of this paragraph and any identification of dispatch 
    system submitted under paragraph (b) or (d) of this section; and
        (iii) The designated representative surrender for deduction the 
    number of allowances calculated, consistent with the reports under 
    paragraph (f)(5)(ii) of this section and Secs. 72.91 and 72.92, using 
    the formula in Sec. 72.92(c) and treating the entire unit as a single 
    Phase I unit.
        (6) The designated representative may submit a notification to 
    terminate an approved petition by January 30 of the first year for 
    which the termination is to take effect. The notification must be 
    signed and certified by the designated representatives of all units 
    included in all dispatch systems that include any portion of the unit 
    apportioned under the petition. Upon receipt of the notification 
    meeting the requirements of the prior two sentences by the 
    Administrator, the approved petition is no longer in effect for that 
    year and the remaining years in Phase I and the designated 
    representatives shall make all submissions under Secs. 72.91 and 72.92 
    treating the petition as no longer in effect for all such years.
        (7) Except as expressly provided in paragraphs (f)(1) through (6) 
    of this section or the Administrator's approval of the petition, all 
    provisions of the Acid Rain Program applicable to an affected source or 
    an affected unit shall apply to the entire unit regardless of whether a 
    petition has been submitted or approved, or reports have been 
    submitted, under such paragraphs. Approval of a petition under such 
    paragraphs shall not constitute a determination of the percentage 
    ownership in a unit under any other provision of the Acid Rain Program 
    and shall not change the liability of the owners and operators of an 
    affected unit that has excess emissions under Sec. 72.9(e).
        4. Section 72.43 is amended by revising paragraph (e) to read as 
    follows:
    
    
    Sec. 72.43  Phase I reduced utilization plans.
    
    * * * * *
        (e) Failure to Submit a Plan. The designated representative of a 
    Phase I unit will be deemed not to violate, during a Phase I calendar 
    year, the requirement to submit a reduced utilization plan under 
    paragraph (b)(1) or (4) of this section if the designated 
    representative complies with the allowance surrender and other 
    requirements of Secs. 72.33, 72.91, and 72.92 of this chapter.
    * * * * *
        5. Section 72.91 is amended by revising the introductory language 
    of paragraph (a) (the formula is unchanged) to read as follows:
    
    
    Sec. 72.91  Phase I unit adjusted utilization.
    
        (a) Annual Compliance Certification Report. The designated 
    representative for each Phase I unit shall include in the annual 
    compliance certification report the unit's adjusted utilization for the 
    calendar year in Phase I covered by the report, calculated as follows:
    * * * * *
        6. Section 72.92 is amended by revising paragraphs (a), 
    (b)(2)(ii)(F), (b)(2)(ii)(G), (b)(2)(ii)(H), (c)(2)(v) and Table 1, 
    removing and reserving paragraph (b)(1), and adding paragraphs 
    (b)(2)(ii)(I) and (b)(2)(ii)(J) to read as follows:
    
    
    Sec. 72.92  Phase I unit allowance surrender.
    
        (a) Annual Compliance Certification Report. If a Phase I unit's 
    adjusted utilization for the calendar year in Phase I under 
    Sec. 72.91(a) is greater than zero, then the designated representative 
    shall include in the annual compliance certification report the number 
    of allowances that shall be surrendered for adjusted utilization using 
    the formula in paragraph (c) of this section and the calculations that 
    were performed to obtain that number.
        (b) Other Submissions.
        (1) [Reserved]
        (2) * * *
        (ii) * * *
        (F) The calculation of ``dispatch system emissions rate'' under 
    paragraph (c)(2)(v)(B) of this section;
        (G) The calculation of ``fraction of generation from non-utility 
    generators'' under paragraph (c)(2)(v)(C) of this section;
        (H) The calculation of ``non-utility generator average emissions 
    rate `` under paragraph (c)(2)(v)(F) of this section;
        (I) A certification that each designated representative will use 
    these figures, as appropriate, in its annual compliance certification 
    report and will submit upon request the data supporting these 
    calculations; and
        (J) The signatures of all the designated representatives.
        (c) * * *
        (2) * * *
        (v) Calculating Emissions Rate. ``Emissions rate'' (in lbs/mmBtu) 
    is the weighted average emissions rate for sulfur dioxide of all units 
    and generators, within and outside the dispatch system, that 
    contributed to the dispatch system's electrical output for the year, 
    calculated as follows:
    
