94-8622. Passage of Instrumented Internal Inspection Devices  

  • [Federal Register Volume 59, Number 70 (Tuesday, April 12, 1994)]
    [Rules and Regulations]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-8622]
    
    
    [[Page Unknown]]
    
    [Federal Register: April 12, 1994]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    DEPARTMENT OF TRANSPORTATION
    
    Research and Special Programs Administration
    
    49 CFR Part 190, 192, 193, and 195
    
    RIN 2137-AB71
    [Docket No. PS-126; Amdts. 190-5, 192-72, 193-9, 195-50]
    
    Passage of Instrumented Internal Inspection Devices
    
    AGENCY: Research and Special Programs Administration (RSPA), DOT.
    
    ACTION: Final rule.
    
    -----------------------------------------------------------------------
    
    SUMMARY: This final rule amends the gas, hazardous liquid and carbon 
    dioxide pipeline safety regulations to require that certain new and 
    replacement pipelines be designed and constructed to accommodate the 
    passage of instrumented internal inspection devices (smart pigs). This 
    action was taken in response to a mandate in the Pipeline Safety 
    Reauthorization Act of 1988. The intended effect of these amended 
    regulations is to improve the safety of gas, hazardous liquid and 
    carbon dioxide pipelines by permitting their inspection by ``smart 
    pigs'' using the latest technology for detecting and recording 
    abnormalities in the pipe wall.
    
    EFFECTIVE DATE: The effective date of this final rule is May 12, 1994.
    
    FOR FURTHER INFORMATION CONTACT: Albert C. Garnett, (202) 366-2036 
    regarding the subject matter of this amendment or the Docket Unit, 
    (202) 366-5046 regarding copies of this amendment or other material in 
    the docket.
    
    SUPPLEMENTARY INFORMATION:
    
    Notice of Proposed Rulemaking
    
        RSPA published a Notice of Proposed Rulemaking (NPRM) on November 
    20, 1992 (57 FR 54745) proposing that new and replacement gas 
    transmission lines and new and replacement hazardous liquid pipelines 
    and carbon dioxide pipelines be designed and constructed to accommodate 
    the passage of instrumented internal inspection devices. However, the 
    rules would not apply to specific installations for which such design 
    and construction would be impracticable. In addition, the NPRM proposed 
    a procedure for operators seeking an administrative ruling on any rule 
    in parts 192, 193 and 195 in which the administrator is authorized to 
    make a finding or approval.
        The NPRM was issued in response to Congressional mandates in 
    sections 108(b) and 207(b) of the Pipeline Safety Reauthorization Act 
    of 1988 (hereinafter ``Reauthorization Act'') (Pub. L. 100-561; Oct. 
    31, 1988). Section 108(b) of the Reauthorization Act amended section 3 
    of the Natural Gas Pipeline Safety Act of 1968 (NGPSA) by adding 
    subsection (g), ``Instrumented Internal Inspection Devices'' (49 app. 
    U.S.C. 1672). This new subsection requires the Secretary of 
    Transportation to establish regulations requiring that:
    
        (1) The design and construction of new [gas] transmission 
    facilities, and (2) when replacement of existing transmission 
    facilities or equipment is required, the replacement of such 
    existing facilities, be carried out, to the extent practicable, in a 
    manner so as to accommodate the passage through such transmission 
    facilities of instrumented internal inspection devices (commonly 
    referred to as ``smart pigs'').
    
    Section 207(b) of the Reauthorization Act amended section 203 of the 
    Hazardous Liquid Pipeline Safety Act of 1979 (HLPSA) (49 app. U.S.C. 
    2002) to require that DOT establish similar regulations with respect to 
    pipeline facilities subject to the HLPSA.
    
    Future Rulemaking Involving Smart Pigs
    
        The Pipeline Safety Act of 1992 (hereinafter ``PLSA of 1992'') 
    (Pub. L. 102-508; Oct. 24, 1992) in sections 103 and 203 amended the 
    NGPSA and the HLPSA, respectively, by requiring the Secretary of 
    Transportation to issue regulations that require the periodic 
    inspection of gas transmission facilities and hazardous liquid 
    pipelines in high-density population areas, and hazardous liquid 
    pipelines in environmentally sensitive areas or crossing navigable 
    waterways. In response to these mandates, RSPA will issue an NPRM 
    proposing to prescribe the circumstances, if any, under which such 
    inspections would be conducted with smart pigs. In those circumstances 
    under which an inspection by a smart pig would not be required, RSPA is 
    mandated to require the use of an inspection method that is at least as 
    effective as the use of smart pigs in providing for the safety of the 
    pipeline.
    
    Regulations
    
        In the NPRM, RSPA proposed to require all future new and 
    replacement gas transmission lines subject to 49 CFR part 192 and 
    hazardous liquid and carbon dioxide pipelines subject to 49 CFR part 
    195 to be designed and constructed to accommodate the passage of smart 
    pigs, except where impracticable. For the purposes of this rulemaking, 
    RSPA proposed that it would be impracticable to require the 
    accommodation of smart pigs under the following categories of piping: 
    Manifolds, station piping (such as compressor stations, pump stations, 
    metering stations or regulator stations), cross-overs, and fittings 
    providing branch line junctures (such as tees and other lateral 
    connections). Additionally, the NPRM proposed to allow pipeline 
    operators to petition (minimum 90 days in advance) the Administrator, 
    in a particular case, for a finding that design or construction to 
    accommodate a smart pig would be impracticable.
    
