[Federal Register Volume 63, Number 73 (Thursday, April 16, 1998)]
[Notices]
[Pages 18897-18898]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-10090]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP98-334-000]
Midwestern Gas Transmission Company; Notice of Request Under
Blanket Authorization
April 10, 1998.
Take notice that on April 6, 1998, Midwestern Gas Transmission
Company (Midwestern), Post Office Box 2511, Houston, Texas 77252, filed
in Docket No. CP98-334-000 a request pursuant to Sections 157.205,
157.212, and 157.216 of the Commission's Regulations under the Natural
Gas Act (18 CFR 157.205, 157.212, and 157.216) for authorization to
upgrade a delivery point for continued service to Western Kentucky Gas
Company (Western Kentucky), a local distribution company. Midwestern
makes such request under its blanket certificate issued in Docket No.
CP82-414-000 pursuant to Section 7 of the Natural Gas Act, all as more
fully set forth in the request on file with the Commission and open to
public inspection.
Midwestern request authorization to modify an existing delivery
point on its system in Daviess County, Kentucky in order to deliver
additional volumes at that delivery point to Western Kentucky.
Midwestern proposes to uprate its existing Meter Station No. 2-7068
located at Milepost 2106-1+3.88, in order to enable Midwestern to
deliver on an interruptible and firm basis up to 30 MMcf a day of
natural gas at that meter station.
Specifically, Midwestern is proposing to modify the existing meter
station by removing the existing 2-inch orifice meter and associated
piping, 2-inch flow control valve and associated bypass and isolation
valves, 3-inch check valve and approximately 45 feet of 3-inch diameter
interconnecting pipe. Midwestern states that it will install an 8-inch
orifice meter, 4-inch flow control valve and associated bypass and
isolation valves, 8-inch check value and approximately 45 feet of 8-
inch diameter interconnecting pipe. Additionally, Midwestern states
that it also proposes to reconfigure the
[[Page 18898]]
electronic gas measurement to accommodate the above described changes.
The current capacity at that meter station is 1.5 MMcf per day, and
Midwestern states that the proposed modifications are designed to
increase the capacity to 30 MMcf per day, without having a significant
impact on Midwestern's peak day or annual deliveries.
The overall cost of the project, including both the removal and the
installation of facilities will be approximately $197,900. It is stated
that Western Kentucky will fully reimburse Midwestern for this project.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 98-10090 Filed 4-15-98; 8:45 am]
BILLING CODE 6717-01-M