[Federal Register Volume 59, Number 74 (Monday, April 18, 1994)]
[Unknown Section]
[Page 0]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 94-9245]
[[Page Unknown]]
[Federal Register: April 18, 1994]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EL94-47-000, et al.]
Florida Municipal Power Agency, et al. Electric Rate and
Corporate Regulation Filings
April 8, 1994.
Take notice that the following filings have been made with the
Commission:
1. Florida Municipal Power Agency v. Florida Power & Light Company
Docket No. EL94-47-000; Docket Nos. ER93-465-000 [Not yet
Consolidated]
Take notice that on March 17, 1994, Florida Municipal Power Agency
(FMPA) tendered for filing a complaint against Florida Power & Light
Company (FP&L) and a Motion to Consolidate with Florida Power & Light
Company, Docket Nos. ER93-465-000, et al.
In its complaint FMPA seeks an order from the Commission: (1)
Finding that the rate currently charged by FP&L for partial
requirements (PR) service under its Wholesale Service Tariff may be
unjust and unreasonable, may produce excessive revenues from FMPA, and
should be subject to reduction and refund consistent with the
complaint; (2) establishing a refund-effective date 60 days after the
date of filing of this complaint; (3) consolidating of the
consideration of the matters raised by this complaint with the ongoing
proceedings in Docket Nos. ER93-465-000, et al.; and (4) affording FMPA
such other relief as may be deemed appropriate.
Comment date: May 9, 1994, in accordance with Standard Paragraph E
at the end of this notice.
2. Portland General Electric Company
[Docket No. ER94-963-000]
Take notice that on February 22, 1994, Portland General Electric
Company tendered for filing a Certificate of Concurrence in the above-
referenced docket.
Comment date: April 22, 1994, in accordance with Standard Paragraph
E at the end of this notice.
3. Massachusetts Electric Company
[Docket No. ER94-798-000]
Take notice that Massachusetts Electric Company (Mass. Electric) on
April 4, 1994, tendered an amendment to its filing in this proceeding.
Mass. Electric's proposed amendment includes a Petition for Waiver of
the Fuel Adjustment Clause Regulations.
Comment date: April 22, 1994, in accordance with Standard Paragraph
E at the end of this notice.
4. Montaup Electric Company
[Docket No. ER94-1062-000]
Take notice that Montaup Electric Company on March 31, 1994
tendered for filing additional information to its March 21, 1994 filing
in the above-referenced docket.
Comment date: April 22, 1994, in accordance with Standard Paragraph
E at the end of this notice.
5. Ocean State Power II
[Docket No. ER94-1067-000]
Take notice that on March 21, 1994, Ocean State Power II (Ocean
State II) tendered for fling the following supplement (the Supplement)
to its rate schedules with the Federal Energy Regulatory Commission
(FERC or the Commission).
Supplement No. 16 to Rate Schedule FERC No. 8
This filing requests approval of the assignment, and Ocean State
II's acceptance thereof, by Newport Electric Corporation (Newport) of
all of its rights and obligations under its unit power agreement (the
Agreement) with Ocean State II to Montaup Electric Company (Montaup).
On March 27, 1990, Newport became a wholly-owned subsidiary of Eastern
Utilities Associates (EUA), a registered public utility holding
company. Newport intends to become an all-requirements customer of
Montaup, the bulk-power supply entity of the EUA system, and has,
therefore, assigned all of its rights and obligations under the
Agreement to Montaup, such assignment to become effective on the FERC-
allowed effective date for Montaup's modified all-requirements
wholesale tariff, filed on March 21, 1994.
Ocean State, pursuant to Section 10.6 of the Agreement, has
consented to the assignment by Newport of its rights and obligations
under the Agreement to Montaup.
Comment date: April 22, 1994, in accordance with Standard Paragraph
E at the end of this notice.
6. Kansas City Power & Light Company
[Docket No. ER94-1108-000]
Take notice that on March 31, 1994, Kansas City Power & Light
Company (KCPL) tendered for filing an Amendment and Associated Service
Schedule as an additional service pursuant to an Interchange Agreement
dated July 15, 1988, between KCPL and the Union Electric Company (UE).
In its filing, KCPL states that this Amendment and Associated
Service Schedule provides for replacement of an existing tap structure
and the addition of a second structure to modify an existing
interconnection between KCPL and UE.
Comment date: April 21, 1994, in accordance with Standard Paragraph
E at the end of this notice.