    Advisory Committees
    
        The Technical Pipeline Safety Standards Committee (TPSSC) and the 
    Technical Hazardous Liquid Pipeline Safety Standards Committee 
    (THLPSSC) have been established by statute to evaluate pipeline safety 
    regulations. The TPSSC and the THLPSSC met in joint session in 
    Washington, DC on August 3, 1993, and considered the NPRM. Both 
    committees accepted the NPRM as feasible, reasonable, and practicable 
    with the incorporation of several changes. RSPA's disposition of the 
    advisory committees' recommendations are discussed below.
    
    Discussion of Comments
    
        RSPA received public comments on the proposed rule change from 48 
    pipeline operators, seven pipeline-related associations, three state/
    Federal agencies, and one consulting engineer. The following discussion 
    explains how RSPA considered the advisory committees' positions and the 
    public comments on the proposed regulations in developing the final 
    rule.
    
    Low Stress Pipelines
    
        Twenty-three commenters indicated that the rule should except 
    pipelines in which the internal operating pressure results in low 
    stress in the pipe wall. Many commenters argued that since gas 
    transmission lines are not subject to certain pipeline safety 
    regulations (Secs. 192.609, 192.711 & 192.713) if they operate at or 
    below 40 percent of the specified minimum yield strength (SMYS), that 
    this rule should similarly not apply to these same transmission lines. 
    The TPSSC also recommended that piping operating at a stress level of 
    40 percent of SMYS or less be excepted.
        While RSPA understands this position, it does not agree that it 
    justifies exception of gas transmission lines based solely on their low 
    hoop stress at maximum operating pressure. Pipelines operating at lower 
    stress levels are as susceptible to corrosion and other types of 
    damage, identifiable by smart pigs, as pipelines operating at higher 
    stress. In addition, the Reauthorization Act mandate to require certain 
    new and replacement pipelines to be designed and constructed to 
    accommodate the passage of smart pigs limits RSPA's discretion only to 
    situations that make such design and construction impracticable. RSPA 
    finds that an exception from the requirements adopted in this rule for 
    pipelines operating at or below 40% SMYS is not appropriate, because 
    the pipe wall stress does not, within the terms of the Reauthorization 
    Act, affect the practicability of designing and constructing a line to 
    accommodate passage of smart pigs.
    
    Short Lengths
    
        Eighteen commenters recommended that the rule except new or 
    replacement pipelines based on their short lengths. Some commenters 
    recommended excepting replacement pipelines depending on whether the 
    adjoining portions of the pipeline are piggable. One of these 
    commenters reasoned that unless the adjoining portion of pipeline can 
    accommodate the passage of instrumented internal inspection devices, 
    there can be no added benefit from making a replacement section 
    piggable because the pipeline overall will still contain restrictions 
    prohibiting inspection by smart pigs.
        Nine commenters recommended exception of minimum lengths that 
    ranged from 2000 feet to 5 miles. A gas transmission line operator 
    recommended that the minimum excepted length should be the distance 
    between compressor stations (40 to 60 miles), to exclude the necessity 
    to replace non-full opening valves on short replacement sections. Four 
    commenters suggested that the minimum excepted length should be 
    determined by RSPA.
        The disparity of the commenters' recommendations illustrates that 
    there is no generally accepted rationale for determining the minimum 
    length, if any, of pipe that should be excepted. Moreover, RSPA does 
    not agree that the rule should except replacement pipelines based on 
    either the length of the replaced section of pipeline or on whether the 
    adjoining portion of pipeline can accommodate passage of instrumented 
    internal inspection devices.
        The plain objective of the statutory mandate is to make both short 
    and long pipelines that are not now piggable from end to end, piggable 
    in time through replacements. Therefore, the final rule does not 
    include these exceptions. However, operators wishing to except short 
    length pipelines may want to petition the Administrator under the 
    procedures set out in the new Sec. 190.9.
    
    Non-Steel Pipelines
    
        Five commenters recommended that the rule apply only to steel 
    pipelines. One commenter argued that current internal inspection 
    devices cannot monitor non-ferrous pipelines for stress corrosion. The 
    commenter contends that no benefit derives from the running of smart 
    pigs on these lines, and therefore it would be unreasonable to require 
    operators to make them piggable.
        Another commenter contended that, although some polyethylene gas 
    pipelines are by DOT definition transmission lines, there are no smart 
    pigs (except camera pigs) that are designed for use in plastic pipe.
        RSPA does not agree that the rule should except non-steel 
    pipelines. It is true that smart pigs cannot presently monitor non-
    steel pipelines for as many defects or anomalies as are detectable in 
    steel pipelines. However, smart pigs can currently detect some physical 
    defects in non-steel pipelines; i.e. dents, change in internal 
    diameter, ovality, misalignment of joints, and change in position of 
    the pipe. Moreover, by making new and replacement plastic pipelines 
    piggable, they will be able to accommodate new smart pig technology as 
    it is developed. Nonetheless, all the exceptions in this rule 
    applicable to steel pipelines are also applicable to non-steel 
    pipelines.
    
    Small Diameter Pipelines
    
        Twenty-four commenters recommended that the rule except the smaller 
    diameter pipelines. Some reasoned that commercially available smart pig 
    technology is limited to the larger pipe sizes. Consequently, for those 
    sizes of pipe for which there are no commercially available smart pigs, 
    designing and constructing pipelines to pass smart pigs would be 
    impracticable.
        RSPA does not agree that the rule should include a blanket 
    exception for all small diameter pipelines. In recent years we have 
    seen the increasing miniaturization of electro-mechanical components in 
    equipment used in smart pigs and we expect the trend to continue.
        RSPA understands that where no commercially available technology 
    exists to inspect a particular pipe size by smart pigs, the pipeline 
    operator would lack sufficient technical information to establish the 
    design and construction criteria, e.g. minimum internal pipe diameter 
    and minimum pipe bend radius, essential for passage of smart pigs. 
    Therefore, the final rule has been written to apply only to pipeline 
    diameters for which there is a commercially available smart pig at the 
    time the new or replacement pipeline is designed. At the time of 
    preparation of this document, RSPA finds that 4 inches is the minimum 
    nominal pipe size for which smart pigs are commercially available.
    
