98-10080. Central Maine Power Company, et al.; Electric Rate and Corporate Regulation Filings  

  • [Federal Register Volume 63, Number 73 (Thursday, April 16, 1998)]
    [Notices]
    [Pages 18904-18907]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-10080]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. EC98-36-000, et al.]
    
    
    Central Maine Power Company, et al.; Electric Rate and Corporate 
    Regulation Filings
    
    April 8, 1998.
        Take notice that the following filings have been made with the 
    Commission:
    
    1. Central Maine Power Company
    
    [Docket No. EC98-36-000]
    
        Take notice that on April 3, 1998, Central Maine Power Company 
    submitted an application pursuant to Section 203 of the Federal Power 
    Act, 16 U.S.C. 824b, and Part 33 of the Commission's Regulations, 18 
    CFR Part 33, for authority to effect a corporate reorganization 
    involving the formation of a holding company structure.
        Comment date: May 7, 1998, in accordance with Standard Paragraph E 
    at the end of this notice.
    
    2. Midwest Independent Transmission System Operator, Inc.
    
    [Docket No. ER98-1438-000]
    
        Take notice that on April 1, 1998, the Midwest Independent 
    Transmission System Operator, Inc. (Midwest ISO), tendered for filing 
    certain additional executed signature pages in order to supplement its 
    January 15, 1998, filing in Docket No. ER98-1438.
        Specifically, the Midwest ISO, for Ameren and Illinois Power 
    Company, tenders additional signature pages for the ``Agreement of the 
    Transmission Facilities Owners to Organize the Midwest Independent 
    Transmission System Operator, Inc., A Delaware Non-Stock Corporation,'' 
    and a signature page for Ameren for the ``Agency Agreement for Open 
    Access Transmission Service Offered by the Midwest ISO for Non-
    transferred Transmission Facilities.'' These signature pages are being 
    tendered to reflect the fact that these parties have executed the 
    aforementioned agreements.
        Comment date: April 22, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    3. PJM Interconnection, LLC
    
    [[Page 18905]]
    
    [Docket No. ER98-2293-000]
    
        Take notice that on March 24, 1998, the PJM Interconnection, L.L.C. 
    (PJM), filed on behalf of the Members of the LLC, membership 
    applications of NESI Power Marketing, Inc. PJM requests an effective 
    date on the day after this Notice of Filing is received by FERC.
        Comment date: April 21, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    4. Pacific Gas and Electric Company
    
    [Docket No. ER98-2351-000]
    
        Take notice that on March 30, 1998, Pacific Gas and Electric 
    Company (PG&E), tendered for filing revisions to its Transmission Owner 
    Tariff (TO Tariff), and Cost Support for PG&E specific rates associated 
    with the TO Tariff. PG&E requests that its filing be made effective 
    March 31, 1998, which is the projected date the Independent System 
    Operator (ISO) and Power Exchange (PX) are to begin operations.
        This filing proposes changes to PG&E's transmission access charges, 
    which are calculated in accordance with the rate methodology set forth 
    in PG&E's TO Tariff. Moreover, PG&E is providing cost support for 
    PG&E's proposed transmission access charges and PG&E is continuing to 
    request that the Commission establish the transmission revenue 
    requirement to be used in designating wholesale and retail transmission 
    access charges, but that it defer to the California Public Utilities 
    Commission (CPUC) on the allocation of costs among retail classes and 
    the design of retail access charges based on the allocated costs.
        In addition, PG&E is proposing changes to the non-rate terms and 
    conditions of its TO Tariff in order to: (a) be consistent with the 
    Tariff filed by the ISO; (b) comply with a Commission Order in Docket 
    EC96-19-001, et al.; and,  make other clarifications to the 
    TO Tariff.
        Copies of this filing have been served upon the CPUC and the ISO.
        Comment date: April 21, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    5. Boston Edison Company
    
    [Docket No. ER98-616-000]
    
        Take notice that on April 3, 1998, Sithe Energies, Inc. (Sithe), 
    tendered for filing with the Federal Energy Regulatory Commission 
    Amendment No. 1 to the Transition Agreement (Amendment), entered into 
    between Boston Edison Company and Sithe Energies, Inc., and filed with 
    the Commission on February 17, 1998, in the above-referenced docket. 
    Sithe states that the Amendment provides that Sithe Mystic LLC, Sithe 
    Edgar LLC, Sithe New Boston LLC, Sithe Framingham LLC, Sithe West 
    Medway LLC and Sithe Wyman LLC will be the sellers of electric 
    capacity, energy and ancillary services under the terms of the 
    Transition Agreement.
        Sithe requests that the tendered Amendment become effective on 
    April 30, 1998.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    6. Allegheny Power Service Corporation, on Behalf of Monongahela 
    Power Company, The Potomac Edison Company and West Penn Power 
    Company (Allegheny Power)
    
    [Docket No. ER98-1434-000 and Docket No. ER98-1466-000]
    
