97-10071. Entergy Operations, Inc.; System Energy Resources, Inc.; South Mississippi Electric Power Association; Entergy Mississippi, Inc.; Grand Gulf Nuclear Station, Unit 1; Environmental Assessment and Finding of No Significant Impact  

  • [Federal Register Volume 62, Number 75 (Friday, April 18, 1997)]
    [Notices]
    [Pages 19144-19147]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-10071]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 50-416]
    
    
    Entergy Operations, Inc.; System Energy Resources, Inc.; South 
    Mississippi Electric Power Association; Entergy Mississippi, Inc.; 
    Grand Gulf Nuclear Station, Unit 1; Environmental Assessment and 
    Finding of No Significant Impact
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering the issuance of an amendment to Facility Operating License 
    No. NPF-29, issued to Entergy Operations, Inc. (the licensee), for 
    operation of the Grand Gulf Nuclear
    
    [[Page 19145]]
    
    Station, Unit 1 (GGNS), located in Claiborne County, Mississippi.
    
    Environmental Assessment
    
    Identification of the Proposed Action
    
        GGNS is currently licensed to operate until June 16, 2022, which is 
    40 years from the issuance of the low-power license on June 16, 1982. 
    The proposed action would extend the expiration date of the operating 
    license from June 16, 2022, to November 1, 2024. The extended date 
    under consideration would be 40 years after the full-power license was 
    issued on November 1, 1984.
        The proposed action is in accordance with the licensee's 
    application for amendment dated July 21, 1995.
    
    The Need for the Proposed Action
    
        The proposed action would allow the licensee to operate GGNS until 
    November 1, 2024. This would allow the licensee to recapture 
    approximately 2.5 years of low-power operation from June 16, 1982, to 
    November 1, 1984, which was an unusually long period for low-power 
    operation. For the low-power license, the licensee was only authorized 
    to operate the plant up to 5 percent of rated power or 191 megawatts 
    thermal. On August 31, 1984, the Commission amended the low-power 
    license to allow the licensee to operate up to 100 percent rated power 
    or 3833 megawatts thermal. However, in response to a court challenge to 
    the amendment, the Commission issued CLI-84-19 on October 25, 1984, 
    directing the Staff to issue a separate full power license to GGNS. 
    This action by the Commission prevented the licensee from operating 
    GGNS at full power. On November 1, 1984, a full power license was 
    issued to GGNS whose expiration date was 40 years from the date of 
    issuance of the low power license. In the full-power license, the 
    licensee was authorized to operate up to 100 percent of rated power.
        Therefore, this proposed action would allow the licensee to operate 
    GGNS for approximately two additional operating cycles before the plant 
    would be shut down for the expiration of the operating license. The 
    licensee stated that the benefits of the proposed action were the 
    following:
    
         Reduction in the need for buying replacement power, 
    because of operating GGNS, on the order of $120 million using 
    current estimates;
         Additional flexibility in long-range planning by the 
    licensee and a savings in excess of $100,000 in construction costs;
         Deferral of additional system construction;
         Delayed application for license renewal under 10 CFR 
    part 54 until the process has been implemented;
         Compatibility with projected refueling outage schedules 
    for GGNS.
    