    Gas Transmission Lines Operated in Conjunction With Distribution 
    Systems
    
        Twelve commenters recommended that the rule except lines classified 
    as transmission lines because their hoop stress is 20 percent or more 
    of SMYS, that operate in conjunction with gas distribution systems. 
    They reasoned that, typically, these lines have components and 
    configurations that impede passage of instrumented internal inspection 
    devices.
        Some commenters reasoned that many of these transmission lines are 
    the sole gas supply to large gas distribution systems. So, inspection 
    of these lines by instrumented internal inspection devices could, if 
    problems develop while running the inspection device, disrupt customer 
    service.
        RSPA does not agree that the rule should provide an exception for 
    gas transmission lines that are operated in conjunction with 
    distribution systems (except as discussed under the heading ``Gas 
    transmission lines in crowded underground locations''). First, although 
    such lines may have configurations or components that impede inspection 
    by smart pigs, the commenters did not provide information to 
    substantiate the contention that these conditions are impracticable to 
    avoid on new or replacement lines. RSPA believes it is practicable to 
    design and construct new and replacement transmission lines operated in 
    conjunction with distribution systems to accommodate passage of smart 
    pigs. Second, potential service disruption (from stuck smart pigs) on 
    single feed transmission lines will not be a factor on lines that are 
    properly designed, constructed and maintained to accommodate smart 
    pigs. Also, to further reduce the possibility of the smart pig becoming 
    stuck, prior runs can be scheduled, with cleaning and caliper pigs, 
    during periods of minimal load requirements. Third, the use of smart 
    pigs to monitor the integrity of single feed transmission lines can 
    detect problems before they can affect the reliability of the gas 
    supply to the customers.
    
    Gas Transmission Lines in Crowded Underground Locations
    
        Twelve commenters recommended that RSPA except gas transmission 
    lines located in certain urban areas. Most of them pointed out that 
    utility locations underneath city streets in downtown urban areas are 
    typically overcrowded. Physical constraints from other utilities and 
    the structural boundary of available space make the design and 
    construction of replacement pipelines to accommodate smart pigs 
    impracticable. For example, many underground utility locations lack 
    sufficient clearance between existing utilities to allow the 
    replacement of existing short radius elbows with longer radius elbows 
    (which consume more space) to permit passage of smart pigs. 
    Nonetheless, a commenter from a state with few large cities suggested 
    that internal inspection devices should only be required for pipelines 
    located in Class 3 or 4 locations and in environmentally sensitive 
    areas.
        While gas transmission lines operated in conjunction with 
    distribution systems are generally covered under this rule, RSPA agrees 
    that the rule should provide an exception whenever gas transmission 
    lines operated in conjunction with distribution systems are located in 
    certain congested urban areas. RSPA believes it is impracticable to 
    design and construct these particular transmission lines, considering 
    the arguments presented above, to accommodate passage of smart pigs 
    when there exist physical constraints, not associated with the pipe 
    itself, which are beyond an operator's control. Furthermore, RSPA 
    understands that underground utility areas in Class 4 locations are 
    typically overcrowded and unable to accommodate the pipeline 
    configurations needed for the accommodation of smart pigs. So, in the 
    final rule, Sec. 192.150(b)(6) excepts gas transmission lines that are: 
    Operated in conjunction with a gas distribution system and installed in 
    Class 4 locations. However, gas transmission lines, not operated in 
    conjunction with a gas distribution system are not excepted because 
    these lines generally pose greater risks, typically transporting gas at 
    higher pressures.
    
    Gas, Oil and Carbon Dioxide Storage Facilities
    
        Twelve commenters recommended that the rule except gas transmission 
    lines which are part of injection/withdrawal systems at gas storage 
    facilities. Commenters said these gas storage facilities have small 
    diameter piping configured in a grid-like pattern that would not permit 
    the passage of smart pigs. The TPSSC likewise recommended that storage 
    facilities be excepted. Similarly, one commenter urged an exception of 
    delivery/withdrawal piping associated with hazardous liquid storage in 
    breakout tanks, due to the short lengths, short radius bends and other 
    tank farm piping configurations which are unable to accommodate the 
    passage of smart pigs. The THLPSSC also recommended that tank farm 
    piping be excepted from compliance with this rule.
        RSPA agrees that because of piping configuration constraints 
    associated with the storage facilities for gas, hazardous liquids and 
    carbon dioxide it is generally impracticable for design and 
    construction to accommodate passage of smart pigs. Therefore, 
    Sec. 192.150(b)(3) of the rule excepts piping associated with gas 
    storage facilities, other than a continuous run of transmission line 
    between a compression station and storage facilities, and 
    Sec. 195.120(b)(2) excepts piping associated with liquid storage 
    facilities. Nonetheless, RSPA will be studying underground storage 
    issues and, based on that work, may initiate rulemaking to address new 
    safety measures that may be necessary.
    