7. Wisconsin Public Service Corporation
[Docket No. ER94-1109-000]
Take notice that on March 31, 1994, Wisconsin Public Service
Corporation (WPSC), tendered for filing an amendment to its February
22, 1993, agreement with the City of Marshfield, Wisconsin pursuant to
which WPSC provides Marshfield with various electric services and has
provided Marshfield an option to purchase a share of a combustion
turbine generating unit. The amendment reflects Marshfield's exercise
of the option to purchase a share of the generating unit; modifies the
parties' agreement with respect to WPSC's lease of transmission
facilities from Marshfield; and makes several other changes to the
agreement.
WPSC requests that the Commission waive the 60-day notice
provisions of the Federal Power Act and the Commission's regulations
thereunder as necessary to allow the amendment to become effective on
October 1, 1993.
WPSC states that copies of this filing have been served on the City
of Marshfield and the Public Service Commission of Wisconsin.
Comment date: April 21, 1994, in accordance with Standard Paragraph
E at the end of this notice.
8. Puget Sound Power & Light Company
[Docket No. ER94-1110-000]
Take notice that on March 31, 1994, Puget Sound Power & Light
Company (Puget) submitted a supplement to its earlier filing in the
above-referenced docket of a changes in Puget Rate Schedule FERC No. 16
between the United States of America Department of Energy acting by and
through the Bonneville Power Administration (Bonneville) and Puget. A
copy of the supplement was served upon Bonneville.
Comment date: April 21, 1994, in accordance with Standard Paragraph
E at the end of this notice.
9. Puget Sound Power & Light Company
[Docket No. ER94-1111-000]
Take notice that on March 31, 1994, Puget Sound Power & Light
Company (Puget) tendered for filing, as an initial rate schedule, an
unexecuted letter agreement by and between Puget and the United States
of America Department of Energy acting by and through the Bonneville
Power Administration (Bonneville), together with attachments thereto
(the Agreement). A copy of the filing was served upon Bonneville.
Puget states that the Agreement relates to construction of bypass
and related facilities in connection with service by Puget for a
Bonneville wholesale customer.
Comment date: April 21, 1994, in accordance with Standard Paragraph
E at the end of this notice.
10. Puget Sound Power & Light Company
[Docket No. ER94-1112-000]
Take notice that on March 31, 1994, Puget Sound Power & Light
Company (Puget) tendered for filing a change to Puget Rate Schedule
FERC No. 88 between Puget and Public Utility District No. 1 of
Snohomish County (District). A copy of the filing was served upon
District.
Puget states that under a Supplement to the Rate Schedule Puget
provides Standby transmission service to District. The Supplement
changes the transmission demand limit and the daily charge for such
transmission service.
Comment date: April 21, 1994, in accordance with Standard Paragraph
E at the end of this notice.
11. Western Resources, Inc.
[Docket No. ER94-1116-000]
Take notice that on March 31, 1994, Western Resources, Inc., (WRI)
tendered for filing a proposed change in its Rate Schedule FERC No. 264
and to Kansas Gas and Electric's (KG&E) Rate Schedule FERC No. 183. WRI
states that the change is in accordance with its Electric Power,
Transmission and Service Contract with Kansas Electric Power
Cooperative (KEPCo) and further that the proposed change for KG&E is in
accordance with the Electric Power, Transmission and Service contract
between KG&E and KEPCo. Revised Exhibits B set forth Nominated
Capacities for transmission, distribution and dispatch service for the
contact year beginning June 1, 1994 and for the four subsequent
contract years, pursuant to Article IV, Section 4.1 of Rate Schedule
FERC Nos. 264 and 183. Revised Exhibits C set forth KEPCo's Nominated
Capacities for the Points of Interconnection, pursuant to Article IV,
Section 4.1 of Rate Schedule FERC Nos. 264 and 183. Revised Exhibits D
set forth KEPCo's load forecast and KEPCo's Capacity Resources intended
to provide power and energy to meet the forecast requirements for ten
years into the future, pursuant to Article V, Section 5.1 of Rate
Schedule FERC Nos. 264 and 183.
Copies of the filing were served upon Rate Kansas Electric Power
Cooperative, Inc. and the Kansas Corporation Commission.
Comment date: April 21, 1994, in accordance with Standard Paragraph
E at the end of this notice.
