97-8401. Watts Bar Nuclear Plant, Unit 1; Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity For a Hearing  

  • [Federal Register Volume 62, Number 63 (Wednesday, April 2, 1997)]
    [Notices]
    [Pages 15733-15737]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-8401]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    [Docket No. 50-390]
    
    
    Watts Bar Nuclear Plant, Unit 1; Notice of Consideration of 
    Issuance of Amendment to Facility Operating License, Proposed No 
    Significant Hazards Consideration Determination, and Opportunity For a 
    Hearing
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an amendment to Facility Operating License No. 
    NPF-90, issued to the Tennessee Valley Authority (TVA or the licensee), 
    for operation of the Watts Bar Nuclear Plant (WBN), Unit 1 located in 
    Rhea County, Tennessee. This Notice supersedes a Notice placed in the 
    Federal Register on March 26, 1997 (62 FR 14469) on this matter.
        The proposed amendment would revise the Watts Bar Nuclear Plant 
    (WBN) Unit 1 Technical Specifications to increase the enrichment and 
    storage capacity of the spent fuel pool racks. The proposed 
    modification increases the WBN spent fuel storage capacity from 484 
    fuel assemblies to 1835 fuel assemblies. The initial enrichment of the 
    fuel to be stored in the spent fuel storage racks will be increased 
    from 3.5 weight percent (wt%) to 5.0 wt%. This modification would also 
    change the spacing of stored fuel assembly center-to-center spacing 
    from a nominal 10.72 inches to 10.375 inches in 24 PaR flux trap rack 
    modules and 8.972 inches in ten smaller burnup credit rack modules to 
    be installed peripherally along the south and west pool walls and in a 
    single 15 x 15 burnup credit rack to be installed in the cask pit.
        In addition to the above proposed revisions, two limiting 
    conditions for operation will be added to require that the combination 
    of initial enrichment and burnup of each spent fuel assembly to be 
    stored is in the acceptable region and to require boron concentration 
    of the cask pit to be greater than or equal to 2000 parts per million 
    (ppm) during fuel movement in the flooded cask pit. As an added 
    protection to the fuel stored in the cask pit area, the Technical 
    Requirements Manual (TRM) is being revised to require that an impact 
    shield be in place over the fuel when heavy loads are moved near or 
    across the cask pit area.
        The WBN Unit 1 Technical Specification Bases and the TRM would be 
    revised to support these changes.
        Before issuance of the proposed license amendment, the Commission 
    will have made findings required by the Atomic Energy Act of 1954, as 
    amended (the Act) and the Commission's regulations.
        The Commission has made a proposed determination that the amendment 
    request involves no significant hazards consideration. Under the 
    Commission's regulations in 10 CFR 50.92, this means that operation of 
    the facility in accordance with the proposed amendment would not (1) 
    involve a significant increase in the probability or consequences of an 
    accident previously evaluated; or (2) create the possibility of a new 
    or different kind of accident from any accident previously evaluated; 
    or (3) involve a significant reduction in a margin of safety. As 
    required by 10 CFR 50.91(a), the licensee has provided its analysis of 
    the issue of no significant hazards consideration, which is presented 
    below:
    
        The Nuclear Regulatory Commission has provided standards for 
    determining whether a significant hazards consideration exists (10 
    CFR 50.92(c)). A proposed amendment to an operating license for a 
    facility involves no significant hazards consideration if operation 
    of the facility in accordance with the proposed amendment would not 
    (1) involve a significant increase in the probability or 
    consequences of an accident previously evaluated; or (2) create the 
    possibility of a new or different kind of accident from any accident 
    previously evaluated; or (3) involve a significant reduction in a 
    margin of safety. Each standard is discussed below for the proposed 
    amendment.
        (1) Operation of the facility in accordance with the proposed 
    amendment would not involve a significant increase in the 
    probability or consequences of an accident previously evaluated.
        The following potential scenarios were considered:
        1. A spent fuel assembly drop.
        2. Drop of the transfer canal gate or the cask pit divider gate.
        3. A seismic event.
        4. Loss-of-cooling flow in the spent fuel pool.
        5. Installation activities.
        The effect of additional spent fuel pool storage cells fully 
    loaded with fuel on the
    