    Emergencies and Unforeseen Construction Problems
    
        The NPRM proposed to exclude from the rule piping that the 
    Administrator finds, upon petition by an operator, to be impracticable 
    to design and construct to accommodate the passage of smart pigs. 
    Eighteen commenters stated that many construction situations are under 
    tight contractual or other time constraints that do not allow 
    sufficient time to obtain a finding by the Administrator. For example, 
    an operator may have to make immediate adjustments in the field because 
    of the discovery of obstructions or other unforeseen problems. Thus, 
    some commenters reasoned that while the Administrator would have at 
    least 90 days to decide whether to grant a petition, most pipeline 
    construction projects would not allow delays of a few days. A few 
    commenters suggested that the operators should be permitted to accept 
    the ``burden of proof'' when encountering an impracticability during 
    construction and so inform RSPA.
        Similarly, the TPSSC recommended that the test for impracticability 
    be left up to the operator instead of petitioning the Administrator for 
    a finding. The Committee suggested the wording ``and any other piping 
    that the operator determines and documents would be impracticable to 
    design and construct to accommodate the passage of an instrumented 
    internal inspection device'' be substituted for ``the Administrator 
    finds'' in the exception of Sec. 192.150(b) from the NPRM. Also, the 
    TPSSC recommended that ``emergency repairs'' be added to the list of 
    exceptions contained in Sec. 192.150(b).
        RSPA acknowledges that emergencies, construction time constraints, 
    and unforeseen pipeline construction problems would not allow operators 
    the time to petition for a finding of impracticability and wait for 
    RSPA's response. Therefore, RSPA has added Secs. 192.150(c) and 
    195.120(c) which permit an operator discovering an emergency, 
    construction time constraint or other unforeseeable construction 
    problem to make a provisional determination of impracticability. In 
    such instances the operator must document the circumstances resulting 
    in its impracticability determination. Within 30 days after discovering 
    an emergency or a construction problem, the operator must petition 
    under the new Sec. 190.9, ``Petitions for finding or approval'' for a 
    finding by the Administrator that design and construction to 
    accommodate passage of internal inspection devices would be 
    impracticable. If the petition is denied, the operator must modify the 
    line section to allow passage of instrumented internal inspection 
    devices, within 1 year after the date of the notice of denial.
    
    Petitions for Finding or Approval
    
        The NPRM proposed that Sec. 190.9, ``Petitions for finding or 
    approval'' be added to part 190 of this Chapter. Except as discussed 
    above, commenters did not oppose the establishment of a procedure to 
    allow an operator to petition the Administrator for an administrative 
    ruling on any rule under parts 192, 193, and 195 in which the 
    Administrator is authorized to make a finding or approval. Heretofore, 
    a similar procedure in part 193 (Sec. 193.2015) applied only to 
    petitions relating to LNG facilities.
        In this rule, the Sec. 190.9 has been revised to require operators 
    of intrastate pipelines located in states, participating under section 
    5 of the NGPSA or section 205 of the HLPSA to direct their petitions to 
    the state pipeline safety agency. The participating state agency will 
    then make a recommendation to the Administrator as to the disposition 
    of the petition.
    
    Restraining Elements
    
        Nine commenters objected to the proposed requirement to add 
    restraining devices to all fittings providing branch line connections. 
    Restraining elements are added when the outlet to the branch line could 
    impede the passage of the smart pig. Many commenters argued that the 
    addition of restraining elements to these fittings may inhibit cleaning 
    of the branch lines by spheres or cleaning pigs. Other commenters 
    pointed out that the use of restraining elements in the main line is 
    unnecessary whenever the branch line has a significantly smaller 
    diameter than the main line.
        RSPA agrees that the rule should not require restraining elements 
    where they are unnecessary or make impracticable other functions that 
    are an essential and routine part of pipeline operations and 
    maintenance. So, the rule does not include a requirement for installing 
    restraining elements, but leaves their installation to the discretion 
    of the operator.
    
