97-10975. Shieldalloy Metallurgical Corp. (Newfield, New Jersey); Director's Decision Under 10 CFR Sec. 2.206  

  • [Federal Register Volume 62, Number 82 (Tuesday, April 29, 1997)]
    [Notices]
    [Pages 23284-23287]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 97-10975]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket No. 040-07102]
    
    
    Shieldalloy Metallurgical Corp. (Newfield, New Jersey); 
    Director's Decision Under 10 CFR Sec. 2.206
    
    I. Introduction
    
        In an undated letter addressed to U.S. Nuclear Regulatory 
    Commission (``NRC'') Chairman Shirley Jackson and received on October 
    11, 1996, Sherwood Bauman, Chairperson of Save Wills Creek 
    (``Petitioner''), requested that the NRC take action with respect to 
    NRC licensee Shieldalloy Metallurgical Corporation (``SMC''), of 
    Newfield, New Jersey. The Petitioner requested, pursuant to 10 CFR 
    Sec. 2.206, that the NRC modify SMC's license to allow only possession 
    of radioactive material for the express purpose of decommissioning and 
    decontaminating its Newfield facility, and that current operations 
    resulting in additional radioactive material being stored at the site 
    be immediately halted. The Petitioner cites the lack of adequate 
    financial assurance, as required by 10 CFR Sec. 40.36, as the basis for 
    his request.
    
    [[Page 23285]]
    
        The Petitioner submitted a follow-up letter, addressed to the NRC 
    Executive Director for Operations and dated February 7, 1997, 
    reiterating the above request. In this letter, the Petitioner stated 
    that SMC is attempting to reclassify wastes as potential resources for 
    which the Petitioner believes there is no viable market. Furthermore, 
    the Petitioner concludes that without a viable market and the resultant 
    inadequate financial assurance for the company, SMC is jeopardizing the 
    health and safety of the local Newfield community.
        By letter dated November 14, 1996, I formally acknowledged receipt 
    of the Petitioner's original correspondence and informed the Petitioner 
    that his request was being treated pursuant to 10 CFR Sec. 2.206 of the 
    Commission's regulations. A notice of receipt of the petition was 
    published in the Federal Register on Thursday, November 21, 1996 (61 FR 
    59251). By letter dated March 7, 1997, I formally acknowledged receipt 
    of the Petitioner's supplementary letter.
        I have evaluated the Petitioner's request and have determined that, 
    for the reasons stated below, the Petition is granted in part and 
    denied in part.
    
    II. Background
    
        At its Newfield, New Jersey facility, SMC processes pyrochlore, a 
    concentrated ore containing columbium (niobium), to produce ferro-
    columbium, an additive/ conditioner used in the production of specialty 
    steel and superalloys. The pyrochlore contains, by weight, more than 
    0.05 percent natural uranium and thorium, which are source materials 
    and therefore require a NRC license pursuant to 10 CFR Part 40. SMC 
    operates this process under the authority of NRC Source Material 
    License No. SMB-743.
        During the manufacturing process, the radioactive materials are 
    concentrated in both high-temperature slag and baghouse 1 
    dust, which are then stored in the source material storage yard at the 
    site. The slag contains most of the licensed material. In a letter to 
    the NRC, dated June 24, 1996, the licensee indicated that the 
    concentration of source material in the baghouse dust is, on average, 
    less than the ``unimportant quantity'' source material threshold of 
    0.05 percent by weight, as described in 10 CFR Sec. 40.13(a), 
    2 and need not be treated as licensed material after it is 
    removed from the site. The licensee has stored source material in this 
    manner at the Newfield site since the 1950s and has accumulated 
    approximately 295,000 kilograms (kg) of thorium and 40,000 kg of 
    uranium at the site. SMC's current license limits SMC to 303,050 kg of 
    thorium and 45,000 kg of uranium. That license expired on July 31, 
    1985, and SMC has continued operations in accordance with its existing 
    license under the timely renewal provisions of 10 CFR Sec. 40.42(a). 
    The SMC site has been included in the NRC's Site Decommissioning 
    Management Plan because it contains a large volume of contaminated 
    material for which disposal may prove difficult.
    ---------------------------------------------------------------------------
    