    [[Page 15734]]
    
    first four potential accident scenarios listed above has been 
    considered. It was concluded that after installation activities have 
    been completed, the presence of additional fuel in the pool does not 
    increase the probability of occurrence of these four events. Also, 
    based on evaluations of bulk pool temperature, rack seismic 
    responses, and refueling accidents, it is reasonable to conclude 
    that there is no significant increase in the consequences of these 
    events after installation is complete (See Reference 1). During the 
    installation activities, the following considerations support a 
    conclusion that neither the probability or consequences of these 
    four scenarios would be significantly increased.
        A spent fuel assembly cannot be dropped during installation of 
    the 24 Programmed and Remote System Corporation (PaR) flux trap rack 
    modules because this activity will take place before the end of 
    operating cycle one and there will be no spent fuel in the WBN pool 
    to be moved or shuffled. Before installing the ten smaller burnup 
    credit racks in the pool, some fuel will be moved to create a three 
    foot lateral free zone clearance from stored fuel. This would 
    involve a one-time movement of an estimated maximum of 225 fuel 
    assemblies, which is less tha[n] half the fuel movements during one 
    refueling outage. This does not significantly increase the 
    probability of dropping a fuel assembly, particularly when the many 
    administrative controls and physical limitations imposed on fuel 
    handling operations are considered. The fuel handling system 
    consists of equipment and structures utilized for safely 
    implementing refueling operations in accordance with requirements of 
    General Design Criteria 61 and 62 of 10 CFR 50, Appendix A. The 
    radiological dose consequences of dropping a 5.0 wt% fuel assembly 
    are different from the previous FSAR [Final Safety Analysis Report] 
    evaluation for the 3.5 wt% fuel assembly. The Beta and Gamma doses 
    decrease and the maximum thyroid dose increase is less than 9%. 
    Therefore, the change in calculated dose values is insignificant and 
    remains well within regulatory guidelines.
        It may be necessary to move the transfer canal gate and the cask 
    pit divider gate between their gated and stored positions during 
    installation of the burnup credit ``baby'' rack modules along the 
    south and west walls. During rack installation, the previously 
    mentioned three foot lateral free zone clearance to stored fuel 
    would exist. Therefore, no heavy load would be carried directly over 
    irradiated fuel during installation of the racks. There are numerous 
    design features which comply with NUREG-0612 to preclude these gates 
    from dropping on spent fuel. These features include design of the 
    lifting devices, design of the crane, and use of written procedures. 
    Also, the evaluation results for a gate drop on the racks indicates 
    that permanent damage to a fuel storage cell is limited to a maximum 
    depth of less than six inches below the top of the rack with no 
    effect on the subcriticality of fuel stored in adjacent cells. Based 
    on the foregoing, it is reasonable to conclude that gate handling 
    during the installation of the ``baby'' racks would not involve a 
    significant increase in the probability or consequences of an 
    accident.
        The probability of a seismic event is not related to 
    installation activities. The worst consequence resulting from a 
    seismic event during installation activities would occur during 
    handling of a rack. The consequences would be insignificant because 
    the Auxiliary Building crane is seismically qualified and both 
    handling equipment and operations meet the criteria of NUREG-0612. 
    Nevertheless, if the seismic event resulted in a rack drop, the 
    consequences are insignificant, i.e., localized damage to the pool 
    liner and a minor leak rate which would be small in comparison to 
    available installed makeup capacity. The cooling and shielding of 
    the spent fuel would remain unaffected. Also the racks being moved 
    are empty during installation and therefore, the criticality 
    consequences of seismic events are bounded by evaluations for loaded 
    racks.
        Rack installation activities cannot cause an accidental loss-of-
    cooling flow in the spent fuel pool. The vital components of the spent 
    fuel pool cooling and cleanup system (SFPCCS) are not located proximate 
    to the pool installation activities. Coolant flow may be deliberately 
    curtailed to facilitate installation of the ``baby'' racks directly 
    beneath the discharge piping in the southwest corner of the pool. The 
    effects of such an action would be readily minimized and made 
    inconsequential during the detailed installation planning phase by 