    Emissions rate = [fraction of generation within dispatch system  x  
    dispatch system emissions rate] + [fraction of generation from non-
    utility generators  x  non-utility generator average emissions rate] 
    + [fraction of generation outside dispatch system  x  fraction of 
    non-Phase 1 and non-foreign generation in NERC region  x  NERC 
    region emissions rate]
    
    Where:
    
        (A) ``Fraction of generation within dispatch system'' is the 
    fraction of the dispatch system's total sales accounted for by 
    generation from units and generators within the dispatch system, other 
    than generation from non-utility generators. This term equals the total 
    generation (in Kwh) by all units and generators within the dispatch 
    system for the calendar year minus the total non-utility generation 
    from non-utility generators within the dispatch system for the calendar 
    year and divided by the total sales (in Kwh) by the dispatch system for 
    the calendar year.
        (B) Dispatch system emissions rate'' is the weighted average rate 
    (in lbs/mmBtu) for the dispatch system calculated as follows:
        Dispatch system emissions rate =
    [GRAPHIC][TIFF OMITTED]TR11AP95.000
    
    
    [[Page 18471]]
    
    Where:
    
    gi = the difference between a Phase II unit's actual 
    utilization for the calendar year and that Phase II unit's baseline. 
    If that difference is less than or equal to zero, then the 
    difference shall be treated as zero only for purposes of paragraph 
    (c)(2)(v) of this section and that unit will be excluded from the 
    calculation of dispatch system emissions rate. Notwithstanding the 
    prior sentence, if the actual utilization of each Phase II unit for 
    the year is equal to or less than the baseline, then gi shall 
    equal a Phase II unit's actual utilization for the year. 
    Notwithstanding any provision in this paragraph (c)(2)(v)(B) to the 
    contrary, if the actual utilization of each Phase II unit in the 
    dispatch system is zero or there are no Phase II units in the 
    dispatch system, then the dispatch system emissions rate shall equal 
    the fraction of non-Phase I and non-foreign generation in the NERC 
    region multiplied by the NERC region emissions rate.
    ri = a Phase II unit's emissions rate (in lbs/mmBtu), 
    determined in accordance with part 75 of this chapter, for the 
    calendar year.
    k = number of Phase II units in the dispatch system.
    
        (C) ``Fraction of generation from non-utility generators'' is the 
    fraction of the dispatch system's total sales accounted for by 
    generation acquired from non-utility generators within or outside the 
    dispatch system. This term equals the total non-utility generation from 
    non-utility generators (within or outside the dispatch system) for the 
    calendar year divided by the total sales (in Kwh) by the dispatch 
    system for the calendar year.
        (D) ``Non-utility generator'' is a power production facility 
    (within or outside the dispatch system) that is not an affected unit or 
    a sulfur-free generator and that has a ``non-utility generator 
    emissions rate'' for the calendar year under paragraph (c)(2)(v)(F) of 
    this section.
        (E) ``Non-utility generation'' is the generation (in Kwh) that the 
    dispatch system acquired from a non-utility generator during the 
    calendar year as required by federal or State law or an order of a 
    utility regulatory authority or under a contract awarded as the result 
    of a power purchase solicitation required by federal or State law or an 
    order of a utility regulatory authority.
        (F) ``Non-utility generator average emissions rate'' is the 
    weighted average rate (in lbs/mmBtu) for the non-utility generators 
    calculated as follows:
        Non-utility generator average emissions rate =
    [GRAPHIC][TIFF OMITTED]TR11AP95.001
    
    
    Where:
    
    Ni = non-utility generation from a non-utility generator;
    Ri = non-utility generator emissions rate for the calendar year 
    for a non-utility generator, which shall equal the most stringent 
    federally enforceable or State enforceable SO2 emissions 
    limitation applicable for the calendar year to such power production 
    facility, as determined in accordance with paragraphs (c)(2)(v)(F) 
    (1), (2), and (3) of this section; and
    n = number of non-utility generators from which the dispatch system 
    acquired non-utility generation. If n equals zero, then the non-
    utility generator average emissions rate shall be treated as zero 
    only for purposes of paragraph (c)(2)(v) of this section.
    