        \1\ The baghouses contain filters comprised of cloth (or similar 
    material) arranged in a tubular fashion in an enclosed housing. The 
    effluent stream from the production area is blown through the filter 
    bags, which trap the particulates on the collected material that 
    builds up on the bags. As the buildup of material on the bags 
    increases, so too does resistance to flow. For that reason, the 
    baghouse filters are equipped with shaking/vibrating devices to 
    remove the collected dust and re-condition the bags. The rated 
    efficiency of the filters used in the D-111 baghouses is over 99 
    percent.
        \2\ Under Sec. 40.13(a), any person is exempt from the 
    requirements of 10 CFR Part 40 and from the requirements for a 
    license under Section 62 of the Atomic Energy Act to the extent that 
    such person receives, possesses, uses, transfers or delivers source 
    material in any chemical mixture, compound, solution, or alloy in 
    which the source material is by weight less than 0.05 percent of the 
    mixture, compound, solution, or alloy.
    ---------------------------------------------------------------------------
    
        The primary issue significantly delaying SMC's license renewal is 
    SMC's ability to meet the financial assurance requirements of 10 CFR 
    Sec. 40.36 3. To meet its obligation under Sec. 40.36, SMC 
    originally provided the NRC with a Letter of Credit, dated July 23, 
    1990, in the amount of $750,000 to serve as financial assurance pending 
    completion of the NRC's review of SMC's decommissioning funding plan.
    ---------------------------------------------------------------------------
    
        \3\ The NRC's financial assurance requirements in 10 CFR 
    Sec. 40.36, as pertain to SMC's Newfield license, state that:
        (a) Each applicant for a specific license authorizing the 
    possession and use of more than 100 mCi of source material in a 
    readily dispersible form shall submit a decommissioning funding plan 
    (DFP) as described in paragraph (d) of this section.
        *        *        *        *        *
        (d) Each DFP must contain a cost estimate for decommissioning 
    and a description of the method (such as a prepayment, a surety, or 
    an external sinking fund as described in Sec. 40.36(e)) of assuring 
    funds for decommissioning.
    ---------------------------------------------------------------------------
    
        In September 1993, SMC notified the NRC that it had filed for 
    bankruptcy under Chapter 11 of the U.S. Bankruptcy Code. At that time, 
    SMC also informed the NRC that it could not provide an acceptable 
    decommissioning funding plan for reaching unrestricted release limits 
    4 by disposing of all stored material in a licensed disposal 
    facility. Despite SMC's filing for bankruptcy and continued efforts to 
    satisfy the NRC's financial assurance requirements, SMC has and 
    continues to maintain public health and safety at its Newfield facility 
    during continued operations under its existing license. Therefore, the 
    status of current public health and safety protection is not at issue 
    in this case.
    ---------------------------------------------------------------------------
    
        \4\ The NRC's guidance for unrestricted release limits can be 
    found in ``Disposal or Onsite Storage of Thorium or Uranium Wastes 
    from Past Operations'' (October 23, 1981; 46 FR 52061).
    ---------------------------------------------------------------------------
    
        By letter dated December 12, 1995, SMC submitted a new 
    decommissioning funding plan to the NRC, proposing that the licensed 
    slag be exported for use in steel production. The decommissioning 
    funding plan also proposes that SMC sell the baghouse dust domestically 
    (for cement manufacturing) without restriction because it is, on 
    average, less than the 10 CFR Sec. 40.13(a) ``unimportant quantity'' 
    threshold described above. Finally, under the new decommissioning 
    funding plan, SMC would decontaminate and decommission the remainder of 
    the Newfield site, after off-site shipment of the aforementioned 
    products and in accordance with the NRC's unrestricted release 
    criteria, by disposing of remaining contaminated structures and soils 
    in a licensed disposal facility.
        In December 1994, SMC submitted an application to the NRC for a 
    license to export a test shipment of slag to a steel mill in Trinidad. 
    The NRC's review of the export license application became moot in early 
    1996 when public concern in Trinidad led SMC's potential customer to 
    reconsider purchasing the material. SMC has unofficially indicated to 
    the NRC that it is currently negotiating with other steel mills and 
    will likely revise its export application for export to steel mills in 
    one or more countries during 1997.
        By letter dated June 24, 1996, SMC requested permission for the 
    proposed domestic sale and transfer of the baghouse dust to unlicensed 
    persons; the staff is currently reviewing the request.
    
