E8-7952. Natural Gas Pipeline Company of America LLC; Notice of Application  

  • Start Preamble April 9, 2008.

    Take notice that on April 7, 2008, Natural Gas Pipeline Company of America LLC (Natural), 747 East 22nd Street, Lombard, Illinois 60148, filed an application pursuant to section 7(c) of the Natural Gas Act for a certificate of public convenience and necessity to construct and operate certain facilities, located in Cameron Parish, Louisiana, all as more fully set forth in the application which is on file with the Commission and open for public inspection. This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, contact (202) 502-8659.

    Specifically, Natural proposes to construct and operate approximately 900 feet of 16-inch diameter pipeline and operate an already constructed meter, consisting of ultrasonic meter runs, flow control valve, gas quality monitoring devices, and Electronic flow Measurement facilities. Natural states that the facilities are necessary to receive up to 300 MDth/day of re-vaporized liquefied natural gas from the Sabine Pass Segment of the Cheniere Creole Trail Pipeline (Cheniere), located in Cameron Parish, Louisiana. Natural estimates the cost of construction to be Start Printed Page 20280$4,892,350, and all costs borne by Natural will be reimbursed by Cheniere.

    Any questions regarding this Application should be directed to Bruce H. Newsome, Vice President, Regulatory, Natural Gas Pipeline Company of America, 747 East 22nd Street, Lombard, Illinois 60148-5072 or by telephone at (630) 691-3526 or e-mail at bruce_newsome@kindermorgan.com.

    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission's public record (eLibrary) for this proceeding, or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff's issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission's public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff's FEIS or EA.

    There are two ways to become involved in the Commission's review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the below listed comment date, file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding.

    However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission's rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest.

    Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission's environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission's environmental review process. Environmental commenters will not be required to serve copies of filed documents on all other parties. However, the non-party commenters will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission's final order.

    Motions to intervene, protests and comments may be filed electronically via the Internet in lieu of paper; see, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site under the “e-Filing” link. The Commission strongly encourages electronic filings.

    Comment Date: April 21, 2008.

    Start Signature

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    [FR Doc. E8-7952 Filed 4-14-08; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Effective Date:
4/21/2008
Published:
04/15/2008
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
E8-7952
Dates:
April 21, 2008.
Pages:
20279-20280 (2 pages)
Docket Numbers:
Docket No. CP08-114-000
EOCitation:
of 2008-04-09
PDF File:
e8-7952.pdf