    selecting a time when decay heat input from stored fuel is relatively 
    constant. Also careful preplanning of the work would minimize out-of-
    service time and provide for intermittent coolant flow restart, if 
    necessary, to maintain acceptable bulk coolant temperatures. Similarly, 
    the effect of an independently initiated loss-of-coolant flow incident 
    on reracking activities can be easily accommodated by stopping work, as 
    necessary, to mitigate any adverse effects on the installation process. 
    The consequences of loss-of-cooling flow in the spent fuel pool during 
    installation are bounded by the analysis in Chapter 5 of the report 
    which includes the situation in which ``baby'' racks and the 15 x 15 
    cask pit rack are installed, and the pool is filled to capacity with 
    spent fuel.
        With regard to the actual installation activities, the existing 
    WBN TRM prohibits loads in excess of 2059 pounds from travel over 
    fuel assemblies in the storage pool and requires the associated 
    crane interlocks and physical stops be periodically demonstrated 
    operable. During installation, racks and associated handling tools 
    will be moved over the spent fuel pool, however there will be no 
    fuel in the pool when the 24 flux trap rack modules are installed. A 
    three foot lateral free zone clearance from stored spent fuel will 
    be maintained during installation of the ten smaller burnup credit 
    rack modules. Installation work in the spent fuel pit area will be 
    controlled and performed in strict accordance with specific written 
    instructions.
        NUREG-0612 states that in lieu of providing a single failure-
    proof crane system, the control-of-heavy-loads guidelines can be 
    satisfied by establishing that the potential for a heavy load drop 
    is extremely small. Storage rack movements to be accomplished with 
    the WBN Auxiliary Building crane will conform with NUREG-0612 
    guidelines in that the probability of a drop of a storage rack is 
    extremely small. The crane has a tested capacity of 125 tons. The 
    maximum weight of any existing, replacement, or new storage rack and 
    its associated handling tool is less than 20 tons. Therefore, there 
    is ample safety factor margin for movements of the storage racks by 
    the Auxiliary Building crane. Special lifting devices, which have 
    redundancy or a rated capacity sufficient to maintain adequate 
    safety factors, will also be utilized in the movements of the 
    storage racks. In accordance with NUREG-0612, Appendix B, the safety 
    margin ensures that the probability of a load drop is extremely low.
        Future load travel over fuel stored in a rack specifically 
    designed for the cask loading area of the cask pit will be 
    prohibited unless an impact shield, which has been specifically 
    designed for this purpose, is covering the area. Loads that are 
    permitted when the shield is in place must meet analytically 
    determined weight, travel height, and cross-sectional area criteria 
    that preclude penetration of the shield. A Technical Requirement 
    (TR) has been proposed that incorporates the previously mentioned 
    load criteria.
        Also a rack change-out sequence is being developed that 
    addresses removal of the existing racks, movement of the new racks 
    into the Auxiliary Building, initial staging on the refueling floor, 
    and final installation in the pool. The change-out sequence 
    objectives include establishing lift heights, travel distances, and 
    number of lifts to be as low as reasonably achievable. Accordingly, 
    it is concluded that the proposed installation activities will not 
    significantly increase the probability of a load-handling accident. 
    The consequences of a load-handling accident are unaffected by the 
    proposed installation activities.
        The consequences of a spent fuel assembly drop were evaluated, 
    and it was determined that the racks will not be distorted such that 
    the racks would not perform their safety function. The criticality 
    acceptance criterion, Keff less than or equal to 0.95, is not 
    violated, and the calculated doses are well within 10 CFR Part 100 
    guidelines. The radiological consequences of the fuel assembly drop 
    accident evaluated for WBN, have changed, however, the changes do 
    not involve a significant increase in consequences and are well 
    within the 10 CFR 100 requirements.
        A TRM change has been proposed that would permit the transfer-
    canal gate and the divider gate for the cask pit to travel over fuel 
    assemblies in the spent fuel pool during movement between their 
    gated and stored position. Rack damage is restricted to an area 
    above the active fuel region, therefore, neither criticality nor 
    radiological concerns exist.
        The consequences of a seismic event have been evaluated. The 
    replacement racks are
    