    Offshore Pipelines
    
        Eleven commenters recommended that the rule except offshore 
    pipelines. Several commenters based their recommendations on the fact 
    that offshore pipeline networks are tied-in by ``hot-tapped'' or tee 
    connections and these tie-ins are without restraining elements. This 
    type of construction permits cleaning pigs or spheres, required for 
    removal of materials (such as liquids from gas lines and wax from oil 
    lines) that impede normal flow, to pass into laterals of ever 
    increasing diameters.
        The system design is contingent on the passage of these cleaning 
    devices through the various laterals for final tie-in to the liquid 
    trunk (main) lines and to the gas transmission lines. Then, these 
    larger diameter lines transport the cleaning pigs to onshore 
    facilities, for eventual retrieval.
        An operator of offshore gas systems said that because of the many 
    subsea tie-ins to pipelines of larger diameter, smart pigs will require 
    some type of elaborate receiving device or physically disconnecting/
    lifting the pipeline; either of which would be very expensive. Other 
    commenters advised that smart pigs cannot be launched or received 
    subsea. An offshore operator said that new offshore platforms typically 
    connect new platforms to an existing subsea network. Connections to an 
    existing subsea pipeline are ``hot-tapped'' or are extensions to 
    existing laterals. This operator summed up his recommendations by 
    saying that it is impractical to design for the passage of smart pigs 
    through these connections and it is certainly impractical to install 
    subsea traps.
        Commenters also stated that because of space limitations on the 
    offshore platforms, the pipelines (risers) which have been routed up 
    onto the platforms have been designed and constructed with short radius 
    bends and other fittings that are only adequate for the launching of 
    cleaning pigs or spheres. These commenters argue that the construction 
    of the risers with long-sweeping bends on the sea floor and on the 
    platform, and the installation of the longer launchers and receivers 
    required to accommodate smart pigs, would be impracticable. For many of 
    the same reasons, both the TPSSC and the THLPSSC recommended that 
    offshore pipelines be excepted from the rule.
        RSPA acknowledges that many subsea pipelines have been designed and 
    constructed without restraining bars on branch line connections, 
    because they would prohibit the passage of cleaning pigs and spheres. 
    This design allows cleaning pigs and spheres to pass through the 
    network of subsea laterals and ultimately into larger transmission or 
    trunk (main) lines that transport gas or liquids to shore facilities.
        It is also apparent to RSPA, that designers of offshore platforms 
    seldom anticipated the space required to accommodate facilities 
    necessary for the operation of smart pigs. Moreover, RSPA accepts that 
    smart pigs cannot be launched or received subsea. However, RSPA does 
    not agree with the commenters or the two advisory committees that all 
    gas and liquid offshore pipelines should be fully excepted from this 
    rule.
        For pipelines subject to part 195, the current Sec. 195.120 
    requires that each component of a main line system, other than 
    manifolds, that change direction within the pipeline system must have a 
    radius of turn that readily allows the passage of pipeline scrapers, 
    spheres, and internal inspection equipment. This requirement for main 
    line components to readily allow the passage of smart pigs through 
    changes of direction has been in effect since 1970, when offshore 
    liquid lines became subject to part 195.
        Part 192 has applied to offshore gas lines since 1971. In 
    accordance with the requirements of section 108(b) of the 
    Reauthorization Act, RSPA sees the need for certain new and replacement 
    offshore gas transmission lines and risers from these lines to be 
    designed and constructed to allow passage of smart pigs.
        Accordingly, in Secs. 192.150(b)(7) and 195.120(b)(6), while the 
    rule has not excepted all offshore lines and related facilities, it has 
    excepted offshore lines which are not gas transmission lines or liquid 
    main lines 10 inches or greater in nominal diameter that transport 
    these commodities to onshore facilities. RSPA limited the accommodation 
    of smart pigs to these larger gas transmission and liquid main lines 
    because we find, for the reasons expressed by the commenters, that the 
    unique design and construction of the excepted offshore pipeline 
    systems makes them generally impracticable for the passage of smart 
    pigs.
        When the rulemaking mandated by the PLSA of 1992 discussed under 
    the heading--Future Rulemaking Involving Smart Pigs--is issued, RSPA 
    may prescribe the circumstances for inspection with smart pigs. Such 
    circumstances, if included in any final rule, may require the need for 
    offshore platforms that contain risers, to also accommodate launchers 
    and (where appropriate) receivers for the passage of smart pigs.
    
    Above Ground Pipelines
    
        Three commenters recommended that RSPA except above ground 
    pipelines because operators can inspect these pipelines visually.
        RSPA finds that regardless of whether an operator can visually 
    inspect a line above ground is irrelevant to the practicability of 
    design and construction of pipelines to accommodate passage of smart 
    pigs. Furthermore, smart pigs are capable of detecting internal defects 
    that cannot be discovered by a visual inspection of the outside surface 
    of a pipeline. Moreover, above ground pipelines are required to be 
    externally coated and coating materials usually preclude visual 
    inspection of the outside surface. So, this recommendation was not 
    adopted.
    
    Clarification of the Term ``Replacement''
    
        Thirteen commenters recommended that the terms ``replacement 
    transmission line'' and ``replacement pipeline'' be clarified to 
    indicate the portion of an existing line that must be modified to 
    accommodate smart pigs when replacements are made for other reasons.
        A gas pipeline operator recommended that the meaning of the term 
    ``replacement transmission line'' be limited to the pipe and components 
    such as valves, bends, and fittings which are added to or replaced in 
    an existing transmission line. Another gas pipeline operator expressed 
    support for regulations stating that replacement pipeline facilities 
    could not be constructed which would further restrict the passage of a 
    smart pig. RSPA cannot accept the first commenter's recommendations 
    because if ``replacement'' is limited to a replaced valve, a joint of 
    pipe, or other component, then pipelines with restrictive components, 
    such as elbows and tight radius field bends (which when properly 
    maintained never need replacement) would never be piggable. Also RSPA 
    cannot accept the second commenter's position because it appears to 
    mean that the operator need only to make the replacement no more 
    restrictive than it was prior to it being replaced. The clear intent of 
    the congressional mandate is to improve an existing pipeline's 
    piggability.
        A pipeline operator and a pipeline related association, recommended 
    that the word ``pipeline'' be replaced with ``line section'' defined in 
    Sec. 195.2. A gas pipeline association urged that ``replacement 
    transmission line'' be changed to ``replacement transmission section'' 
    to clearly indicate that only the portion of line replaced must 
    accommodate the passage of smart pigs. Another pipeline related 
    association interpreted ``replacement'' to mean either: (1) Replacement 
    of the entire line, or (2) replacement of the line segment between two 
    logical points (e.g. compressor stations). A gas pipeline operator also 
    believed the term ``segment'' is appropriate because it is frequently 
    used in part 192 and it recognizes that pipelines are segmented for 
    different regulatory purposes. A gas transmission operator felt that 
    the definition of ``replacement line'' should exempt the replacement of 
    partial segments of existing gas pipelines within a valve section that 
    are replaced because of class change or regular maintenance work 
    because of construction restraints. A gas distribution operator stated 
    that if the proposal was intended to apply to the replaced or relocated 
    section only, then that limitation should be in the final rule.
        The Congressional mandate requires the gradual elimination of 
    restrictions in existing gas transmission lines and existing hazardous 
    liquid and carbon dioxide lines in a manner that will eventually make 
    the lines piggable. Operators are only required to remove the 
    restrictions when replacements are made on the pipeline. On those 
    occasions, the economic burden of the upgrading is reduced because 
    crews and equipment will be on the site and that portion of the 
    pipeline will need to be out of service. Six of the commenters appear 
    to have considered the favorable economics when they recommended that 
    the upgrading for piggability cover the ``line segment'' or ``line 
    section''. While ``line segment'' is frequently used in the gas 
    regulations it is not defined, although it's used similarly to ``line 
    section'' (one commenter suggested it was the distance between two 
    logical points e.g. compressor stations).
        Therefore, in consideration of the comments ``line section'' is 
    used in place of the term ``replacement transmission line'' in part 
    192, and ``line section'' is used in place of the term ``replacement 
    pipeline'' in part 195, as those terms are used in the NPRM. ``Line 
    section,'' as added to part 192 is similar to ``line section'' as it is 
    defined in Sec. 195.2.
        In part 195, ``line section'' is currently defined in Sec. 195.2 to 
    mean a continuous run of pipe between adjacent pressure pump stations, 
    between a pressure pump station and terminal or breakout tanks, between 
    a pressure pump station and a block valve, or between adjacent block 
    valves. Now, in part 192 ``line section'' is defined in Sec. 192.3 to 
    mean a continuous run of transmission line between adjacent compressor 
    stations, between a compressor station and storage facilities, between 
    a compressor station and a block valve, or between adjacent block 
    valves.
        Accordingly, Secs. 192.150(a) and 195.120(a) have been revised to 
    clarify that when a replacement is made of line pipe, line valve, line 
    fitting, or other line component in an existing pipeline, covered by 
    this rule, the complete line section must be made to accommodate smart 
    pigs.
        Also, RSPA has modified the final rule in response to the comment 
    from the gas transmission operator that felt replacements of certain 
    partial segments within an existing valve section that are replaced 
    because of MAOP class change or regular maintenance work requirements, 
    should be excepted because of construction constraints. Although, the 
    construction restraints were not specified, RSPA has addressed 
    construction type problems with the procedure set out in 
    Secs. 192.150(c) and 195.120(c).
    