        (1) For purposes of determining the most stringent emissions 
    limitation, applicable emissions limitations shall be converted to lbs/
    mmBtu in accordance with Appendix B of this part. If an applicable 
    emissions limitation cannot be converted to a unit-specific limitation 
    in lbs/mmBtu under appendix B of this part, then the limitation shall 
    not be used in determining the most stringent emissions limitation. 
    Where the power production facility is subject to different emissions 
    limitations depending on the type of fuel it uses during the calendar 
    year, the most stringent emissions limitation shall be determined 
    separately with regard to each type of fuel and the resulting 
    limitation with the highest amount of lbs/mmBtu shall be treated as the 
    facility's most stringent federally enforceable or State enforceable 
    emissions limitation.
        (2) If there is no applicable emissions limitation that can be used 
    in determining the most stringent emissions limitation under paragraph 
    (c)(2)(v)(F)(1) of this section, then the power production facility has 
    no non-utility generator emissions rate for purposes of paragraphs 
    (c)(2)(v) (D) and (F) of this section and the generation from the 
    facility shall be treated, for purposes of this paragraph (c)(2)(v) as 
    generation from units and generators within the dispatch system if the 
    facility is within the dispatch system or as generation from units and 
    generators outside the dispatch system if the facility is outside the 
    dispatch system.
        (3) Notwithstanding paragraphs (c)(2)(v)(F) (1) and (2) of this 
    section, if the power production facility is authorized under federal 
    or State law to use only natural gas as fuel, then the most stringent 
    emissions limitation for the facility for the calendar year shall be 
    deemed to be 0.0006 lbs/mmBtu.
        (G) ``Fraction of generation outside dispatch system'' = 1-fraction 
    of generation within dispatch system-fraction of generation from non-
    utility generators.
        (H) ``Fraction of non-Phase I and non-foreign generation in NERC 
    region'' is the portion of the NERC region's total sales generated by 
    units and generators other than Phase I units or foreign sources in the 
    unit's NERC region in 1985, as set forth in Table 1 of this section.
        (I) ``NERC region emissions rate'' is the weighted average emission 
    rate (in lbs/mmBtu) for the unit's NERC region in 1985, as set forth in 
    Table 1 of this section.
    
           Table 1.--NERC Region Generation and Emissions Rate in 1985      
    ------------------------------------------------------------------------
                                                        Fraction            
                                                         of non-      NERC  
                                                         phase I    weighted
                                                        and non-    average 
                       NERC region                       foreign   emissions
                                                       generation  rate (lbs/
                                                         in NERC     mmBtu) 
                                                         region             
    ------------------------------------------------------------------------
    WSCC.............................................       0.847      0.466
    SPP..............................................       0.948      0.647
    SERC.............................................       0.749      1.315
    NPCC.............................................       0.423      1.058
    MAPP.............................................       0.725      1.171
    MAIN.............................................       0.682      1.495
    MAAC.............................................       0.750      1.599
    ERCOT............................................       1.000      0.491
    ECAR.............................................       0.549      1.564
    ------------------------------------------------------------------------
    
    [FR Doc. 95-8601 Filed 4-10-95; 8:45 am]
    BILLING CODE 6560-50-P
    
    

Document Information

Effective Date:
5/22/1995
Published:
04/11/1995
Department:
Environmental Protection Agency
Entry Type:
Rule
Action:
Direct final rule.
Document Number:
95-8601
Dates:
This direct final rule will be effective on May 22, 1995 unless significant, adverse comments are received by May 11, 1995. If significant, adverse comments are timely received on any portion of the direct final rule, that portion of the direct final rule will be withdrawn through a notice in the Federal Register.
Pages:
18462-18471 (10 pages)
Docket Numbers:
FRL-5186-3
RINs:
2060-AE59
PDF File:
95-8601.pdf
Supporting Documents:
» Acid Rain Program: Permits
» Acid Rain Program: Permits
» Acid Rain Program: Permits
» Acid Rain Program: Permits and Allowance System Proposed Regulations; Change in Public Comment Period for the Proposed Revisions to the Rules
» Acid Rain Program; Permits and Allowance System Proposed Regulations; Change in Public Comment Period for the Proposed Revisions to the Rules
» Add Rain Program: Notice of Final Permit [A-93-40-I-A-11]
» Draft Acid Rain Permits Public Comment Period; Correction [A-93-40-I-A-10]
» Acid Rain Program: General Provisions and Permits, Allowance System, Continuous Emissions Monitoring, Excess Emissions and Administrative Appeals; Correction [A-93-40-I-A-9]
» Add Rain Allowance Allocations and Reserves; Correction to Final Regulations [A-93-40-I-A-8]
» Legacy Index for Docket A-93-40
CFR: (11)
40 CFR 72.91(a)
40 CFR 72.92(b)
40 CFR 72.33(c)(4)
40 CFR 72.43(e)(2)
40 CFR 72.43(e)
More ...