95-9373. In the Matter of: Long Island Power Authority (Shoreham Nuclear Power Station, Unit 1); Order Terminating the Facility Operating License  

  • [Federal Register Volume 60, Number 73 (Monday, April 17, 1995)]
    [Notices]
    [Pages 19309-19311]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-9373]
    
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket No. 50-322; License No. NPF-82]
    
    
    In the Matter of: Long Island Power Authority (Shoreham Nuclear 
    Power Station, Unit 1); Order Terminating the Facility Operating 
    License
    
    I
    
        Long Island Power Authority (LIPA or the licensee) is the holder of 
    Facility Operating License No. NPF-82, issued by the U.S. Nuclear 
    Regulatory Commission (NRC) pursuant to part 50 of Title 10 of the Code 
    of Federal Regulations (10 CFR) on April 21, 1989. The license was 
    amended on June 14, 1991, to remove the authority to operate the 
    Shoreham Nuclear Power Station (SNPS), in accordance with conditions 
    specified therein, and authorized the possession only for SNPS. The 
    facility is located on LIPA's site in the town of Brookhaven, Suffolk 
    County, New York.
    
    II
    
        On February 28, 1989, Long Island Lighting Company (LILCO), the 
    former licensee, entered into an agreement with the State of New York 
    to transfer its Shoreham assets to an entity of the State (LIPA) for 
    decommissioning. LILCO, however, continued to pursue with NRC its 
    request for a full-power license to operate its Shoreham plant. On 
    April 21, 1989, NRC issued to LILCO a Facility Operating License No. 
    NPF-82, which allowed full-power operation of the Shoreham plant. On 
    June 28, 1989, LILCO's shareholders ratified LILCO's agreement with the 
    State. Consistent with the terms of the settlement agreement, which 
    prohibits further operation of the Shoreham facility, 
    [[Page 19310]] LILCO defueled the reactor and reduced its staff. On 
    February 29, 1992, NRC approved the transfer of the Shoreham license to 
    LIPA.
        In a letter dated June 27, 1991 (SNRC-1818), the former licensee, 
    LILCO requested, in accordance with the requirement of 10 CFR 50.82(a), 
    approval for termination of SNPS License No. NPF-82. The application 
    for license termination was preceded by a proposed decommissioning plan 
    (DP) that was submitted to NRC on December 29, 1990.
        In June 1992, the NRC approved the licensee's DP, which described 
    the planned dismantlement and decontamination methods that would be 
    used to reduce contamination at the facility to meet the unrestricted 
    release criteria. By an agreement between the Philadelphia Electric 
    Company (PECo) and LIPA, the slightly irradiated fuel stored in the 
    SNPS spent fuel pool was transferred to the Limerick Generating Station 
    for reuse. The fuel transfers began in September 1993, and were 
    completed in June 1994.
        The dismantlement and decontamination tasks necessary for 
    decommissioning SNPS, began in June 1992, and were completed in August 
    1994. All contaminated waste generated during the decommissioning of 
    SNPS has been removed from the site.
    III
    
        The SNPS proposed DP was approved by an Order dated June 11, 1992. 
    Approximately 602 curies of radioactive material were present in the 
    RPV and internal components; 1370 curies in the control rod blades, 
    local-power-range monitors, and antimony/beryllium pins; 457 
    millicuries in the reactor bioshield wall; and 3 millicuries in 
    contaminated systems and areas. Approximately 593 millicuries were 
    present in the spent fuel storage pool water (SFSP) and on the surfaces 
    of the SFSP and fuel storage racks.
        The SNPS was decommissioned in accordance with the approved DP, as 
    supplemented. The licensee decommissioned SNPS by dismantlement and 
    decontamination. The activated and contaminated reactor vessel 
    internals were removed and disposed of as radioactive waste. Activated 
    portions of the reactor pressure vessel (RPV) that exceeded 
    unrestricted release criteria, were segmented, packaged, and disposed 
    as radioactive waste. Large contaminated components and portions of 
    plant systems and structures that could not be decontaminated 
    effectively were segmented, as necessary, and packaged and shipped 
    offsite for volume reduction and/or direct disposal at licensed low-
    level waste disposal facilities. Contaminated water was processed and 
    released in accordance with approved release requirements, and 
    activated portions of the reactor bioshield wall exceeding unrestricted 
    release criteria were removed and disposed as low-level radioactive 
    waste.
        The DP, as supplemented, contained the licensee's Termination 
    Survey Plan (Plan). The Plan described the methods used to demonstrate 
    compliance with the existing NRC unrestricted release criteria. The 
    guidelines used by the licensee for residual radioactivity at the SNPS 
    are consistent with the values provided in Table 1, of Regulatory Guide 
    1.86, which establishes acceptable residual surface contamination 
    levels. NRC approved alternative contamination limits for iron-55 and 
    tritium above those specified in Regulatory Guide 1.86. These 
    alternative criteria were presented to the Commission in SECY 94-145 
    and increased the allowable residual average and maximum total residual 
    beta activity levels for iron-55 and tritium from 5,000 average total 
    and 15,000 maximum total (fixed plus removable) disintegrations per 
    minute (dpm)/100 square centimeters to 200,000 average total and 
    600,000 maximum total dpm/100 square centimeters, respectively. This 
    permitted the licensee to safely retain on site major portions of the 
    reactor bioshield wall that did not exceed the gamma dose rate 
    criterion or the surface contamination limits for other isotopes, but 
    which would have required offsite disposal under the original iron-55 
    and tritium surface contamination limits of Regulatory Guide 1.86. A 
    concentration limit for cobalt-60 in soil and other bulk materials of 8 
    picocuries per gram was also established. An average gamma dose rate 
    criterion of 5 uR per hour above background, at a distance of 1 meter 
    from accessible surfaces, and an individual gamma exposure rates are 
    not to exceed 10 uR per hour above background at 1 meter were used. In 
    addition, the licensee's Plan also described the technical methods that 
    would be used for the planning and design of the Termination Survey. 
    The methods used by the licensee for the planning and design of the 
    Termination Survey were derived from regulatory guidance contained in 
    the NRC Regulatory Guide 1.86 and draft NUREG/CR-5849.
        The licensee's Termination Plan was implemented at the individual 
    survey unit level. The licensee established the following three survey 
    units: (1) Structures, which included building interiors; (2) plant 
    systems; and (3) outdoor areas. The licensee used a phased approach to 
    conduct the actual termination surveys. Phase 1 of the termination 
    surveys included surveys of the main turbine internals, turbine 
    building, site and grounds, and the exterior of buildings. Phases 2 and 
    3 of the termination surveys included portions of the reactor and 
    radwaste buildings and the suppression pool. Phase 4 (final phase) of 
    the termination survey included those portions of the reactor and spent 
    fuel pool used to support irradiated fuel storage, before the fuel's 
    removal from the site. The licensee completed the Termination Surveys 
    in August 1994.
        The licensee submitted phases 1, 2, and 3 of the Final Termination 
    Survey Reports to NRC in September 1993, February 1994, and June 1994, 
    respectively. Phase 4 of the Final Termination Report was submitted to 
    NRC for review in October 1994. The Oak Ridge Institute for Science and 
    Education (ORISE) performed independent confirmatory surveys at SNPS 
    for NRC.
        Based on the licensee's completion of the decommissioning tasks at 
    the SNPS, as described in the approved DP, and supplements, the staff's 
    review of the licensee's Final Termination Survey Reports, and the 
    results of the ORISE confirmatory surveys, the staff has determined 
    that the decommissioning of the SNPS is complete, that the residual 
    radioactivity levels have been reduced in accordance with NRC release 
    criteria, and that the facility and the site are suitable to be 
    released for unrestricted use.
    
