94-9474. El Paso Natural Gas Company, et al.; Natural Gas Certificate Filings  

  • [Federal Register Volume 59, Number 76 (Wednesday, April 20, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-9474]
    
    
    [[Page Unknown]]
    
    [Federal Register: April 20, 1994]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP94-329-000, et al.]
    
     
    
    El Paso Natural Gas Company, et al.; Natural Gas Certificate 
    Filings
    
    April 12, 1994.
        Take notice that the following filings have been made with the 
    Commission:
    
    1. El Paso Natural Gas Co.
    
    [Docket No. CP94-329-000]
    
        Take notice that on April 1, 1994, El Paso Natural Gas Company (El 
    Paso), Post Office Box 1492, El Paso, Texas 79978, filed an application 
    at Docket No. CP94-329-000, pursuant to section 7(c) of the Natural Gas 
    Act (NGA) for a certificate of public convenience and necessity 
    authorizing El Paso to construct and operate its North/South Transfer 
    Project. El Paso also requests a determination that the costs for the 
    North/South Transfer Project would be rolled into El Paso's cost-of-
    service as a part of the first system-wide general rate proceeding 
    following the in-service date of the proposed facilities, all as more 
    fully set forth in the application which is on file with the Commission 
    and open to public inspection.
        El Paso requests expeditious authorization of the North/South 
    Transfer Project since it has been designed to enhance El Paso's system 
    operating flexibility and to contribute directly to maximum system 
    utilization, by providing enhanced multi-directional flow operations. 
    El Paso states that construction of the North/South Transfer Project 
    would therefore facilitate El Paso's ability to react quickly to 
    changing market requirements on both the demand and supply sides on its 
    system.
        El Paso states that while its system has always had to respond to 
    changing markets prior to open-access, El Paso could optimize the 
    sequencing of supplies to maximize system efficiency. El Paso states 
    that it controls neither the market nor the supply and must stand ready 
    to handle a wide variety of combinations of supply and demand. El Paso 
    further states that during the last five years, the California market 
    has been evolving in a new direction which has resulted in fundamental 
    changes in the demand patterns on El Paso's transmission system. El 
    Paso states that the day-to-day changes in system loading has created a 
    need for additional system flexibility.
        El Paso also states that the market changes are caused, in part, by 
    several events. First, the demand for gas deliveries at the Topock 
    Delivery Point by El Paso's California customers has decreased as a 
    result of the expansion of Pacific Gas Transmission Company's system to 
    move Canadian gas supplies into northern California, the capacity 
    available through the Kern River Gas Transmission Company system, and 
    the capacity available from the Transwestern Pipeline Company 
    (Transwestern) system at Topock (referred to as Needles by 
    Transwestern). El Paso states that if prices for gas in the southwest 
    are high, the California market shifts to the Canadian supplies. This 
    decrease in demand at Topock imposes an external constraint on El 
    Paso's North System which results in capacity allocations in the San 
    Juan Basin supply area. Second, El Paso states that the continuing 
    buildup of supply in the San Juan Basin has made that area's gas 
    production a more economically attractive supply source for El Paso's 
    customers served by the South System. Third, El Paso states that 
    producers in the Permian and Anadarko Basins have found markets within 
    Texas and to the east, unloading El Paso's system. Of El Paso's supply 
    sources, the supplies in the Permian and Anadarko Basins are closest to 
    the eastern markets and can easily swing off El Paso's system in very 
    short notice. El Paso states that the California market changes, the 
    ability for producers in all supply basins to swing off El Paso's 
    system on a day-to-day basis, and El Paso's need for system flexibility 
    to quickly respond to the day-to-day market and supply changes support 
    the need to transfer gas between the two systems and collectively 
    constitutes the driving forces behind the North/South Transfer Project.
        El Paso further states that given these developments in the market 
    and their direct impact on El Paso's system, El Paso has recognized 
    that its existing system can better serve the market if modified to 
    facilitate operation in a multi-directional manner. El Paso proposes to 
    construct and operate approximately 98.4 miles of 30-inch pipeline 
    (``North/South Transfer Line''), with appurtenances, to parallel the 
    existing 30-inch Havasu Crossover Line and proposes to modify the 
    operation of the existing Dutch Flat Compressor Station, all located 
    near the western end of El Paso's North and South Systems. El Paso 
    states that the approximate cost of construction of the North/South 
    Transfer Project is $62,364,000, with a resultant third year cost of 
    service of only approximately $10.4 million.
        El Paso states that its proposal would provide El Paso with the 
    capability to transfer an additional 468.6 Mmcf per day of natural gas 
    from El Paso's North System to its South System. El Paso further states 
    that the construction of these facilities, together with the operation 
    of the existing system in a multi-directional manner would permit El 
    Paso to enhance system flexibility, maximize system utilization, and 
    thereby more quickly respond to ever-changing market and supply 
    conditions. El Paso also states that firm delivery capacity would not 
    be increased by the facilities.
        El Paso also requests a determination from the Commission granting 
    El Paso approval to roll-in the costs associated with the North/South 
    Transfer Project into its total cost of service. El Paso states that 
    when the facilities are placed in-service, El Paso would charge its 
    then current and effective Part 284 rates. El Paso further states that 
    it would roll-in the cost associated with the North/South Transfer 
    Project in the first system-wide general rate proceeding initiated 
    following the in-service date of the North/South Transfer Project.
        El Paso asserts that the proposed North/South Transfer Project 
    benefits producers, end-users, and shippers utilizing El Paso's system. 
    El Paso further asserts that producers in any basin would be able to 
    get their gas more reliably to markets served by El Paso's system and 
    would be less likely to be subject to capacity allocations and shut-
    ins. Shippers will also have more flexibility in moving gas to their 
    new markets and greater certainty of supply sources. El Paso states 
    that as a result of these circumstances, end-users would benefit from a 
    further increase in reliability of gas supplies and deliveries.
        Comment date: May 3, 1994, in accordance with Standard Paragraph F 
    at the end of this notice.
    