    Launchers and Receivers
    
        Several commenters agreed with statements in the NPRM that 
    installation of pig traps should not be required by this rulemaking, 
    but should be left to the discretion of pipeline operators. Also, a 
    commenter agreed with the statement in the NPRM that operators should 
    determine where pig traps are to be permanently located based on 
    individual operating circumstances. A gas pipeline operator said that 
    in a practical sense, it would be more cost effective to add launchers 
    and receivers at the time of construction rather than after the 
    transmission line is in service (which could again require the line to 
    be taken out of service). The National Transportation Safety Board 
    urged RSPA to revise its proposal so that facilities for entering and 
    removing smart pigs are required on all pipelines capable of being 
    traversed by such equipment. However, RSPA believes that revising the 
    NPRM for this purpose would delay the regulatory effect of this 
    rulemaking and the requirement may be included in a future rulemaking.
        In the final rule, as in the NPRM, RSPA has not included 
    requirements for launchers or receivers. However, when the rulemaking 
    mandated by the PLSA of 1992 is issued, RSPA may prescribe the 
    circumstances for inspection with smart pigs. Such circumstances, if 
    included in any final rule, may require facilities for launching or 
    receiving smart pigs. In the meantime, RSPA urges pipeline operators to 
    consider the economic advantages of voluntarily installing facilities, 
    at the time of construction or replacement of pipelines, for launching 
    and receiving smart pigs.
    
    Exemption of Gathering Lines
    
        Several commenters urged clarification of the exception for gas 
    gathering lines in the proposed Sec. 192.9.
        In light of the comments, RSPA agrees that clarification is needed. 
    Therefore, the exception, of the new Sec. 192.150, has been retained 
    and the current exception, as provided in Sec. 192.1, has been 
    referenced in the revised Sec. 192.9.
        Moreover, in Secs. 192.150(b)(7) and 195.120(b)(6), RSPA has 
    excepted offshore pipelines other than gas transmission or liquid main 
    lines, 10 inches or larger, that transport gas or liquids to onshore 
    facilities. Liquid gathering lines, which are defined in Sec. 195.2, 
    are included in this exception.
    
    Economic Impact
    
        Nineteen commenters discussed the economic impact and the majority 
    found fault with RSPA's assessment that the rule would add minimally to 
    the average expense of pipeline design and construction.
        As a result of information presented by the commenters, RSPA has 
    excepted various categories of pipelines from the final rule. These 
    exceptions are: Piping associated with storage facilities, other than 
    gas transmission lines; piping sizes for which a smart pig is not 
    commercially available; gas transmission lines, operated in conjunction 
    with a distribution system, which are installed in Class 4 locations; 
    and offshore pipelines other than certain gas transmission and liquid 
    main lines. Additionally, operators are permitted to make a provisional 
    determination of impracticability in instances of emergencies, 
    construction time constraints or other unforeseeable construction 
    problems that require immediate action. Other less urgent problems can 
    be handled through the newly established procedure in Sec. 190.9, 
    ``Petitions for finding or approval.''
        Accordingly, these exceptions together with others carried forward 
    from the NPRM substantially reduce the cost of compliance with the 
    rule. RSPA finds that the compliance costs will be minimal. A 
    Regulatory Evaluation has been prepared and is available in the Docket.
    
