2023-08167. CPV Three Rivers, LLC; Notice of Institution of Section 206 Proceeding and Refund Effective Date  

  • Start Preamble

    On March 31, 2023, the Commission issued an order in Docket No. EL23–47–000, pursuant to section 206 of the Federal Power Act (FPA), 16 U.S.C. 824e, instituting an investigation into whether CPV Three Rivers, LLC's proposed rate schedule (Rate Schedule) [1] for Reactive Supply and Voltage Control from Generation or Other Sources Service (Reactive Service), as defined in Schedule 2 of the PJM Interconnection, L.L.C. (PJM) Open Access Transmission Tariff (Tariff) [2] is unjust, unreasonable, unduly discriminatory or preferential, or otherwise unlawful and to establish a refund effective date. 3 CPV Three Rivers, LLC, 182 FERC ¶ 61,224 (2023).

    The refund effective date in Docket No. EL23–47–000, established pursuant to section 206(b) of the FPA, will be the date of publication of this notice in the Federal Register .

    Any interested person desiring to be heard in Docket No. EL23–47–000 must file a notice of intervention or motion to intervene, as appropriate, with the Federal Energy Regulatory Commission, in accordance with Rule 214 of the Commission's Rules of Practice and Procedure, 18 CFR 85.214 (2021), within 21 days of the date of issuance of the order.

    In addition to publishing the full text of this document in the Federal Register , the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page ( http://www.ferc.gov) using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission's Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID–19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659.

    The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the “eFile” link at http://www.ferc.gov. In lieu of electronic filing, you may submit a paper copy. Submissions sent via the U.S. Postal Service must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426. Submissions sent via any other carrier must be addressed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.

    Start Signature

    Dated: April 12, 2023.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    Footnotes

    1.  CPV Three Rivers, LLC, Rate Schedules and Tariffs, Section 2, Reactive Rates (0.0.0).

    Back to Citation

    2.   See PJM, Intra-PJM Tariffs, OATT, Schedule 2 (4.0.0). Three Rivers is a new seller that has not previously provided reactive power services to PJM and has no prior transactions and no prior customers. See Chehalis Power Generating, L.P., 152 FERC ¶ 61,050, at P 14 (2015) (“In order for a rate to be considered an initial rate, it must provide for a new service to a new customer.”) (citing Sw. Elec. Power Co., 39 FERC ¶ 61,099, at 61,293 (1987)).

    Back to Citation

    3.  The section 206 investigation will extend to any affiliate of Applicant with market-based rate authorization.

    Back to Citation

    [FR Doc. 2023–08167 Filed 4–17–23; 8:45 am]

    BILLING CODE 6717–01–P

Document Information

Published:
04/18/2023
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2023-08167
Pages:
23667-23667 (1 pages)
Docket Numbers:
Docket No. EL23-47-000
PDF File:
2023-08167.pdf