    Environmental Impacts of the Proposed Action
    
        The Commission has completed its evaluation of the proposed action 
    and concludes that there are no significant environmental 
    considerations involved with the proposed action. The extension of the 
    operating license does not affect the design or operation of the plant, 
    does not involve any modifications to the plant or any increase in the 
    licensed power for the plant, and will not create any new or unreviewed 
    environmental impacts that were not considered in the Final 
    Environmental Statement (FES) related to the operation of GGNS, NUREG-
    0777, dated September 1981. The evaluations presented in the FES were 
    the environmental impacts of generating power at GGNS and the basis for 
    granting a 40-year operating license for GGNS. The environmental 
    impacts of the proposed action are based on the evaluations in the FES. 
    The FES also considered the environmental impacts of operating both 
    Unit 1 and Unit 2; however, Unit 2 was abandoned in 1985 and was never 
    completed.
        Although the FES considered a specific operating period of 30 years 
    for GGNS, the staff concluded in the full-power license issued on 
    November 1, 1984, that the environmental impacts associated with a 40-
    year operating period were sufficiently addressed in the FES. This was 
    based on a consideration of the FES which in general, assesses various 
    impacts associated with operation of the facility in terms of annual 
    impacts and balances these against the anticipated annual energy 
    production benefits. Thus, the overall assessment and conclusions would 
    not be dependent on a specific operating life. There are, however, 
    three areas in which a specific operating life was assumed:
    
    1. Project costs are based on a 30-year levelized cost.
    2. Radiological assessments are based on a 15-year plant midlife.
    3. Uranium fuel cycle impacts are based on one initial core load and 
    annual refuelings.
    
        These were assessed by the staff to determine whether the use of a 
    40-year operating period rather than a 30-year operating period would 
    significantly affect the staff's assessment concerning these areas.
    1. Projected Costs
        The projected costs of the facility which includes the cost of 
    decommissioning are based on a 30-year operating life and are levelized 
    over that period of time. The use of a 40-year operating period rather 
    than a 30-year period would not significantly affect the operating and 
    maintenance cost. If the facility's capital cost were spread over a 40-
    year period, the overall resulting cost of facility operation would be 
    lowered. Therefore, any extension in the operating life of the facility 
    would result in savings in system production costs. The production of 
    energy at reduced cost results in an incremental net benefit for the 
    use of a 40-year operating life of the facility.
    2. Radiological Assessments
        The NRC staff calculates dose commitments to the human population 
    residing around nuclear power reactors to assess the impact on people 
    from radioactive material released from these reactors. The annual dose 
    commitment is calculated to be the dose that would be received over a 
    50-year period following the intake of radioactivity for 1 year under 
    the conditions that would exist 15 years after the plant began 
    operation.
        The 15-year period is chosen as representing the midpoint of plant 
    operation and factors into the dose models by allowing for buildup of 
    long life radionuclides in the soil. It affects the estimated doses 
    only for radionuclides ingested by humans that have half-lives greater 
    than a few years. For a plant licensed for 40 years, increasing the 
    buildup period from 15 to 20 years would increase the dose from long 
    life radionuclides via the ingestion pathways by 33% at most. It would 
    have much less effect on dose from shorter life radionuclides. Tables 
    D-4 and D-5 of Appendix D to the FES indicate that the estimated doses 
    via the ingestion pathways are only a fraction of the regulatory design 
    objectives. For example, the ingestion dose to the thyroid is 7.0 mrem/
    yr compared to an Appendix I design objective of 15 mrem/yr. Thus, for 
    7 mrem/yr, an increase of even as much as 33% in these pathways results 
    in a dose within the Appendix I guidelines and would still not be 
    significant.
    3. Uranium Fuel Cycle Impacts
        The impacts of the uranium fuel cycle are based on 30 years of 
    operation of a model light water reactor (LWR). The fuel requirements 
    for the model LWR were assumed to be one initial core load and 29 
    annual refuelings (approximately \1/3\ core). The annual fuel 
    requirements for the model LWR averaged out over a 40-year operating 
    life (1 initial core and 39 refuelings of approximately \1/3\ core)
    
    [[Page 19146]]
    
    would be reduced slightly as compared to the annual fuel requirement 
    averaged for a 30-year operating life.
        The net result would be an approximately 1.5% reduction in the 
    annual fuel requirement for the model LWR. This small reduction in fuel 
    requirements would not lead to significant changes in the impacts of 
    the uranium fuel cycle. The staff does not believe that there would be 
    any changes to Grand Gulf FES Table 5.10 (S-3) that would be necessary 
    in order to consider 40 years of operation. If anything, the values in 
    Table 5.10 become more conservative when a 40-year period of operation 
    is considered.
        The staff has concluded, based on the reasons discussed above, that 
    the impacts associated with a 40-year operating license duration are 
    not significantly different from those associated with a 30-year 
    operating license duration assessed in the Grand Gulf FES. Therefore, 
    the staff concluded that the Grand Gulf FES sufficiently addresses the 
    environmental impacts associated with a 40-year operating period.
        The considerations involved in completing the Commission's 
    evaluation for the proposed action are discussed below.
    
