DEPARTMENT OF ENERGY
[Project No. 11480 Alaska]
Haida Corporation; Notice of Scoping Pursuant to the National
Environmental Policy Act of 1969
April 5, 1996.
The Energy Policy Act of 1992, allows applicants to prepare their
own draft environmental assessment (EA) for hydropower projects and
file it with the Federal Energy Regulatory Commission (Commission)
along with their license application as part of the ``applicant-
prepared EA'' process. InterMountain Energy, as agent for the Haida
Corporation, intends to prepare an EA to file with the Commission for
the Reynolds Creek Hydroelectric Project No. 11480. InterMountain
Energy will hold two public scoping meetings, pursuant to the National
Environmental Policy Act of 1969, to identify the scope of
environmental issues that should be analyzed in the EA.
Scoping Meetings
The times and locations of the two scoping meetings are:
Agency Meeting
Date: Monday, May 6, 1996.
Place: City Council Chambers, 334 Front Street, Ketchikan, AK.
Time: 1:00 pm.
Public Meeting
Date: Monday, May 6, 1996.
Place: City Building, Hydaburg, AK.
Time: 6:00 pm.
At the scoping meetings, InterMountain Energy will (1) summarize
the environmental issues tentatively identified for analysis in the EA;
(2) solicit from the meeting participants all available information,
especially qualified data, on the resources at issue; and (3) encourage
statements from experts and the public on issues that should be
analyzed in the EA.
All interested individuals, organizations, and agencies are invited
and encouraged to attend either or both meetings to assist in
identifying and clarifying the scope of environmental issues that
should be analyzed in the EA.
To help focus discussions at the meetings, InterMountain Energy
prepared and distributed Scoping Document 1 for this project. Copies of
this scoping document can be obtained by calling Jack Goldwasser of
InterMountain Energy at (541) 592-2187, or can be obtained directly at
either meeting.
Site Visit
InterMountain Energy will also conduct a site visit for this
project on Tuesday, May 7, 1996. Those planning to attend the site
visit should contact Jack Goldwasser at (541) 592-2187 at least three
days prior to that date.
Meeting Procedures
The meetings will be conducted according to the procedures used at
Commission scoping meetings. Because this meeting will be a NEPA
scoping meeting, the Commission will not conduct another NEPA scoping
meeting when the application and draft EA are filed with the
Commission.
Both meetings will be recorded by a stenographer, and thus will
become a part of the formal record of the proceedings for this project.
Those who choose not to speak may instead submit written comments
on the project. These comments should be mailed to Jack Goldwasser,
InterMountain Energy, 115 Airport Drive, P.O. Box 421, Cave Junction,
OR 97523. All correspondence should clearly show the following caption
on the first page: Scoping Comments, Reynolds Creek Project, FERC No.
11480, Alaska.
For further information, please contact Jack Goldwasser at (541)
592-2187, or Mike Strzelecki of the Commission at (202) 219-2827.
Lois D. Cashell,
Secretary.