    Regulatory Notices and Analyses
    
    Executive Order 12866 and DOT Regulatory Policies and Procedures
    
        This final rule is not considered a significant regulatory action 
    under 3(f) of Executive Order 12866 and, therefore, is not subject to 
    review by the Office of Management and Budget. The rule is not 
    considered significant under the regulatory policies and procedures of 
    the Department of Transportation (44 FR 11034; February 26, 1979).
        RSPA believes that the rule will add minimally to the average 
    expense of pipeline design and construction. The information RSPA has 
    collected for the study under section 304 of the Reauthorization Act 
    shows that about 90 percent of hazardous liquid pipelines and 60 
    percent of gas transmission lines have been constructed to accommodate 
    the passage of smart pigs. This information confirms RSPA's field 
    experience that most operators are now constructing new and replacement 
    gas transmission lines and hazardous liquid pipelines to accommodate 
    smart pigs.
        RSPA lacks detailed information about carbon dioxide pipelines 
    which recently became subject to part 195. However, there are only 
    about 10 such pipeline systems and we understand that they are not 
    expected to grow in mileage or to require a significant amount of 
    replacement in the near term. Thus, those pipelines should not be 
    greatly affected by the revision of Sec. 195.120.
    
    Federalism Assessment
    
        This final rule will not have substantial direct effects on the 
    states, on the relationship between the Federal Government and the 
    states, or on the distribution of power and responsibilities among the 
    various levels of government. Therefore, in accordance with Executive 
    Order 12612 (52 FR 41685; October 30, 1987), RSPA has determined that 
    this final rule does not have sufficient federalism implications to 
    warrant preparation of a Federalism Assessment.
    
    Regulatory Flexibility Act
    
        There are very few small entities that operate pipelines affected 
    by this rulemaking. To the extent that any small entity is affected, 
    the regulatory evaluation accompanying this rule shows that the costs 
    are minimal. Based on these facts, I certify that under section 605 of 
    the Regulatory Flexibility Act that this final regulation does not have 
    a significant impact on a substantial number of small entities.
    
    List of Subjects
    
    49 CFR Part 190
    
        Administrative practice and procedure, Penalties, Pipeline safety.
    
    49 CFR Part 192
    
        Pipeline safety, Reporting and recordkeeping requirements.
    
    49 CFR Part 193
    
        Fire prevention, Pipeline safety, Reporting and recordkeeping 
    requirements, Security measures.
    
    49 CFR Part 195
    
        Anhydrous Ammonia, Carbon dioxide, Petroleum, Pipeline safety, 
    Reporting and recordkeeping requirements, Security measures.
        In consideration of the foregoing, RSPA amends 49 CFR parts 190, 
    192, 193, and 195 as follows:
    
    PART 190--[AMENDED]
    
        1. The authority citation for part 190 continues to read as 
    follows:
    
        Authority: 49 App. U.S.C. 1672, 1677, 1679a, 1679b, 1680, 1681, 
    1804, 2002, 2006, 2007, 2008, 2009, and 2010; 49 CFR 1.53.
    
        2. Section 190.9 is added to read as follows:
    
    
    Sec. 190.9  Petitions for finding or approval.
    
        (a) In circumstances where a rule contained in parts 192, 193 and 
    195 of this chapter authorizes the Administrator to make a finding or 
    approval, an operator may petition the Administrator for such a finding 
    or approval.
        (b) Each petition must refer to the rule authorizing the action 
    sought and contain information or arguments that justify the action. 
    Unless otherwise specified, no public proceeding is held on a petition 
    before it is granted or denied. After a petition is received, the 
    Administrator or participating state agency notifies the petitioner of 
    the disposition of the petition or, if the request requires more 
    extensive consideration or additional information or comments are 
    requested and delay is expected, of the date by which action will be 
    taken.
        (1) For operators seeking a finding or approval involving 
    intrastate pipeline transportation, petitions must be sent to: (i) The 
    state agency certified to participate under section 5 of the NGPSA (49 
    U.S.C. 1674) or section 205 of the HLPSA (49 App. U.S.C. 2004); or
        (ii) Where there is no state agency certified to participate, the 
    Administrator, Research and Special Programs Administration, 400 7th 
    Street SW., Washington, DC 20590.
        (2) For operators seeking a finding or approval involving 
    interstate pipeline transportation, petitions must be sent to the 
    Administrator, Research and Special Programs Administration, 400 7th 
    Street SW., Washington, DC 20590.
        (c) All petitions must be received at least 90 days prior to the 
    date by which the operator requests the finding or approval to be made.
        (d) The Administrator will make all findings or approvals of 
    petitions initiated under this section. A participating state agency 
    receiving petitions initiated under this section shall provide the 
    Administrator a written recommendation as to the disposition of any 
    petition received by them. Where the Administrator does not reverse or 
    modify a recommendation made by a state agency within 10 business days 
    of its receipt, the recommended disposition shall constitute the 
    Administrator's decision on the petition.
    
     
    PART 192--[AMENDED]
    
        3. The authority citation for part 192 continues to read as 
    follows:
    
        Authority: 49 App. U.S.C. 1672 and 1804; 49 CFR 1.53.
    
        4. In Sec. 192.3, the definition of Secretary is removed, and 
    definitions of Administrator and Line section are added to read as 
    follows:
    
    
    Sec. 192.3  Definitions
    
        Administrator means the Administrator of the Research and Special 
    Programs Administration or any person to whom authority in the matter 
    concerned has been delegated by the Secretary of Transportation.
    * * * * *
        Line section means a continuous run of transmission line between 
    adjacent compressor stations, between a compressor station and storage 
    facilities, between a compressor station and a block valve, or between 
    adjacent block valves.
    * * * * *
        5. Section 192.9 is revised to read as follows:
    
    
    Sec. 192.9  Gathering lines.
    
        Except as provided in Secs. 192.1 and 192.150, each operator of a 
    gathering line must comply with the requirements of this part 
    applicable to transmission lines.
        6. Section 192.150 is added to read as follows:
    
    
    Sec. 192.150  Passage of internal inspection devices.
    