    1. Radiological Impacts of Design Basis Accidents
    
        The offsite exposure from releases during postulated accidents has 
    been previously evaluated in the Updated Final Safety Analysis Report 
    (UFSAR) for GGNS. The results are acceptable when compared with the 
    criteria defined in 10 CFR Part 100, as documented in the Commission's 
    Safety Evaluation Report, NUREG-0831, dated September 1981, and its 
    seven supplements.
        This conservative design-basis evaluation is a function of four 
    parameters: (1) The type of accident postulated, (2) the radioactivity 
    calculated to be released during the accident, (3) the assumed 
    meteorological conditions at the site, and (4) the population 
    distribution versus distance from the plant. An environmental 
    assessment of accidents is also provided in Section 5.9.2 of the FES. 
    The type of accidents and the calculated radioactivity released do not 
    change with the proposed action. The site meteorology as defined in 
    Chapter 2 of the UFSAR is essentially constant. The Commission staff 
    has concluded that the population size and distribution is the only 
    parameter in the accident analyses that is considered to change for the 
    proposed action.
        The licensee presented information on the population distribution 
    in the general vicinity of GGNS as new data from the 1980 and 1990 
    census compared to the data presented also in Chapter 2 of the UFSAR. 
    The 1980 and 1990 census show a general reduction in the near site 
    population (up to 10 miles) and in Mississippi communities and 
    population centers within 50 miles of the site. Because of the general 
    reduction in population near the site and the short 2.5 years that the 
    license is proposed to be extended, the staff concludes that the 
    proposed action will not significantly change previous conclusions on 
    the potential environmental of offsite releases from postulated 
    accidents.
    
    2. Radiological Impacts of Annual Releases
    
        The annual occupational exposure of workers at the plant, station 
    employees and contractors, is reported in the Annual Operating Report 
    for GGNS submitted by the licensee. For 1989 through 1995, the annual 
    exposure has been measured at values between 56 and 484 person-rems, 
    with the average annual exposure over 7 years being 327 person-rems. 
    The lowest exposure value is for a year without a refueling outage and 
    the highest value is for a year with a refueling outage. In Section 
    5.9.1.1.1 of the FES, the average occupational exposure for a boiling 
    water reactor, as is GGNS, was reported as 740 person-rems. Therefore, 
    the expected annual occupational exposure for the proposed extended 
    period of operation does not change previous conclusions presented in 
    the FES on occupational exposure.
        The offsite exposure from releases during routine operations has 
    been previously evaluated in Section 5.9.1 of the FES. During the low-
    power license up to August 31, 1984, the plant was restricted to no 
    more than 5 percent of rated power and the generation of radioactivity 
    at the plant was significantly smaller than would have occurred if the 
    plant was at full-power operation. The licensee provided in its 
    application the annual public dose from releases of radioactive 
    materials in gaseous and liquid effluents from GGNS for 1987 through 
    1994. These doses for 1995 were reported in the 1995 Annual Radioactive 
    Effluent Release Report which was submitted in the licensee's letter of 
    May 2, 1996. These doses were a small fraction of the dose design 
    objectives of Appendix I to 10 CFR Part 50 which were the estimates of 
    doses to the public that the FES was based on. The average of the 9 
    years was less than 10 percent of the Appendix I values. Therefore, the 
    additional 2.5 years of operation that the licensee has requested does 
    not change previous conclusions presented in the FES on annual public 
    doses.
    