        Take notice that on April 3, 1998, Allegheny Power Service 
    Corporation on behalf of Monongahela Power Company, The Potomac Edison 
    Company and West Penn Power Company (Allegheny Power) submitted a 
    revised amendment to its Standard Generation Service Rate Schedule to 
    comply with the Commission directives in an order issued on March 12, 
    1998, in Docket No. ER98-1466-000 and ER98-1434-000.
        Copies of the filing have been provided to the Public Utilities 
    Commission of Ohio, the Pennsylvania Public Utility Commission, the 
    West Virginia Public Service Commission, and all parties of record.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    7. Minnesota Power & Light Company
    
    [Docket No. ER98-1504-000]
    
        Take notice that on April 3, 1998, Minnesota Power & Light Company 
    and Superior Water, Light & Power Company, as Transmission Provider, 
    submitted for filing an amended Transmission Tariff Service Agreement 
    with Minnesota Power & Light Company, as Transmission Customer, for a 
    point of delivery to the City of Hibbing, MN under its Transmission 
    Tariff Service Agreement.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    8. Energy Clearinghouse Corporation
    
    [Docket No. ER98-2020-000]
    
        Take notice that on March 30, 1998, Energy Clearinghouse 
    Corporation (ECC), petitioned the Commission for acceptance of ECC Rate 
    Schedule FERC No. 1; the granting of certain blanket approvals, 
    including the authority to sell electricity at market-based rates; and 
    the waiver of certain Commission Regulations.
        ECC intends to engage in wholesale electric power and energy 
    purchases and sales as a marketer as well as selling and marketing the 
    same at retail, aggregating and brokering. ECC is not in the business 
    of generating or transmitting electric power. ECC is wholly-owned by 
    Harold E. Scherz.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    9. MEG Marketing, LLC
    
    [Docket No. ER98-2284-000]
    
        Take notice that on March 24, 1998, MEG Marketing, LLC (MEG), 
    petitioned the Commission for acceptance of MEG Rate Schedule FERC No 
    1; the granting of certain blanket approvals, including the authority 
    to sell electricity and natural gas at market-based rates; and the 
    waiver of certain Commission Regulations.
        MEG intends to engage in wholesale electric power and energy 
    purchases and sales as marketer (brokering/trading). MEG is not in the 
    business of generating or transmitting electric power. MEG is a 
    privately-held company.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    10. Northeast Utilities Service Company
    
    [Docket No. ER98-2373-000]
    
        Take notice that on April 3, 1998, Northeast Utilities Service 
    Company (NUSCO), on behalf of The Connecticut Light and Power Company 
    (CL&P), submitted a replacement red-lined version of the Second 
    Amendment to Interruptible Power Supply Service Agreement, previously 
    filed pursuant to Section 205 of the Federal Power Act and Section 
    35.13 of the Commission's Regulations.
        NUSCO renews its request that the rate schedule become effective on 
    April 1, 1998. NUSCO states that copies of the replacement have been 
    mailed to the parties to the Agreement.
        Comment date: April 22, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    11. The Detroit Edison Company
    
    [Docket No. ER98-2412-000]
    
        Take notice that on April 3, 1998, The Detroit Edison Company 
    (Detroit Edison), tendered for filing a Service Agreement for wholesale 
    power sales transactions (the Service Agreement)
    
    [[Page 18906]]
    
    under Detroit Edison's Wholesale Power Sales Tariff (WPS-1), FERC 
    Electric Tariff No. 4 (the WPS-1 Tariff), between Detroit Edison and 
    USGen Power Services, L.P., dated as of March 30, 1998. Detroit Edison 
    requests that the Service Agreement be made effective as of March 30, 
    1998.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    12. Houston Lighting & Power Company
    
    [Docket No. ER98-2426-000]
    
        Take notice that on April 3, 1998, Houston Lighting & Power Company 
    (HL&P), submitted for filing a notice of cancellation of a transmission 
    service agreement with Duke/Louis Dreyfus, L.L.C., under HL&P's tariff 
    for transmission service to, from and over certain HVDC 
    Interconnections.
        HL&P states that a copy of the filing has been served on the 
    affected customer.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    13. Indianapolis Power & Light Company
    
    [Docket No. ER98-2427-000]
    
        Take notice that on April 3, 1998, Indianapolis Power & Light 
    Company (IPL), tendered for filing an interchange agreement, dated 
    April 2, 1998, between IPL and Southern Company Energy Marketing, L.P.
        Copies of this filing were served on Southern Company Energy 
    Marketing, the Indiana Utility Regulatory Commission and the Georgia 
    Public Service Commission.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    14. The Detroit Edison Company
    
    [Docket No. ER98-2428-000]
    
        Take notice that on April 3, 1998, The Detroit Edison Company 
    (Detroit Edison), tendered for filing Service Agreements for wholesale 
    power sales transactions (the Service Agreements) under Detroit 
    Edison's Wholesale Power Sales Tariff (WPS-2), FERC Electric Tariff No. 
    3 (the WPS-2 Tariff), between Detroit Edison and USGen Power Services, 
    L.P., dated as of March 30, 1998. Detroit Edison requests that the 
    Service Agreement be made effective as of March 30, 1998.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    15. Texas Utilities Electric Company
    