    IV
    
        Accordingly, pursuant to sections 103, 161b, 161i, and 161o of the 
    Atomic Energy Act of 1954, as amended, and the Commission's regulations 
    in 10 CFR 2.202 and 10 CFR 50.82(f), NRC terminates License No. NPF-82.
        Any person adversely affected by this Order may request a hearing 
    within 20 days of its issuance. Any request for a hearing shall be 
    submitted to the Secretary, U.S. Nuclear Regulatory Commission, ATTN: 
    Chief, Docketing and Service Section, Washington, DC 20555. Copies of 
    the hearing request shall also be sent to the Director, Office Nuclear 
    Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, 
    Washington, DC 20555, to the Assistant General Counsel for Hearings and 
    Enforcement at the same address, to the Regional Administrator, NRC 
    Region I, 475 Allendale Road, King of Prussia, PA 19406, and to the 
    licensee. If such a person requests a hearing, that person 
    [[Page 19311]] shall set forth with particularity the manner in which 
    his interest is adversely affected by this Order and shall address the 
    criteria set forth in 10 CFR 2.714(d). The Commission will issue an 
    Order designating the time and place of the hearing.
        If a hearing is granted, the issue to be heard is whether the 
    licensee complied with the Commission-approved decommissioning plan.
        In the absence of any request for hearing, the provisions specified 
    in Section IV above shall be final 20 days from the date of this Order 
    without further order or proceedings.
        For further details with respect to this action, see: (1) The 
    licensee's request to terminate the SNPS license presented in letters 
    dated June 27, 1991 (SNRC-1818), and August 4, 1994 (LSNRC-2178); (2) 
    the Commission's Order approving decommissioning dated June 11, 1992; 
    (3) the licensee's Termination Survey Final Report, Phase 1 (LSNRC-
    2101), dated September 30, 1993; the licensee's Termination Survey 
    Final Report, Phase 2 (LSNRC-2144), dated February 4, 1994; the 
    licensee's Termination Survey Final Report, Phase 3 (LSNRC-2173), dated 
    June 14, 1994; the licensee's Termination Survey Final Report, Phase 4 
    (LSNRC-2184), dated October 12, 1994; and (4) the ORISE Final 
    Confirmatory Reports dated July 1993, September 1994, and February 
    1995. These documents are available for public inspection at the 
    Commission's Public Document Room, the Gelman Building, 2102 L Street, 
    NW., Washington, DC 20555, and at the Shoreham Wading River Public 
    Library, Route 25A, Shoreham, NY 11786. Copies may be obtained upon 
    request addressed to the U.S. Nuclear Regulatory Commission, 
    Washington, DC 20555, Attention: Director, Division of Waste 
    Management.
    
        Dated at Rockville, Maryland, this 11th day of April, 1995.
    
    For the Nuclear Regulatory Commission.
    John T. Greeves,
    Director, Division of Waste Management, Office of Nuclear Material 
    Safety and Safeguards.
    [FR Doc. 95-9373 Filed 4-14-95; 8:45 am]
    BILLING CODE 7590-01-M
    
    

Document Information

Published:
04/17/1995
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
95-9373
Pages:
19309-19311 (3 pages)
Docket Numbers:
Docket No. 50-322, License No. NPF-82
PDF File:
95-9373.pdf