    [[Page 15735]]
    
    designed and fabricated and the new racks will be fabricated to meet 
    the requirements of applicable portions of the NRC regulatory guides 
    and published standards. Design margins have been provided for rack 
    tilting, deflection, and movement such that the racks do not impact 
    each other or the spent fuel pool walls in the active fuel region 
    during the postulated seismic events. The free-standing racks will 
    maintain their integrity during and after a seismic event. The fuel 
    assemblies also remain intact and therefore no criticality concerns 
    exist.
        The spent fuel pool system is a passive system with the 
    exception of the fuel pool cooling train and heating, ventilating, 
    and air-conditioning (HVAC) equipment. Redundancies in the cooling 
    train and HVAC hardware are not reduced by the planned fuel storage 
    modification. The potential increased heat load resulting from any 
    additional storage of spent fuel is well within the existing system 
    cooling capacity. Therefore, the probability of occurrence or 
    malfunction of safety equipment leading to the loss-of-cooling flow 
    in the spent fuel pool is not significantly affected. Furthermore, 
    the consequences of this type incident are not significantly 
    increased from previously evaluated cooling system loss of flow 
    malfunctions. Thermal-hydraulic scenarios assume the reracked pool 
    is approximately 90% full with spent fuel assemblies. From this 
    starting point, the remaining storage capacity is utilized by 
    analyzing both normal and unplanned full core off loads using 
    conservative assumptions and previously established methods. 
    Calculated values include maximum pool water bulk temperature, 
    coincident maximum pool water local temperature, the maximum fuel 
    cladding temperature, time-to-boil after loss-of-cooling paths, and 
    the effect of flow blockage in a storage cell.
        Although the proposed modification increases the pool heat load, 
    results from the above analyses yield a maximum bulk temperature 
    less than 160 degrees Fahrenheit which is below the bulk boiling 
    temperature. Also the maximum local water temperature is below 
    nucleate boiling condition values. Associated results from 
    corresponding loss-of-cooling evaluations give minimums of 5.3 hours 
    before boiling begins and 45 hours before the pool water level drops 
    to the minimum required for shielding spent fuel.
        This is sufficient time to begin utilization of available 
    alternate sources of makeup cooling water. Also, the effect of the 
    increased thermal loading on the pool structure, associated cooling 
    system, and components was evaluated and determined to establish an 
    acceptable design basis with the new storage configuration. No 
    modifications were necessary because of the increased temperature.
        (2) Operation of the facility in accordance with the proposed 
    amendment would not create the possibility of a new or different 
    kind of accident from any accident previously analyzed.
        The proposed modification has been evaluated in accordance with 
    the guidance of the NRC position paper entitled, ``OT Position for 
    Review and Acceptance of Spent-Fuel Storage and Handling 
    Applications'', appropriate NRC regulatory guidelines; appropriate 
    NRC standard review plans; and appropriate industry codes and 
    standards. Proven analytical technology was used in designing the 
    planned fuel storage expansion and will be utilized in the 
    installation process. Basic reracking technology has been developed 
    and demonstrated in applications for fuel pool capacity increases 
    that have already received NRC staff approval.
        Proposed TSs for the spent fuel storage racks use burnup credit 
    and fuel assembly administrative placement restrictions for 
    criticality control. These restrictions are described in the 
    proposed change to the design features section of the TSs by 
    reference to the Spent Fuel Pool Modifications report. Additional 
    evaluations were required to ensure that the criticality criterion, 
    keff less than or equal to 0.95, is maintained. These include 
    evaluation for the abnormal placement of unirradiated (fresh) fuel 
    assemblies of 5.0 wt% enrichment into a storage cell location 
    designed for lower enrichment or irradiated fuel. Soluble boron, for 
    which credit is permitted under these abnormal conditions, ensures 
    that reactivity is maintained substantially less than the design 
    requirement. For example, if the PaR flux trap racks are 
    inadvertently all loaded with fresh assemblies of the maximum 5.0 
    wt% fuel instead of observing the 3.8 wt% and 6.75 MWD/KgU controls, 
    the worth of the 2000 ppm borated water is sufficient to lower the 
    keff of the storage racks to 0.83. The existing and proposed 
