97-9661. Tennessee Valley Authority; Watts Bar Nuclear Plant, Unit 1; Environmental Assessment and Finding of No Significant Impact  

  • [Federal Register Volume 62, Number 72 (Tuesday, April 15, 1997)]
    [Notices]
    [Pages 18371-18373]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-9661]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-390]
    
    
    Tennessee Valley Authority; Watts Bar Nuclear Plant, Unit 1; 
    Environmental Assessment and Finding of No Significant Impact
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an amendment to Facility Operating License No. 
    NPF-90, issued to Tennessee Valley Authority, (the licensee), for 
    operation of the Watts Bar Nuclear Plant, Unit 1, located in Rhea 
    County, Tennessee.
    
    Environmental Assessment
    
    Identification of the Proposed Action
    
        The current spent fuel pool storage capacity at the Watts Bar 
    Nuclear Plant (WBN) is 1312 fuel assembly storage locations of which 
    484 are usable. The Tennessee Valley Authority (TVA) requested an 
    amendment to the WBN Unit 1 operating license that would increase the 
    storage capacity of the spent fuel pool to 1835 assemblies. The 
    proposal consists of replacing the existing racks with spent fuel 
    storage racks that were designed, manufactured, and used until 1995 in 
    the Sequoyah Nuclear Plant, increasing the maximum initial enrichment 
    of fuel to 5.0 weight percent (wt%) U-235, changing the spacing of 
    stored fuel assemblies; adding limiting condition for operation (LCO) 
    requirements for the combination of initial enrichment and burnup in an 
    acceptable burnup domain, and requiring the boron concentration to be 
    greater than or equal to 2000 parts per million (ppm) during fuel 
    movement. The submittal also proposed surveillance requirements to 
    verify the initial enrichment and burnup and require chemical analysis 
    to verify boron concentration. The proposed action is in accordance 
    with the licensee's application for amendment dated October 23, 1996, 
    as supplemented by letters dated December 11, 1996, January 31, 
    February 10 and 24, and March 11 and , 1997.
    
    The Need for the Proposed Action
    
        WBN is in its first operating cycle; therefore, the spent fuel pool 
    is dry and no fuel assemblies are stored in it. Under current 
    conditions, the spent fuel pool capacity will support three to four 
    cycles of operation before losing the capacity for a full core offload 
    (193 fuel assemblies). However, taking into account loading new fuel 
    into the pool and component shuffling during an outage, the ability to 
    accept a discharge of one full core off-load could be impacted as early 
    as the year 2000. There are no commercial independent spent fuel 
    storage facilities operating in the U.S., nor are there any domestic 
    reprocessing facilities; therefore, the projected loss of storage 
    capacity in the WBN pool would affect TVA's ability to operate WBN. The 
    proposed amendment is needed to ensure the capability of full core 
    offload is available for some time in the future.
    
    Alternatives to the Proposed Action
    
        The licensee considered several wet and dry storage alternatives to 
    the proposed action. The following wet storage alternatives were 
    considered by the licensee: reracking with new ultra high density 
    racks, rod consolidation, and transshipment (pool-to-pool). The 
    following dry storage alternatives were considered by the licensee: 
    metal casks, concrete casks, concrete vaults, and multi-purpose 
    canisters/overpacks. The licensee considered several factors when 
    evaluating the options: effects on plant systems and operations; 
    impacts on safety, including fuel handling; radiation exposure; 
    industry experience; subsequent actions for further increasing onsite 
    spent fuel storage capacity; flexibility for ultimate disposal of spent 
    fuel; and overall costs. Based on these considerations, the licensee 
    determined that reuse of the Sequoyah Nuclear Plant storage racks was 
    the most viable option.
        In 1975, the staff prepared a Generic Environmental Impact 
    Statement (GEIS) on spent fuel storage. The findings were documented in 
    NUREG-0575, ``Final Generic Environmental Impact Statement (FGEIS) on 
    Handling and Storage of Spent Light Water Power Reactor Fuel.'' The 
    storage of spent fuel, as discussed in the NUREG, is considered to be 
    an interim action, not a final solution to permanent disposal. The 
    methods of expanding spent fuel storage capacity considered in the 
    FGEIS identified negligible differences in the environmental impacts 
    and costs of the different alternatives, with the exception that 
    expansion of the spent fuel pool was less costly and did not involve 
    transportation issues. The FGEIS noted that since there are variations 
    in storage design and limitations caused by spent fuel already stored 
    in the pools, licensing reviews should be performed on a case-by-case 
    basis to resolve plant-specific concerns.
        The staff evaluated the licensee's list of alternatives as well as 
    other alternatives. The following alternatives were considered by the 
    staff:
    Shipment of Fuel to a Permanent Federal Fuel Storage/Disposal Facility
        Shipment of spent fuel to a high-level radioactive storage facility 
    is an alternative to increasing the onsite spent fuel storage capacity. 
    However, the U.S. Department of Energy's (DOE's) high-level radioactive 
    waste repository is not expected to begin receiving spent fuel until 
    approximately 2010, at the earliest. In October 1996, the 
    Administration did
    