        (a) Except as provided in paragraphs (b) and (c) of this section, 
    each new transmission line and each line section of a transmission line 
    where the line pipe, valve, fitting, or other line component is 
    replaced must be designed and constructed to accommodate the passage of 
    instrumented internal inspection devices.
        (b) This section does not apply to: (1) Manifolds;
        (2) Station piping such as at compressor stations, meter stations, 
    or regulator stations;
        (3) Piping associated with storage facilities, other than a 
    continuous run of transmission line between a compressor station and 
    storage facilities;
        (4) Cross-overs;
        (5) Sizes of pipe for which an instrumented internal inspection 
    device is not commercially available;
        (6) Transmission lines, operated in conjunction with a distribution 
    system which are installed in Class 4 locations;
        (7) Offshore pipelines, other than transmission lines 10 inches or 
    greater in nominal diameter, that transport gas to onshore facilities; 
    and
        (8) Other piping that, under Sec. 190.9 of this chapter, the 
    Administrator finds in a particular case would be impracticable to 
    design and construct to accommodate the passage of instrumented 
    internal inspection devices.
        (c) An operator encountering emergencies, construction time 
    constraints or other unforeseen construction problems need not 
    construct a new or replacement segment of a transmission line to meet 
    paragraph (a) of this section, if the operator determines and documents 
    why an impracticability prohibits compliance with paragraph (a) of this 
    section. Within 30 days after discovering the emergency or construction 
    problem the operator must petition, under Sec. 190.9 of this chapter, 
    for approval that design and construction to accommodate passage of 
    instrumented internal inspection devices would be impracticable. If the 
    petition is denied, within 1 year after the date of the notice of the 
    denial, the operator must modify that segment to allow passage of 
    instrumented internal inspection devices.
    
    PART 193--[AMENDED]
    
        7. The authority citation for part 193 continues to read as 
    follows:
    
        Authority: 49 App. U.S.C. 1671 et seq.; and 49 CFR 1.53.
    
    
    Sec. 193.2015  [Removed]
    
        8. Section 193.2015 is removed and reserved.
    
    PART 195--[AMENDED]
    
        9. The authority citation for part 195 is revised to read as 
    follows:
    
        Authority: 49 App. U.S.C. 2002 and 2015; 49 CFR 1.53.
    
        10. In Sec. 195.2, the definition of Secretary is removed, and the 
    definition of Administrator is added to read as follows:
    
    
    Sec. 195.2  Definitions.
    
        Administrator means the Administrator of the Research and Special 
    Programs Administration or any person to whom authority in the matter 
    concerned has been delegated by the Secretary of Transportation.
    * * * * *
    
    
    Secs. 195.8, 195.56, 195.58, 195.106, 195.260  [Amended]
    
        11. In Secs. 195.8, 195.56(a), 195.58, 195.106(e), and 195.260(e), 
    the term ``Secretary'' is removed and the term ``Administrator'' is 
    added in its place.
        12. Section 195.120 is revised to read as follows:
    
    
    Sec. 195.120  Passage of internal inspection devices.
    
        (a) Except as provided in paragraphs (b) and (c) of this section, 
    each new pipeline and each line section of a pipeline where the line 
    pipe, valve, fitting or other line component is replaced; must be 
    designed and constructed to accommodate the passage of instrumented 
    internal inspection devices.
        (b) This section does not apply to:
        (1) Manifolds;
        (2) Station piping such as at pump stations, meter stations, or 
    pressure reducing stations;
        (3) Piping associated with tank farms and other storage facilities;
        (4) Cross-overs;
        (5) Sizes of pipe for which an instrumented internal inspection 
    device is not commercially available;
        (6) Offshore pipelines, other than main lines 10 inches or greater 
    in nominal diameter, that transport liquids to onshore facilities; and
        (7) Other piping that the Administrator under Sec. 190.9 of this 
    chapter, finds in a particular case would be impracticable to design 
    and construct to accommodate the passage of instrumented internal 
    inspection devices.
        (c) An operator encountering emergencies, construction time 
    constraints and other unforeseen construction problems need not 
    construct a new or replacement segment of a pipeline to meet paragraph 
    (a) of this section, if the operator determines and documents why an 
    impracticability prohibits compliance with paragraph (a) of this 
    section. Within 30 days after discovering the emergency or construction 
    problem the operator must petition, under Sec. 190.9 of this chapter, 
    for approval that design and construction to accommodate passage of 
    instrumented internal inspection devices would be impracticable. If the 
    petition is denied, within 1 year after the date of the notice of the 
    denial, the operator must modify that segment to allow passage of 
    instrumented internal inspection devices.
    
        Issued in Washington, DC on April 6, 1994.
    Ana Sol Gutierrez,
    Acting Administrator, Research and Special Programs Administration.
    [FR Doc. 94-8622 Filed 4-11-94; 8:45 am]
    BILLING CODE 4910-60-P
    
    
    

Document Information

Effective Date:
5/12/1994
Published:
04/12/1994
Department:
Research and Special Programs Administration
Entry Type:
Rule
Action:
Final rule.
Document Number:
94-8622
Dates:
The effective date of this final rule is May 12, 1994.
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: April 12, 1994, Docket No. PS-126, Amdts. 190-5, 192-72, 193-9, 195-50, FR Doc. 94-8622 Filed 4-11-94, 8:45 am
RINs:
2137-AB71: Pipeline Safety: Passage of Internal Inspection Devices
RIN Links:
https://www.federalregister.gov/regulations/2137-AB71/pipeline-safety-passage-of-internal-inspection-devices
CFR: (10)
49 CFR 192.150(b)(3)
49 CFR 195.120(b)(2)
49 CFR 190.9
49 CFR 192.3
49 CFR 192.9
More ...