    TSs require boron concentration in the pool and cask pit to be 
    greater than or equal to 2000 ppm during fuel movement. An 
    analytical determination of the reactivity worth of 2000 ppm borated 
    water in the spent fuel storage pool predicted the change in 
    keff to be approximately 17 percent keff. Although no 
    credit for soluble boron was proposed in the TSs, it was also 
    determined by an independent calculation that a minimum 
    concentration of 520 ppm soluble boron allows the unrestricted 
    storage of 5.0 wt% enriched fuel in the PaR flux trap racks.
        The Holtec-designed peripheral ``baby'' racks and the 15 x 15 
    racks in the cask loading area can safely and conservatively store 
    fuel of 5 wt% initial enrichment burned to 41 MWD/kgU or lower 
    enriched fuel with lower burnup, i.e., fuel of equivalent 
    reactivity. Evaluations have confirmed that, for the abnormal 
    placement of a fresh fuel assembly of 5.0 wt% in these racks, the 
    criticality criterion is maintained with the existing and proposed 
    TS requirements of 2000 ppm soluble boron.
        Although these changes required addressing additional aspects of 
    a previously analyzed accident, the possibility of a previously 
    unanalyzed accident is not created.
        The impact shield design together with its attendant 
    administrative controls and NUREG-0612 heavy load lift compliance, 
    renders the possibility of a heavy load drop on fuel as not credible 
    in accordance with the NUREG-0612 single-failure-proof criteria. 
    Accordingly, since this particular part of the proposed reracking 
    modification is not a change that could malfunction by a new single 
    failure, the movement of heavy loads over the cask pit does not 
    create the possibility of a new or different kind of accident.
        It is therefore concluded that the proposed reracking does not 
    create the possibility of a new or different kind of accident from 
    any previously analyzed.
        (3) Operation of the facility in accordance with the proposed 
    amendment would not involve a significant reduction in a margin of 
    safety.
        The design and technical review process applied to the reracking 
    modification included addressing the following areas:
        1. Nuclear criticality considerations.
        2. Thermal-hydraulic considerations.
        3. Mechanical, material, and structural considerations.
        The established acceptance criterion for criticality is that the 
    neutron multiplication factor shall be less than or equal to 0.95, 
    including all uncertainties. The results of the criticality analyses 
    for the rack designs demonstrate that this criterion is satisfied. 
    The methods used in the criticality analysis conform to the 
    applicable portions of NRC guidance and industry codes, standards, 
    and specifications. In meeting the acceptance criteria for 
    criticality in the spent fuel pool and the cask loading area, such 
    that keff is always less than 0.95 at a 95/95 percent 
    probability tolerance level, the proposed amendment does not involve 
    a significant reduction in the margin of safety for nuclear 
    criticality.
        Conservative methods and assumptions were used to calculate the 
    maximum fuel temperature and the increase in temperature of the 
    water in the spent fuel pit area. The thermal-hydraulic evaluation 
    used methods previously employed. The proposed storage modification 
    will increase the heat load in the spent fuel pool, but the 
    evaluation shows that the existing spent fuel cooling system will 
    maintain the bulk pool water temperature at or below 160 degrees 
    Fahrenheit. Thus it is demonstrated that the worst-case peak value 
    of the pool bulk temperature is considerably lower than the bulk 
    boiling temperature. Evaluation also shows that maximum local water 
    temperatures along the hottest fuel assembly are below the nucleate 
    boiling condition value. Thus, there is no significant reduction in 
    the margin of safety for thermal hydraulic or spent fuel cooling 
    considerations.
        The mechanical, material, and structural design of the spent 
    fuel racks is in accordance with applicable portions of NRC's 
    position in ``OT Position for Review and Acceptance of Spent-Fuel 
    Storage and Handling Applications,'' dated April 14, 1978 (as 
    modified January 18, 1979), as well as other applicable NRC guidance 
    and industry codes. The primary safety function of the spent fuel 
    racks is to maintain the fuel assemblies in a safe configuration 
    through normal and abnormal loading conditions. Abnormal loadings 
    that have been evaluated with acceptable results and discussed 
    previously include the effect of an earthquake and the impact 
    because of the drop of a fuel assembly. The rack materials used are 
    compatible with the fuel assemblies and the environment in the spent 
    fuel pool.
    