    [[Page 18372]]
    
    commit DOE to begin storing wastes at a centralized location by January 
    31, 1998. However, no location has been identified and an interim 
    federal storage facility has yet to be identified in advance of a 
    decision on a permanent repository. Therefore, shipping spent fuel to 
    the DOE repository is not considered an alternative to increased onsite 
    spent fuel storage capacity at this time.
    Shipment of Fuel to a Reprocessing Facility
        Reprocessing of spent fuel from the WBN facility is not a viable 
    alternative since there are no operating commercial reprocessing 
    facilities in the United States. Therefore, spent fuel would have to be 
    shipped to an overseas facility for reprocessing. However, this 
    approach has never been used and it would require approval by the 
    Department of State as well as other entities. Additionally, the cost 
    of spent fuel reprocessing is not offset by the salvage value of the 
    residual uranium; reprocessing represents an added cost.
    Shipment of Fuel to Another Utility or Site for Storage
        The shipment of fuel to another utility for storage would provide 
    short-term relief from the storage problem at WBN. The Nuclear Waste 
    Policy Act and 10 CFR Part 53, however, clearly places the 
    responsibility for the interim storage of spent fuel with each owner or 
    operator of a nuclear plant. The shipment of fuel to another source is 
    not an acceptable alternative because of increased fuel handling risks 
    and additional occupational radiation exposure, as well as the fact 
    that no additional storage capacity would be created.
    Reduction of Spent Fuel Generation
        Improved usage of fuel and/or operation at a reduced power level 
    would decrease the amount of fuel being stored in the pool and thus 
    increase the amount of time before full core off-load capacity is lost. 
    With extended burnup of fuel assemblies, the fuel cycle would be 
    extended and fewer offloads would be necessary. The licensee is 
    planning on operating on an 18-month refueling cycle, and, as part of 
    this proposed amendment, the licensee plans on increasing its fuel 
    enrichment to 5 percent. Operating the plant at a reduced power level 
    would not make effective use of available resources, and would cause 
    unnecessary economic hardship on TVA and its customers. Therefore, 
    reducing the amount of spent fuel generated by increasing burnup 
    further or reducing power is not considered a practical alternative.
    Development of Onsite Independent Storage Facility
        An independent spent fuel storage installation (ISFSI) is licensed 
    under 10 CFR Part 72. It is a passive storage system which stores spent 
    fuel in dry casks on a concrete platform in a secured area. There are 
    no commercial ISFSIs operating in the United States. Although use of an 
    ISFSI provides many benefits, the site-specific development of an 
    independent dry fuel storage facility at WBN was deemed undesirable by 
    the licensee compared to the use of the already existing, licensed 
    spent fuel racks. Furthermore, construction of such a facility would 
    not use the existing expansion capacity of the existing pool, would not 
    use the existing spent fuel racks taken out of the Sequoyah plant, and 
    would have the potential to cause additional and different 
    environmental impacts due to activities related to construction and 
    operation. Development of a site-specific ISFSI at this time and in 
    rsponse to TVA's current needs would waste available resources.
    No Action Taken
        If no action were taken, the storage capacity could be lost as 
    early as 2000 and WBN would have to shut down. This alternative is 
    considered a waste of available resources and is not considered viable.
    
    Environmental Impacts of the Proposed Action:
    
    Radiological Impact
        The WBN has waste treatment systems designed to collect and process 
    waste that may contain radioactive material. The radioactive waste 
    treatment systems were evaluated in the Final Environmental Statement 
    (FES) and its supplement. The Spent Fuel Pool Cooling and Cleaning 
    System is designed to remove the decay heat generated by stored spent 
    fuel assemblies and to clarify and purify the water to permit 
    unrestricted access to the plant fuel storage area and maintain optical 
    clarity of the spent fuel pool water. It is not expected that there 
    will be an increase in the liquid release of radionuclides from the 
    plant as a result of the spent fuel pool expansion. Although the amount 
    of activity in the spent fuel pool cleanup system may increase due to 
    the increased number of spent fuel assemblies and the enrichment, after 
    processing by the liquid radioactive waste system, the amount of 
    activity released to the environment as a result of the proposed change 
    is expected to be negligible. The proposed amendment will not involve 
    any change in the radioactive waste treatment systems or flowrates 
    described in the FES and its supplement.
        Because the racks are being removed from the WBN plant before any 
    spent fuel has been stored in them, they are not contaminated and they 
    will not contribute to the volume of solid radioactive waste. 
    Additionally, the Sequoyah racks are being reused and are not 
    classified as solid radioactive waste at this time. No additional low 
    specific activity waste output is generated and less solid waste will 
    be generated due to the reuse of the spent fuel racks and removal of 
    the existing racks before they become contaminated.
        In addition to the spent fuel assemblies themselves, the only other 
    solid radioactive waste generated by the spent fuel pool is the spent 
    fuel pool polisher resin which is used for water clarity. These resins 
    are replaced approximately once per refueling cycle. No additional 
    resins are expected to be generated by the pool cleanup system; 
    therefore, no significant increase in the volume of solid radioactive 
    waste is expected with the proposed amendment.
        The proposed amendment is not expected to significantly affect the 
    doses to the workers in the fuel storage area. The licensee stated that 
    pressurized water reactor experience has shown that area radiation dose 
    rates are approximately 1-3 millirem/hour. Dose rates on the pool 
    bridge crane platform are approximately 4-5 mrem/hr. During refueling 
    operations, these rates may increase slightly. During the reracking 
    procedures, the occupational exposure to the workers will be much less 
    if the amendment is granted at this time rather than if the racks are 
    taken out in the future, after spent fuel is stored in them. No 
    increases are expected to the concentration of airborne radioactivity 
    as a result of expanded storage capacity.
        The environmental impacts on the uranium fuel cycle and 
    transportation resulting from the use of higher enrichment fuel and 
    extended irradiation were published in NUREG/CR-5009, ``Assessment of 
    the Use of Extended Burnup Fuels in Light Water Power Reactors,'' and 
    discussed in the staff Environmental Assessment and Finding of No 
    Significant Impact published in the Federal Register on February 29, 
    1988 (53 FR 6040). The staff concluded that no significant adverse 
    effects will be generated by increasing the burnup levels as long as 
    the maximum rod average burnup level of any fuel rod is no greater than 
    60 Gwd/MtU. The staff also stated that the environmental impacts 
    summarized in
    
    [[Page 18373]]
    
    Table S-3 and S-4 for a burnup level of 33 Gwd/MtU are conservative and 
    bound the corresponding impacts for burnup levels up to 60 Gwd/MtU and 
    uranium-235 enrichments up to 5 wt%.
        Based on the above, the staff concludes that there are no 
    significant radiological environmental impacts associated with the 
    proposal.
    Non-Radiological Impact
        The proposed amendment does not modify land use at the site; no new 
    facilities or laydown areas are needed to support the rerack or 
    operation after rerack; therefore, the proposal does not affect land 
    use or land with historical or archeological sites.
        As a result of the proposal, steady state pool bulk temperature 
    remains within the limits prescribed for the spent fuel pool to satisfy 
    pool structural strength constraints. The increased spent fuel 
    inventory results in a maximum bulk pool temperature increase of less 
    than 10  deg.F. This increase in temperature results in an increase in 
    pool water evaporation rate. The original analysis was performed 
    assuming two unit operation. The licensee reanalyzed the effects of the 
    increased temperature and evaporation rate and found the increases were 
    well within the capacity of the existing HVAC system and continued to 
    be bounded by the original analysis. The total heat load for the 
    unplanned emergency core off-load is less then 35 million BTU/hr, which 
    is less than one percent of the total plant heat loss.
        The proposal does not affect non-radiological plant effluents and 
    no changes to the National Pollution Discharge Elimination System 
    (NPDES) permit are needed. The proposal does not result in any 
    significant changes to land use or water use, or result in any 
    significant changes to the quantity or quality of effluents; no effects 
    on endangered or threatened species or on their habitat are expected.
        The proposal will not change the method of generating electricity 
    nor the method of handling any influent from the environment or non-
    radiological effluents to the environment. Therefore, no changes or 
    different types of non-radiological environmental impacts are expected 
    as a result of the amendment.
    
    Accident Considerations
    
        In its application, the licensee evaluated the possible 
    consequences of postulated accidents and described the means for 
    mitigating these consequences should they occur. This evaluation 
    included spent fuel handling accidents. A fuel handling accident may be 
    viewed as a reasonably foreseeable design basis event which the pool 
    and associated structure, systems, and components are designed and 
    constructed to prevent. On the basis of its analysis, the licensee 
    concluded that the effects of the proposed TS changes are small and 
    that the calculated consequences are within regulatory requirements and 
    staff guideline dose values.
        The staff evaluated the consequences of operation at a bounding 
    value of burnup (60,000 MWD/T) because of the licensee's reference to 
    the use of more highly enriched fuel (up to 5.0 weight percent U-235). 
    The staff concluded that the only potential increased radiological 
    consequences resulting from a fuel handling accident associated with 
    extended burnup and higher fuel enrichment are the thyroid doses; these 
    doses remain well within the acceptance criteria given in NUREG-0800 
    and are, therefore, acceptable. The environmental impacts of the 
    accident were found not to be significant.
        The staff has considered accidents whose consequences might exceed 
    a fuel handling accident that is beyond design basis events. The 
    licensee and staff, as part of the operating license review, performed 
    an analysis of installation of severe accident mitigation design 
    alternatives (SAMDAs) in the environmental impact review. The staff 
    concluded that none of the five design improvements warranted 
    implementation at WBN.
        The staff believes that the probability of severe structural damage 
    occurring at WBN is extremely low. This belief is based on the 
    Commission's requirements for the design and construction of the spent 
    fuel pool and the contents and on the licensee's adherence to approved 
    industry codes and standards. Therefore, the staff concludes that the 
    potential for environmental impact from severe accidents is negligible.
    
    Summary
    
        The Commission has completed its evaluation of the proposed action. 
    The change will not increase the probability or consequences of 
    accidents, no changes are being made in the types of any effluents that 
    may be released offsite, and there is no significant increase in the 
    allowable individual or cumulative occupational radiation exposure. 
    Accordingly, the Commission concludes that there are no significant 
    radiological environmental impacts associated with the proposed action.
        With regard to potential nonradiological impacts, the proposed 
    action does involve features located entirely within the restricted 
    area as defined in 10 CFR Part 20. It does not affect nonradiological 
    plant effluents and has no other environmental impact. Accordingly, the 
    Commission concludes that there are no significant nonradiological 
    environmental impacts associated with the proposed action.
    
    Alternative Use of Resources
    
        This action does not involve the use of any resources not 
    previously considered in the FES for WBN Units 1 and 2, dated April 
    1995.
    
    Agencies and Persons Consulted
    
        In accordance with its stated policy, on March 24, 1997 the staff 
    consulted with the Tennessee State official, Ms. E. Flanagan of the 
    Division of Radiological Health, regarding the environmental impact of 
    the proposed action. The State official had no comments.
    
    Findings of No Significant Impact
    
        The staff has reviewed the proposed spent fuel pool modification to 
    WBN Unit 1 relative to the requirements set forth in 10 CFR Part 51. 
    Based upon the environmental assessment, the staff has concluded that 
    there are no significant radiological or non-radiological impacts 
    associated with the proposed action and that the proposed license 
    amendment will not have a significant effect on the quality of the 
    human environment. Therefore, the Commission has determined, pursuant 
    to 10 CFR 51.31, not to prepare an environmental impact statement for 
    the proposed amendment.
        For further details with respect to the proposed action, see the 
    licensee's letter dated October 23, 1996, as supplemented by letters 
    dated December 11, 1996, January 31, February 10 and 24, March 11 and 
    April 4, 1997, which are available for public inspection at the 
    Commission's Public Document Room, The Gelman Building, 2120 L Street, 
    NW., Washington, DC, and at the local public document room located at 
    the Chattanooga-Hamilton County Library, 1001 Broad Street, 
    Chattanooga, Tennessee.
    
        Dated at Rockville, Maryland, this 7th day of April 1997.
    
        For The Nuclear Regulatory Commission.
    Frederick J. Hebdon,
    Director, Project Directorate II-3, Division of Reactor Projects--I/II, 
    Office of Nuclear Reactor Regulation.
    [FR Doc. 97-9661 Filed 4-14-97; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
04/15/1997
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
97-9661
Pages:
18371-18373 (3 pages)
Docket Numbers:
Docket No. 50-390
PDF File:
97-9661.pdf