NUCLEAR REGULATORY COMMISSION
[Docket No. 50-255]
Consumers Power Company; Notice of Denial of Amendment to
Facility Operating License and Opportunity For Hearing
The U.S. Nuclear Regulatory Commission (the Commission) has denied
a portion of a request by Consumers Power Company (the licensee) for an
amendment to Facility Operating License No. DPR-20 issued to the
licensee for operation of the Palisades Plant located in Van Buren
County, Michigan. Notice of Consideration of Issuance of this amendment
was published in the Federal Register on November 27, 1995 (60 FR
58399).
The purpose of the licensee's amendment request was to revise the
Facility Operation License (FOL) to reference 10 CFR Part 40, allow the
use of source materials as reactor fuel, delete references to specific
amendments and specific revisions in the listed titles of the Physical
Security Plan, Suitability Training and Qualification Plan, and the
Safeguards Contingency Plan, delete paragraph 2.F on reporting
requirements, and make minor editorial changes to the license. The
Technical Specifications (TS) would also be revised to: (1) Modify TS
3.1.2 to change the pressurizer cooldown limit from 100 deg.F to
200 deg.F/hour; (2) relocate the shield cooling system requirements to
the Final Safety Analysis Report; (3) make minor editorial changes and
corrections; and (4) revise several TS bases pages.
The NRC staff has concluded that the licensee's request to delete
paragraph 2.F of the FOL cannot be granted. The licensee was notified
of the Commission's denial of the proposed change by a letter dated
April 5, 1996.
By May 13, 1996, the licensee may demand a hearing with respect to
the denial described above. Any person whose interest may be affected
by this proceeding may file a written petition for leave to intervene.
A request for hearing or petition for leave to intervene must be
filed with the Secretary of the Commission, U.S. Nuclear Regulatory
Commission, Washington, DC 20555, Attention: Docketing and Services
Branch, or may be delivered to the Commission's Public Document Room,
the Gelman Building, 2120 L Street, NW., Washington, DC, by the above
date.
A copy of any petitions should also be sent to the Office of the
General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC
20555, and to Judd L. Bacon, Esquire, Consumers Power Company, 212 West
Michigan Avenue, Jackson, Michigan 49201, attorney for the licensee.
For further details with respect to this action, see (1) the
application for amendment dated October 17, 1995, and (2) the
Commission's letter to the licensee dated April 5, 1996.
These documents are available for public inspection at the
Commission's Public Document Room, the Gelman Building, 2120 L Street,
NW., Washington, DC, and at the local public document room located at
the Van Wylen Library, Hope College, Holland, Michigan 49423.
Dated at Rockville, Maryland, this 5th day of April 1996.
For the Nuclear Regulatory Commission.
Mark F. Reinhart,
Acting Project Director, Project Directorate III-1, Division of Reactor
Projects--III/IV, Office of Nuclear Reactor Regulation.
[FR Doc. 96-9023 Filed 4-10-96; 8:45 am]
BILLING CODE 7590-01-P