    [[Page 15736]]
    
    The structural design for the new racks provides tilting, 
    deflection, and movement margins such that the racks do not impact 
    each other or the spent fuel pit walls in the active fuel region 
    during the postulated seismic events. Also the spent fuel assemblies 
    themselves remain intact and no criticality concerns exist. In 
    addition, finite element analysis methods were used to evaluate the 
    continued structural acceptability of the spent fuel pit. The 
    analysis was performed in accordance with ``Building Code 
    Requirements for Reinforced Concrete,'' (ACI 318-63,77). Therefore, 
    with respect to mechanical, material, and structural considerations, 
    there is no significant reduction in a margin of safety.
    
    Summary
    
        Based on the above analysis, TVA has determined that operation 
    of WBN, in accordance with the proposed amendment, would not: (1) 
    involve a significant increase in the probability of consequences of 
    an accident previously evaluated, (2) create the possibility of a 
    new or different kind of accident from any accident previously 
    evaluated, or (3) involve a significant reduction in a margin of 
    safety. Therefore, operations of WBN in accordance with the proposed 
    amendments as described do not involve significant hazard 
    considerations as defined in 10 CFR 50.92 and that the criteria of 
    10 CFR 50.91 have accordingly been met.
    
        The NRC staff has reviewed the licensee's analysis and, based on 
    this review, it appears that the three standards of 10 CFR 50.92(c) are 
    satisfied. Therefore, the NRC staff proposes to determine that the 
    amendment request involves no significant hazards consideration.
        The Commission is seeking public comments on this proposed 
    determination. Any comments received within thirty (30) days after the 
    date of publication of this notice will be considered in making any 
    final determination.
        Normally, the Commission will not issue the amendment until the 
    expiration of the 30-day notice period. However, should circumstances 
    change during the notice period, such that failure to act in a timely 
    way would result, for example, in derating or shutdown of the facility, 
    the Commission may issue the license amendment before the expiration of 
    the 30-day notice period, provided that its final determination is that 
    the amendment involves no significant hazards consideration. The final 
    determination will consider all public and State comments received. 
    Should the Commission take this action, it will publish in the Federal 
    Register a notice of issuance and provide for opportunity for a hearing 
    after issuance. The Commission expects that the need to take this 
    action will occur very infrequently.
        Written comments may be submitted by mail to the Rules Review and 
    Directives Branch, Division of Freedom of Information and Publications 
    Services, Office of Administration, U.S. Nuclear Regulatory Commission, 
    Washington, DC 20555-0001, and should cite the publication date and 
    page number of this Federal Register notice. Written comments may also 
    be delivered to Room 6D22, Two White Flint North, 11545 Rockville Pike, 
    Rockville Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. 
    Copies of written comments received may be examined at the NRC Public 
    Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC.
        The filing of requests for hearing and petitions for leave to 
    intervene is discussed below.
        By May 2, 1997, the licensee may file a request for a hearing with 
    respect to issuance of the amendment to the subject facility operating 
    license and any person whose interest may be affected by this 
    proceeding and who wishes to participate as a party in the proceeding 
    must file a written request for a hearing and a petition for leave to 
    intervene. Requests for a hearing and a petition for leave to intervene 
    shall be filed in accordance with the Commission's ``Rules of Practice 
