98-10447. Northern Natural Gas Company; Notice of Request Under Blanket Authorization  

  • [Federal Register Volume 63, Number 76 (Tuesday, April 21, 1998)]
    [Notices]
    [Page 19721]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 98-10447]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    [Docket No. CP98-345-000]
    
    
    Northern Natural Gas Company; Notice of Request Under Blanket 
    Authorization
    
    April 15, 1998.
        Take notice that on April 10, 1998, Northern Natural Gas Company 
    (Northern), 1111 South 103rd Street, Omaha, Nebraska 68124-1000, filed 
    in Docket No. CP98-345-000 a request pursuant to Sections 157.205 and 
    157.212 of the Commission's Regulations under the Natural Gas Act (18 
    CFR 157.205, 157.212) for authorization to install and operate a new 
    delivery point in Wright County, Minnesota, to accommodate natural gas 
    deliveries to UtiliCorp United Inc. (UCU), under Northern's blanket 
    certificate issued in Docket No. CP82-401-000 pursuant to Section 7 of 
    the Natural Gas Act, all as more fully set forth in the request that is 
    on file with the Commission and open to public inspection.
        Northern states that the proposed volumes to be delivered for UCU 
    at the proposed delivery point are 2 MMBtu on a peak day and 120 MMBtu 
    on an annual basis. Northern also states that the service will be 
    provided to UCU pursuant to currently effective throughput service 
    agreement(s). Northern estimates the cost of constructing the proposed 
    delivery point to be $6,415.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 98-10447 Filed 4-20-98; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
04/21/1998
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
98-10447
Pages:
19721-19721 (1 pages)
Docket Numbers:
Docket No. CP98-345-000
PDF File: