        Take notice that on April 3, 1998, Texas Gas Transmission 
    Corporation (Applicant), 3800 Fredrica Street, Owensboro, Kentucky 
    42301, filed in Docket No. CP98-333-000 a request pursuant to Sections 
    157.205 and 157.211 of the Commission's Regulations under the Natural 
    Gas Act (18 CFR 157.205 and 157.211) for approval to construct and 
    operate a new delivery point for service to Linder Oil Company (Linder) 
    located in Iberia Parish, Louisiana, under Applicant's blanket 
    certificate issued in Docket No. CP82-407-000, pursuant to Section 7(c) 
    of the Natural Gas Act (NGA), all as more fully set forth in the 
    request which is on file with the Commission and open to public 
    inspection.
        Applicant proposes to modify an existing receipt point by 
    installing a two-inch delivery meter station in order to provide gas 
    lift gas service requested by Linder. Applicant states that this 
    existing receipt point is located on Applicant's East Bayou Pigeon Gulf 
    Eight-Inch Line in Iberia Parish, Louisiana. Applicant asserts that 
    Linder will fully reimburse Applicant for the cost of construction of 
    the aforementioned facilities, which Applicant estimates to be $27,470.
        Applicant indicates that Linder is requesting up to 100 MMBtu per 
    day of interruptible transportation service to be used as gas lift gas 
    for Linder's operations in the Northeast Bayou Pigeon Field. Applicant 
    asserts that this request will have no significant impact on 
    Applicant's peak day and annual deliveries and that service through 
    this point to Linder can be accomplished without detriment to 
    Applicant's other customers.
        Any person or the Commission's Staff may, within 45 days of the 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Rules of Practice and Procedure (18 CFR 
    385.214), a motion to intervene and pursuant to Section 157.205 of the 
    regulations under the Natural Gas Act (18 CFR 157.205), a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activities shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn 30 days after the time allowed for filing a protest, 
    the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 98-9891 Filed 4-14-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
04/15/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-9891
Pages:
18396-18396 (1 pages)
Docket Numbers:
Docket No. CP98-333-000
PDF File:
98-9891.pdf