    [Docket No. ER98-2429-000]
    
        Take notice that on April 3, 1998, Texas Utilities Electric Company 
    (TU Electric), tendered for filing two executed transmission service 
    agreements (TSA's), with OGE Energy Resources, Inc., and American 
    Electric Power Service Corporation for certain Unplanned Service 
    transactions under TU Electric's Tariff for Transmission Service To, 
    From and Over Certain HVDC Interconnections.
        TU Electric requests an effective date for the TSA's that will 
    permit them to become effective on or before the service commencement 
    date under the TSA's. Accordingly, TU Electric seeks waiver of the 
    Commission's notice requirements. Copies of the filing were served on 
    OGE Energy Resources, Inc., and American Electric Power Service 
    Corporation as well as the Public Utility Commission of Texas.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    16. Florida Power & Light Company
    
    [Docket No. ER98-2433-000]
    
        Take notice that on April 3, 1998, Florida Power & Light Company 
    (FPL), tendered for filing proposed service agreements with Columbia 
    Power Marketing Corporation for Short-Term Firm and Non-Firm 
    transmission service under FPL's Open Access Transmission Tariff.
        FPL requests that the proposed service agreements be permitted to 
    become effective on May 1, 1998.
        FPL states that this filing is in accordance with Part 35 of the 
    Commission's Regulations.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    17. The Washington Water Power Company
    
    [Docket No. ER98-2434-000]
    
        Take notice that on April 3, 1998, The Washington Water Power 
    Company (WWP), tendered for filing with the Federal Energy Regulatory 
    Commission an executed Service Agreement for Long-Term Firm Point-To-
    Point Transmission Service with Avista Energy, Inc. WWP requests that 
    the Service Agreement be given an effective date of April 1, 1998.
        Copies of this filing have been provided to the Washington 
    Utilities and Transportation Commission and the Idaho Public Utilities 
    Commission.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    18. Wisconsin Public Service Corporation
    
    [Docket No. ER98-2435-000]
    
        Take notice that on April 3, 1998, Wisconsin Public Service 
    Corporation (WPSC), tendered for filing an executed Transmission 
    Service Agreement between WPSC and PacifiCorp Power Marketing, Inc., 
    provides for transmission service under the Open Access Transmission 
    Service Tariff, FERC Original Volume No. 11.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    19. Wisconsin Public Service Corporation
    
    [Docket No. ER98-2436-000]
    
        Take notice that on April 3, 1998, Wisconsin Public Service 
    Corporation (WPSC), tendered for filing an executed Transmission 
    Service Agreement between WPSC and CNG Power Services Corporation, 
    provides for transmission service under the Open Access Transmission 
    Service Tariff, FERC Original Volume No. 11.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    20. Florida Power Corporation
    
    [Docket No. ER98-2437-000]
    
        Take notice that on April 3, 1998, Florida Power Corporation 
    (Florida Power), tendered for filing a service agreement providing for 
    non-firm point-to-point transmission service to Southern Energy 
    Marketing Corp., Inc. (SEMC), pursuant to its open access transmission 
    tariff. Florida Power requests that the Commission waive its notice of 
    filing requirements and allow the agreement to become effective on 
    April 6, 1998.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    21. Union Electric Company
    
    [Docket No. ER98-2439-000]
    
        Take notice that on April 3, 1998, Union Electric Company (UE), 
    tendered for filing a Reactivated Appendix C, IP-UE Connection 11, 
    Second Revised Appendix C, IP-UE Connection 16 and Letter Agreement 
    dated January 26, 1998, to the Interconnection Agreement dated February 
    18, 1972, between Central Illinois Public Service Company, Illinois 
    Power (IP) and UE.
        Comment date: April 23, 1998, in accordance with Standard Paragraph 
    E at the end of this notice.
    
    [[Page 18907]]
    
    Standard Paragraph
    
        E. Any person desiring to be heard or to protest said filing should 
    file a motion to intervene or protest with the Federal Energy 
    Regulatory Commission, 888 First Street, N.E., Washington, D.C. 20426, 
    in accordance with Rules 211 and 214 of the Commission's Rules of 
    Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such 
    motions or protests should be filed on or before the comment date. 
    Protests will be considered by the Commission in determining the 
    appropriate action to be taken, but will not serve to make protestants 
    parties to the proceeding. Any person wishing to become a party must 
    file a motion to intervene. Copies of these filings are on file with 
    the Commission and are available for public inspection.
    David P. Boergers,
    Acting Secretary.
    [FR Doc. 98-10080 Filed 4-15-98; 8:45 am]
    BILLING CODE 6717-01-P
    
    
    

Document Information

Published:
04/16/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-10080
Dates:
May 7, 1998, in accordance with Standard Paragraph E at the end of this notice.
Pages:
18904-18907 (4 pages)
Docket Numbers:
Docket No. EC98-36-000, et al.
PDF File:
98-10080.pdf