05-7268. Federal Acquisition Regulation; Submission for OMB Review; Schedules for Construction Contracts  

  • Start Preamble

    AGENCIES:

    Department of Defense (DOD), General Services Administration (GSA), and National Aeronautics and Space Administration (NASA).

    ACTION:

    Notice of request for an extension to an existing OMB clearance.

    SUMMARY:

    Under the provisions of the Paperwork Reduction Act of 1995 (44 U.S.C. Chapter 35), the Federal Acquisition Regulation (FAR) Secretariat will be submitting to the Office of Management and Budget (OMB) a request to review and approve an extension of a currently approved information collection requirement concerning schedules for construction contracts. A request for public comments was published in the Federal Register at 70 FR 4821, January 31, 2005. No comments were received.

    Public comments are particularly invited on: Whether this collection of information is necessary for the proper performance of functions of the FAR, and whether it will have practical utility; whether our estimate of the public burden of this collection of information is accurate, and based on valid assumptions and methodology; ways to enhance the quality, utility, and clarity of the information to be collected; and ways in which we can minimize the burden of the collection of information on those who are to respond, through the use of appropriate technological collection techniques or other forms of information technology.

    DATES:

    Submit comments on or before May 12, 2005.

    ADDRESSES:

    Submit comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden to the General Services Administration, FAR Secretariat (VIR), 1800 F Street, NW, Room 4035, Washington, DC 20405. Please cite OMB Control No.

    9000-0058, schedules for construction contracts, in all correspondence.Start Further Info

    FOR FURTHER INFORMATION CONTACT

    Cecelia Davis, Contract Policy Division, GSA (202) 219-0202.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    A. Purpose

    Federal construction contractors may be required to submit schedules, in the form of a progress chart, showing the order in which the contractor proposes to perform the work. Actual progress shall be entered on the chart as directed by the contracting officer. This information is used to monitor progress under a Federal construction contract when other management approaches for ensuring adequate progress are not used.

    B. Annual Reporting Burden

    Respondents: 2,600.

    Responses Per Respondent: 2.

    Annual Responses: 5,200.

    Hours Per Response: 1.

    Total Burden Hours: 5,200.

    Obtaining Copies of Proposals: Requesters may obtain a copy of the information collection documents from the General Services Administration, FAR Secretariat (VIR), Room 4035, 1800 F Street, NW, Washington, DC 20405, telephone (202) 501-4755. Please cite OMB Control No. 9000-0058, Schedules for Construction Contracts, in all correspondence.

    Start Signature

    Dated: April 1, 2005

    Rodney P. Lantier,

    Director, Contract Policy Division

    End Signature End Supplemental Information

    [FR Doc. 05-7268 Filed 4-11-05; 8:45 am]

    BILLING CODE 6820-EP-S

Document Information

Published:
04/12/2005
Department:
National Aeronautics and Space Administration
Entry Type:
Notice
Action:
Notice of request for an extension to an existing OMB clearance.
Document Number:
05-7268
Dates:
Submit comments on or before May 12, 2005.
Pages:
19062-19062 (1 pages)
Docket Numbers:
OMB Control No. 9000-0058
PDF File:
05-7268.pdf