    2. Columbia Gas Transmission Corporation
    
    [Docket No. CP94-332-000]
    
        Take notice that on April 4, 1994, Columbia Gas Transmission 
    Corporation (Columbia), 1700 MacCorkle Avenue, S.E., Charleston, West 
    Virginia 25314, filed in Docket No. CP94-332-000 a petition for 
    declaratory order requesting that the Commission clarify whether 
    certain construction falls within the provisions of Sec. 2.55(b) of the 
    Commission's General Policy and Interpretations for replacement of 
    facilities, all as more fully set forth in the petition which is on 
    file with the Commission and open to public inspection.
        Columbia states that the past practice of ``telescoping'' pipelines 
    in storage fields, the sizing of pipelines in proportion to the gas 
    flow, now impairs Columbia's ability to effectively clean and inspect 
    these facilities. Columbia further asserts that it has experienced 
    failures in its storage pipeline system due to external and internal 
    corrosion of the facilities.
        Columbia states that, in order to correct the corrosion problem, it 
    has initiated a program to install permanent launching and receiving 
    facilities in parts of its existing storage field pipeline system. 
    Columbia further states that in certain storage fields it would be 
    necessary to replace short segments of the telescoped pipeline to 
    provide for a uniform pipe size between launcher and receiver 
    locations. Columbia asserts that uniform pipe size would eliminate the 
    need for multiple launcher and receiver locations thereby enabling the 
    pigging system to be more effective.
        Columbia states that it believes that this replacement construction 
    constitutes the replacement of facilities as envisioned by Sec. 2.55(b) 
    of the Commission's General Policy and Interpretations. Columbia 
    asserts that the ``a substantially equivalent designed delivery 
    capacity as the facilities being replaced'' criteria in Sec. 2.55(b) is 
    not accompanied by further definition that would indicate how the 
    Commission would interpret the phrase. Columbia further asserts that 
    its review of relevant Commission decisions did not clarify the phrase 
    with sufficient precision to eliminate the need to seek NGA section 
    7(c) certificate authorization. Columbia states that it has filed for 
    authorization to construct these type of facilities at the Medina 
    Storage Field in Docket No. CP94-252-000 and at the Weaver Storage 
    Field in Docket No. CP94-320-000.
        Columbia requests that the Commission issue a declaratory order 
    clarifying that Sec. 2.55(b) of the Commission's General Policy and 
    Interpretations may be interpreted to include the replacement of 
    facilities of the type described above and described in more detail in 
    the referenced applications filed by Columbia in regard to the Medina 
    and Weaver Storage Fields.
        Comment date: May 3, 1994, in accordance with the first paragraph 
    of Standard Paragraph F at the end of this notice.
    