    3. Environmental Impact of the Uranium Fuel Cycle
    
        In addition to the impacts associated with the operation of the 
    plant, there are impacts associated with the uranium fuel cycle. The 
    uranium fuel cycle includes those facilities and processes (e.g., 
    uranium mills, fuel fabrication plants, and fuel enrichment facilities) 
    that are necessary to support the operation of the plant by providing 
    the fuel for the reactor. Section 5.10 of the FES described the impacts 
    associated with the fuel cycle for GGNS.
        The operation of the plant from June 16, 1982, to November 1, 1984, 
    did not consume sufficient fuel to require the licensee to use any more 
    fuel than was expected in the estimate for 40 years of operations. If 
    the plant had operated at the maximum power level allowed by the low-
    power license from June 16, 1982, to November 1, 1984, the impact on 
    fuel of this operation would be less than 1 percent of that for the 40 
    years of operation at 100 percent power which is allowed by the full-
    power license. Therefore, the proposed action does not change the 
    estimates of the impacts of the fuel cycle that were presented in the 
    FES.
    
    4. Transportation of Fuel and Radioactive Waste
    
        The environmental impacts of transportation of fuel to and from the 
    site and the transportation of solid radioactive wastes from the site 
    to a waste burial grounds were considered in Table 5.3 of the FES. 
    Because the proposed action should not change the amount of fuel that 
    is expected to be used in 40 years of operations, the impacts in the 
    FES associated with the transportation of fuel should not change due to 
    the proposed action.
        The licensee provides the amount of solid radioactive wastes 
    shipped from the site in its annual (after 1992) and semi-annual (up 
    through 1992) radioactive effluent release reports. In these reports 
    for 1991 through 1995, the average amount of solid radioactive wastes 
    shipped for these 5 years was 46 truck shipments of less than 190 cubic 
    meters per year. This is less than the annual impact reported in the 
    FES for transportation of solid radioactive wastes; therefore, the 
    proposed action should not exceed the environmental impacts given in 
    the FES.
    
    [[Page 19147]]
    
    5. Nonradiological Impacts
    
        The staff has reevaluated the non-radiological impacts associated 
    with the operation of the plant for the proposed action. The non-
    radiological impacts, primarily on water and land use, are shown in the 
    FES to be minor. The major non-radiological impact is the 
    concentrations in and the temperature of the water discharged from the 
    plant to the nearby Mississippi River. The plant makeup and service 
    water is supplied by a series of radial collector wells located in the 
    floodplain parallel to the Mississippi, as described in Section 2.4 of 
    the UFSAR and Section 4.2.3 of the FES. The wells are cylindrical 
    concrete caissons sunk into the alluvial aquifer adjacent to the 
    Mississippi River with perforated pipes projecting horizontally into 
    the aquifer, which draw water from the aquifer and the Mississippi 
    River. The cooling of water for power generation is provided by a 
    cooling tower. The water discharged from the plant to the Mississippi 
    River is the cooling tower blowdown from the cooling tower basin to 
    maintain water quality.
        As explained in Section 5.6 of the FES, the plant's discharges to 
    the Mississippi are regulated by applicable Federal effluent 
    limitations under Sections 401 and 402 of the Federal Water Pollution 
    Control Act. Section 401 is a certification and Section 402 is the 
    National Pollutant Discharge Elimination System (NPDES) Permit, which 
    are issued by the State of Mississippi. These restrictions on the plant 
    effluent into the Mississippi River are not affected by the proposed 
    action.
        In NUREG-1437, ``Generic Environmental Impact Statement for License 
    Renewal of Nuclear Plants,'' dated October 27, 1995, the use of 
    groundwater at GGNS, from the radial collector wells for the cooling 
    tower makeup, is discussed in Sections 4.8.1.4 and 4.8.2.2, in terms of 
    the impact of the groundwater intake on the groundwater level and the 
    water quality. These sections state that the intake of cooling water by 
    GGNS does not conflict with other groundwater uses in the area and that 
    the intake water quality will not be lower than that in the nearby 
    Mississippi River. This is consistent with Section 2.4 of the UFSAR. 
    Therefore, NUREG-1437 shows no adverse environmental impact by the 
    proposed action; however, if the licensee should apply for license 
    renewal of the GGNS full-power operating license under 10 CFR Part 54, 
    ``Requirements for Renewal of Operating Licenses for Nuclear Power 
    Plants,'' the issue of other groundwater uses in the vicinity of the 
    plant would be addressed.
    