12. Idaho Power Company
[Docket No. ER94-1117-000]
Take notice that on March 31, 1994, Idaho Power Company tendered
for filing an agreement with Sierra Pacific Power Company entitled
Agreement for the Purchase, Supply and Firm Transmission of Power and
Energy. Idaho Power Company has requested an effective date for the
agreement of July 1, 1994.
Comment date: April 21, 1994, in accordance with Standard Paragraph
E at the end of this notice.
13. Public Service Electric and Gas Company
[Docket No. ER94-1118-000]
Take notice that Public Service Electric and Gas Company (PSE&G) of
Newark, New Jersey, on behalf of itself and GPU Service Corporation
(GPUSC) of Parsippany, New Jersey, on April 1, 1994, tendered for
filing an agreement for the sale, purchase, and/or exchange of
Pennsylvania-New Jersey-Maryland Interconnection (PJM) Installed
Capacity Credits. Pursuant to the agreement, the PJM Installed Capacity
Credits will be sold, purchased, and/or exchanged at a rate not to
exceed the rate for purchasing capacity as set forth in the appropriate
schedule of the PJM Agreement.
Copies of the filing have been served upon GPUSC and interested
state commissions.
Comment date: April 21, 1994, in accordance with Standard Paragraph
E at the end of this notice.
14. Florida Power & Light Company
[Docket No. ER94-1119-000]
Take notice that on April 1, 1994, Florida Power & Light Company
(FPL) tendered for filing the Notices of Contract Demand for Power
Years 1994, 1995 and 1996 for the following customers under Rate
Schedule PR of FPL's Wholesale Electric Tariff: City of Starke; City of
Jacksonville Beach; City of Green Cove Springs; and the City of
Clewiston. FPL also tendered for filing the Notices of Contract Demand
under Rate Schedule PR for the City of Homestead for Power Year 1994
and for the period June 1, 1995 through September 30, 1995 and the
Notice of Contract Demand for the Utilities Commission, New Smyma Beach
for the period June 1, 1994 through November 28, 1994.
Comment date: April 21, 1994, in accordance with Standard Paragraph
E at the end of this notice.
15. Midwest Power Systems Inc.
[Docket No. ER94-1120-000]
Take notice that on April 1, 1994, Midwest Power Systems Inc.
(MPSI) tendered for filing revised Service Schedule A dated March 16,
1994, to a Facilities Agreement (Agreement) between N.W. Electric Power
Cooperative (Northwest) and Iowa Power and Light Company (IPL), a/k/a
MPSI.
By letter dated October 31, 1989, the Commission accepted for
filing revised Service Schedules A and B (Docket No. ER89-671-000)
dated January 18, 1989, between IPL and Northwest. This filing was
designated Supplement Nos. 3 and 4 to IPL Rate Schedule FERC No. 40 and
redesignated MPSI Rate Schedule FERC No. 9 in Docket No. ER92-784-000.
Service Schedule A, dated March 16, 1994, supersedes the Service
Schedule A currently effective under the Agreement between MPSI and
Northwest. The revised Service Schedule A covers the ownership,
maintenance, and operation of two 13 Kv breakers at the Hamburg
Substation.
MPSI states that copies of this filing were served on Northwest and
the Iowa Utilities Board.
Comment date: April 21, 1994, in accordance with Standard Paragraph
E at the end of this notice.
16. Okeelanta Power Limited Partnership
[Docket No. QF94-64-000]
On April 7, 1994, Okeelanta Power Limited Partnership tendered for
filing an amendment to its initial filing in this docket.
The amendment pertains to the ownership structure and technical
aspects of the cogeneration facility. No determination has been made
that the submittal constitutes a complete filing.
Comment date: April 28, 1994, in accordance with Standard Paragraph
E at the end of this notice.
Standard Paragraphs
E. Any person desiring to be heard or to protest said filing should
file a motion to intervene or protest with the Federal Energy
Regulatory Commission, 825 North Capitol Street NE., Washington, DC
20426, in accordance with Rules 211 and 214 of the Commission's Rules
of Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such
motions or protests should be filed on or before the comment date.
Protests will be considered by the Commission in determining the
appropriate action to be taken, but will not serve to make protestants
parties to the proceeding. Any person wishing to become a party must
file a motion to intervene. Copies of this filing are on file with the
Commission and are available for public inspection.
Lois D. Cashell,
Secretary.
[FR Doc. 94-9245 Filed 4-15-94; 8:45 am]
BILLING CODE 6717-01-P