    3. Transcontinental Gas Pipe Line Corp.
    
    [Docket No. CP94-348-000]
    
        Take notice that on April 11, 1994, Transcontinental Gas Pipe Line 
    Corporation (TGPL), P.O. Box 1396, Houston, Texas 77251-1396, filed in 
    Docket No. CP94-348-000, a request pursuant to Secs. 157.205 and 
    157.212 of the Commission's Regulations under the Natural Gas Act (18 
    CFR 157.205 and 157.212) for authorization to operate an existing 
    delivery tap to Piedmont Natural Gas Company, Inc. (Piedmont) on TGPL's 
    Maiden Lateral in Lincoln County, North Carolina under the blanket 
    certificate issued in Docket No. CP82-426-000, pursuant to section 7(c) 
    of the Natural Gas Act, all as more fully set forth in the request 
    which is on file with the Commission and open to public inspection.
        TGPL proposes to operate an existing 4-inch delivery tap, located 
    at milepost 0.18 on TGPL's Maiden Lateral in Lincoln County, North 
    Carolina, which will be used by Piedmont to receive up to 750 Mcf of 
    gas per day into its distribution system on a firm and interruptible 
    basis. TGPL asserts it will not alter the authorized firm 
    transportation service entitlement for Piedmont. TGPL states it has 
    sufficient system delivery flexibility to accomplish these deliveries 
    without any detriment to its other customers. TGPL indicates that the 
    operation of this delivery point is not prohibited by its FERC Gas 
    Tariff.
        TGPL states that the facilities necessary to make this tap 
    operational will consist of tie-in piping between the existing tap and 
    Piedmont's facilities. TGPL further states that this tie-in piping will 
    be constructed pursuant to Sec. 2.55(a) of the Commission's regulations 
    and will cost an estimated $10,000.
        Comment date: May 27, 1994, in accordance with Standard Paragraph G 
    at the end of this notice.
    
    Standard Paragraphs
    
        F. Any person desiring to be heard or to make any protest with 
    reference to said application should on or before the comment date, 
    file with the Federal Energy Regulatory Commission, Washington, DC 
    20426, a motion to intervene or a protest in accordance with the 
    requirements of the Commission's Rules of Practice and Procedure (18 
    CFR 385.214 or 385.211) and the Regulations under the Natural Gas Act 
    (18 CFR 157.10). All protests filed with the Commission will be 
    considered by it in determining the appropriate action to be taken but 
    will not serve to make the protestants parties to the proceeding. Any 
    person wishing to become a party to a proceeding or to participate as a 
    party in any hearing therein must file a motion to intervene in 
    accordance with the Commission's Rules.
        Take further notice that, pursuant to the authority contained in 
    and subject to the jurisdiction conferred upon the Federal Energy 
    Regulatory Commission by sections 7 and 15 of the Natural Gas Act and 
    the Commission's Rules of Practice and Procedure, a hearing will be 
    held without further notice before the Commission or its designee on 
    this application if no motion to intervene is filed within the time 
    required herein, if the Commission on its own review of the matter 
    finds that a grant of the certificate and/or permission and approval 
    for the proposed abandonment are required by the public convenience and 
    necessity. If a motion for leave to intervene is timely filed, or if 
    the Commission on its own motion believes that a formal hearing is 
    required, further notice of such hearing will be duly given.
        Under the procedure herein provided for, unless otherwise advised, 
    it will be unnecessary for applicant to appear or be represented at the 
    hearing.
        G. Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Sec. 157.205 of the 
    Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the 
    request. If no protest is filed within the time allowed therefor, the 
    proposed activity shall be deemed to be authorized effective the day 
    after the time allowed for filing a protest. If a protest is filed and 
    not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to section 7 of the Natural Gas Act.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 94-9474 Filed 4-19-94; 8:45 am]
    BILLING CODE 6717-01-P
    
    
    

Document Information

Published:
04/20/1994
Department:
Energy Department
Entry Type:
Uncategorized Document
Document Number:
94-9474
Dates:
May 3, 1994, in accordance with Standard Paragraph F at the end of this notice.
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: April 20, 1994, Docket No. CP94-329-000, et al.