    6. Conclusion
    
        Beyond the impacts discussed above, the proposed action will not 
    increase the probability or consequences of any accidents and will not 
    change the licensed power level for the plant. No changes are being 
    made to any structure, system, or component in the plant, to how the 
    plant is operated, in the types of any effluents that may be released 
    offsite, and in the allowable individual or cumulative occupational 
    radiation exposure for the plant. Accordingly, the Commission concludes 
    that there are no significant radiological environmental impacts 
    associated with the proposed action.
        With regard to potential nonradiological impacts, the proposed 
    action does involve features located entirely within the restricted 
    area as defined in 10 CFR Part 20. It does not affect nonradiological 
    plant effluents and has no other environmental impact. Accordingly, the 
    Commission concludes that there are no significant nonradiological 
    environmental impacts associated with the proposed action.
    
    Alternatives to the Proposed Action
    
        Since the Commission has concluded there is no significant 
    environmental impact associated with the proposed action, any 
    alternatives with equal or greater environmental impact need not be 
    evaluated. As an alternative to the proposed action, the staff 
    considered denial of the proposed action. In this case, GGNS would shut 
    down upon expiration of the present full-power operating license. 
    Denial of the application would result in no change in current 
    environmental impacts. The environmental impacts of the proposed action 
    and the alternative action are similar.
        In Section 6.4 of the FES, a benefit-cost analysis was presented 
    for the operation of GGNS. The environmental costs for the extended 
    period of operation would be less than the cost of the replacement 
    power or the installation of new electrical generating capacity. 
    Moreover, with the extended period of operation, the overall financial 
    cost per year of the plant would decrease because the initial capital 
    outlay would be averaged over a greater number of years of operation. 
    In summary, the benefit-cost of operating GGNS would improve with the 
    extended plant operating lifetime.
    
    Alternative Use of Resources
    
        This action does not involve the use of any resources not 
    previously considered in the FES for the GGNS.
    
    Agencies and Persons Consulted
    
        In accordance with its stated policy, on April 8, 1997, the staff 
    consulted with Mississippi State officials, Robert Goff and Robert Bell 
    of the Division of Radiological Health, State Board of Health, 
    regarding the environmental impact of the proposed action. The State 
    officials had no comments.
    
    Finding of No Significant Impact
    
        Based upon the environmental assessment, the Commission concludes 
    that the proposed action will not have a significant effect on the 
    quality of the human environment. Accordingly, the Commission has 
    determined not to prepare an environmental impact statement for the 
    proposed action.
        For further details with respect to the proposed action, see the 
    licensee's letter dated July 21, 1995, which is available for public 
    inspection at the Commission's Public Document Room, The Gelman 
    Building, 2120 L Street, NW., Washington, DC, and at the local public 
    document room located at the Judge George W. Armstrong Library, 220 S. 
    Commerce Street, Natchez, Mississippi 39120.
    
        Dated at Rockville, Maryland, this 11th day of April, 1997.
    
        For the Nuclear Regulatory Commission.
    William D. Beckner,
    Director, Project Directorate IV-1, Division of Reactor Projects III/
    IV, Office of Nuclear Reactor Regulation.
    [FR Doc. 97-10071 Filed 4-17-97; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
04/18/1997
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
97-10071
Pages:
19144-19147 (4 pages)
Docket Numbers:
Docket No. 50-416
PDF File:
97-10071.pdf