94-9972. Northern Natural Gas Co.; Request Under Blanket Authorization
[Federal Register Volume 59, Number 80 (Tuesday, April 26, 1994)]
[Unknown Section]
[Page 0]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 94-9972]
[[Page Unknown]]
[Federal Register: April 26, 1994]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. CP94-356-000]
Northern Natural Gas Co.; Request Under Blanket Authorization
April 20, 1994.
Take notice that on April 14, 1994, Northern Natural Gas Company
(Northern), 1111 South 103rd Street, Omaha, Nebraska 68124-1000, filed
in Docket No. CP94-356-000 a request pursuant to Secs. 157.205, 157.212
and 157.216 of the Commission's Regulations under the Natural Gas Act
(18 CFR 157.205, 157.212 and 157.216) for authorization to (1) abandon
and transfer by sale to Metropolitan Utilities District (MUD) the
existing Omaha TBS #4 and approximately 1.2 miles of the Omaha Public
Power District (OPPD) branchline and easements in Sarpy County,
Nebraska; and (2) install and operate one (1) delivery point and
appurtenant facilities to allow Northern to make natural gas deliveries
to MUD, under Northern's blanket certificate issued in Docket No. CP82-
401-000 pursuant to Section 7 of the Natural Gas Act, all as more fully
set forth in the request that is on file with the Commission and open
to public inspection.
Northern states that it requests authority to (1) abandon and
transfer by sale to MUD the existing Omaha TBS #4 and approximately 1.2
miles of the Sarpy County OPPD branchline and easements; and (2)
install and operate one (1) delivery point and appurtenant facilities
to make deliveries under Northern's existing transportation rate
schedules. The estimated total volumes proposed to be delivered to MUD
at the proposed new delivery point are 67,000 Mcf per day and 223,000
Mcf on an annual basis. The estimated cost to install the delivery
point is $211,555. Northern states that MUD will contribute $189,000 to
Northern for the cost of these facilities.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Sec. 157.205 of the
Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the
request. If no protest is filed within the time allowed therefore, the
proposed activity shall be deemed to be authorized effective the day
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to section 7 of the Natural Gas Act.
Lois D. Cashell,
Secretary.
[FR Doc. 94-9972 Filed 4-25-94; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 04/26/1994
- Department:
- Energy Department
- Entry Type:
- Uncategorized Document
- Document Number:
- 94-9972
- Pages:
- 0-0 (1 pages)
- Docket Numbers:
- Federal Register: April 26, 1994, Docket No. CP94-356-000