    for Domestic Licensing Proceedings'' in 10 CFR Part 2. Interested 
    persons should consult a current copy of 10 CFR 2.714 which is 
    available at the Commission's Public Document Room, the Gelman 
    Building, 2120 L Street, NW., Washington, DC and at the local public 
    document room located at the Chattanooga-Hamilton County Library, 1001 
    Broad Street, Chattanooga, Tennessee 37402. If a request for a hearing 
    or petition for leave to intervene is filed by the above date, the 
    Commission or an Atomic Safety and Licensing Board, designated by the 
    Commission or by the Chairman of the Atomic Safety and Licensing Board 
    Panel, will rule on the request and/or petition; and the Secretary or 
    the designated Atomic Safety and Licensing Board will issue a notice of 
    hearing or an appropriate order.
        As required by 10 CFR 2.714, a petition for leave to intervene 
    shall set forth with particularity the interest of the petitioner in 
    the proceeding, and how that interest may be affected by the results of 
    the proceeding. The petition should specifically explain the reasons 
    why intervention should be permitted with particular reference to the 
    following factors: (1) The nature of the petitioner's right under the 
    Act to be made a party to the proceeding; (2) the nature and extent of 
    the petitioner's property, financial, or other interest in the 
    proceeding; and (3) the possible effect of any order which may be 
    entered in the proceeding on the petitioner's interest. The petition 
    should also identify the specific aspect(s) of the subject matter of 
    the proceeding as to which petitioner wishes to intervene. Any person 
    who has filed a petition for leave to intervene or who has been 
    admitted as a party may amend the petition without requesting leave of 
    the Board up to 15 days prior to the first prehearing conference 
    scheduled in the proceeding, but such an amended petition must satisfy 
    the specificity requirements described above.
        Not later than 15 days prior to the first prehearing conference 
    scheduled in the proceeding, a petitioner shall file a supplement to 
    the petition to intervene which must include a list of the contentions 
    which are sought to be litigated in the matter. Each contention must 
    consist of a specific statement of the issue of law or fact to be 
    raised or controverted. In addition, the petitioner shall provide a 
    brief explanation of the bases of the contention and a concise 
    statement of the alleged facts or expert opinion which support the 
    contention and on which the petitioner intends to rely in proving the 
    contention at the hearing.
        The petitioner must also provide references to those specific 
    sources and documents of which the petitioner is aware and on which the 
    petitioner intends to rely to establish those facts or expert opinion. 
    Petitioner must provide sufficient information to show that a genuine 
    dispute exists with the applicant on a material issue of law or fact. 
    Contentions shall be limited to matters within the scope of the 
    amendment under consideration. The contention must be one which, if 
    proven, would entitle the petitioner to relief. A petitioner who fails 
    to file such a supplement which satisfies these requirements with 
    respect to at least one contention will not be permitted to participate 
    as a party.
        Those permitted to intervene become parties to the proceeding, 
    subject to any limitations in the order granting leave to intervene, 
    and have the opportunity to participate fully in the conduct of the 
    hearing, including the opportunity to present evidence and cross-
    examine witnesses.
        If a hearing is requested, the final determination will serve to 
    decide when the hearing is held.
        If the final determination is that the amendment request involves 
    no significant hazards consideration, the Commission may issue the 
    amendment and make it immediately effective,
    
    [[Page 15737]]
    
    notwithstanding the request for a hearing. Any hearing held would take 
    place after issuance of the amendment.
        If the final determination is that the amendment request involves a 
    significant hazards consideration, any hearing held would take place 
    before the issuance of any amendment.
        A request for a hearing or a petition for leave to intervene must 
    be filed with the Secretary of the Commission, U.S. Nuclear Regulatory 
    Commission, Washington, DC 20555-0001, Attention: Docketing and 
    Services Branch, or may be delivered to the Commission's Public 
    Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC, 
    by the above date. Where petitions are filed during the last 10 days of 
    the notice period, it is requested that the petitioner promptly so 
    inform the Commission by a toll-free telephone call to Western Union at 
    1-(800) 248-5100 (in Missouri 1-(800) 342-6700). The Western Union 
    operator should be given Datagram Identification Number N1023 and the 
    following message addressed to Mr. Frederick J. Hebdon: petitioner's 
    name and telephone number, date petition was mailed, plant name, and 
    publication date and page number of this Federal Register notice. A 
    copy of the petition should also be sent to the Office of the General 
    Counsel, U.S. Nuclear Regulatory Commission, Washington, DC, and to 
    General Counsel, Tennessee Valley Authority, ET 10H, 400 West Summit 
    Hill Drive, Knoxville, Tennessee 37902, attorney for the licensee.
        Nontimely filings of petitions for leave to intervene, amended 
    petitions, supplemental petitions and/or requests for hearing will not 
    be entertained absent a determination by the Commission, the presiding 
    officer or the presiding Atomic Safety and Licensing Board that the 
    petition and/or request should be granted based upon a balancing of the 
    factors specified in 10 CFR 2.714(a)(1)(i)-(v) and 2.714(d).
        The Commission hereby provides notice that this is a proceeding on 
    an application for a license amendment falling within the scope of 
    section 134 of the Nuclear Waste Policy Act of 1982 (NWPA), 42 U.S.C. 
    10154. Under section 134 of the NWPA, the Commission, at the request of 
    any party to the proceeding, must use hybrid hearing procedures with 
    respect to ``any matter which the Commission determines to be in 
    controversy among the parties.'' The hybrid procedures in section 134 
    provide for oral argument on matters in controversy, preceded by 
    discovery under the Commission's rules, and the designation, following 
    argument, of only those factual issues that involve a genuine and 
    substantial dispute, together with any remaining questions of law, to 
    be resolved in an adjudicatory hearing. Actual adjudicatory hearings 
    are to be held on only those issues found to meet the criteria of 
    section 134 and set for hearing after oral argument.
        The Commission's rules implementing section 134 of the NWPA are 
    found in 10 CFR Part 2, Subpart K, ``Hybrid Hearing Procedures for 
    Expansion of Spent Nuclear Fuel Storage Capacity at Civilian Nuclear 
    Power Reactors'' (published at 50 FR 41670, October 15, 1985) to 10 CFR 
    2.1101 et seq. Under those rules, any party to the proceeding may 
    invoke the hybrid hearing procedures by filing with the presiding 
    officer a written request for oral argument under 10 CFR 2.1109. To be 
    timely, the request must be filed within 10 days of an order granting a 
    request for hearing or petition to intervene. (As outlined above, the 
    Commission's rules in 10 CFR Part 2, Subpart G, and 2.714 in 
    particular, continue to govern the filing of requests for a hearing or 
    petitions to intervene, as well as the admission of contentions.) The 
    presiding officer shall grant a timely request for oral argument. The 
    presiding officer may grant an untimely request for oral argument only 
    upon showing of good cause by the requesting party for the failure to 
    file on time and after providing the other parties an opportunity to 
    respond to the untimely request. If the presiding officer grants a 
    request for oral argument, any hearing held on the application shall be 
    conducted in accordance with the hybrid hearing procedures. In essence, 
    those procedures limit the time available for discovery and require 
    that an oral argument be held to determine whether any contentions must 
    be resolved in adjudicatory hearing. If no party to the proceedings 
    requests oral argument, or if all untimely requests for oral argument 
    are denied, then the usual procedures in 10 CFR Part 2, Subpart G, 
    apply.
        For further details with respect to this action, see the 
    application for amendment dated, October 23, 1996, as supplemented on 
    December 11, 1996, January 31, February 10 and 24 and March 11, 1997 
    which is available for public inspection at the Commission's Public 
    Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC, 
    and at the local public document room, located at the Chattanooga-
    Hamilton County Library, 1001 Broad Street, Chattanooga, Tennessee.
    
        Dated at Rockville, Maryland, this 27th day of March 1997.
    
        For the Nuclear Regulatory Commission.
    Robert E. Martin,
    Sr. Project Manager, Project Directorate II-3, Division of Reactor 
    Projects--I/II, Office of Nuclear Reactor Regulation.
    [FR Doc. 97-8401 Filed 4-1-97; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
04/02/1997
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
97-8401
Pages:
15733-15737 (5 pages)
Docket Numbers:
Docket No. 50-390
PDF File:
97-8401.pdf