    III. Discussion
    
        The Petitioner cites the lack of adequate financial assurance, as 
    required by 10 CFR Sec. 40.36, as the basis for his request. The 
    Petitioner states that SMC is attempting to reclassify wastes as 
    potential resources for which the Petitioner believes there is no 
    viable market. Furthermore, the Petitioner concludes that lacking both 
    a viable market and adequate decommissioning funding, SMC is 
    jeopardizing the health and safety of the local Newfield community. To 
    support his request, the Petitioner presents three factors he believes 
    are relevant to his petition:
        1. The Petitioner stated that the NRC's draft environmental impact 
    statement, dated July 1996, for SMC's Cambridge facility (docket 040-
    8948), discussed an identical proposal to sell slag from the
    
    [[Page 23286]]
    
    Cambridge site. As part of that discussion, the Petitioner noted that 
    the NRC staff stated that SMC could not actually demonstrate that SMC's 
    proposal for sale of ferro-columbium slag at the Cambridge site is a 
    workable and viable option.
        2. The Petitioner also stated that to prove the lack of 
    marketability for sale of ferro-columbium, the NRC could determine 
    whether or not potential customers in the United States would require a 
    license to possess the material in question. The Petitioner believes 
    that few, if any, domestic companies will be willing to obtain any NRC 
    licenses that may be required for the use of this material.
        3. Finally, the Petitioner stated that the only customer SMC has 
    been able to locate, to date, was not in the United States, but in an 
    under-developed third world country with little protection. After 
    adverse publicity in the affected country, the facility purchasing the 
    material canceled its order, and SMC has been unable to develop a new 
    market during the succeeding 3 years.
    
    A. Regulatory Framework.
    
    1. Summary of 10 CFR Sec. 40.36
        Under 10 CFR Sec. 40.36, a licensee is required to submit a 
    detailed decommissioning funding plan, describing both the plan for 
    decommissioning the site upon termination of operations and the method 
    of assuring funds to complete the actions described in the 
    decommissioning plan. The purpose of this requirement is to assure that 
    a licensee possesses sufficient funds to eventually decontaminate and 
    decommission the site to a level at which public health and safety is 
    assured. This rule was originally implemented in 1990. The NRC 
    generally requires its licensees to provide financial assurance 
    sufficient to decommission a site for unrestricted release consistent 
    with the definition of decommissioning in 10 CFR Sec. 40.4. To meet 
    these unrestricted release criteria, licensees generally transfer any 
    radioactive waste generated during decommissioning to a licensed 
    disposal facility. However, in some cases the staff has used its 
    discretion to accept lesser amounts of financial assurance, based on a 
    finding of the acceptability of alternative approaches (e.g., in-situ 
    disposal) or a binding commitment (such as a license condition or NRC 
    order) from the licensee to pursue alternative approaches. In cases 
    that involve a major federal action and where the potential 
    environmental impacts of the alternative approaches may be significant, 
    the NRC prepares an Environmental Impact Statement (EIS) and Record of 
    Decision in accordance with the requirements of 10 CFR Part 51.
    2. Application of 10 CFR Sec. 40.36 to License No. SMB-743
        Prior to 1990, the NRC did not require financial assurance for 
    decommissioning from its licensees. During the period prior to the 
    rule's implementation, SMC amassed large quantities of slag at the site 
    contaminated with source material. Because SMC was in timely renewal at 
    the time, SMC was only required to provide certification of financial 
    assurance for $750,000 to meet the financial assurance requirements 
    pursuant to 10 CFR Sec. 40.36(c)(2).
        In 1993, after SMC notified the NRC that it could not provide 
    adequate financial assurance to meet unrestricted release limits, the 
    NRC began to develop an EIS for the decommissioning of the SMC Newfield 
    site in response to the licensee's request to dispose of the 
    contaminated slag and baghouse dust in situ. The NRC suspended EIS 
    development in 1995 when the licensee informed the NRC of its intent to 
    transfer the slag for use in steel smelting and the baghouse dust for 
    other, non-licensed purposes.
        In December 1995, SMC submitted a modified decommissioning funding 
    plan. That plan proposes that the licensed slag be exported for use in 
    steel production as a fluxing agent that also removes impurities from 
    the steel mixture, the result being a derived slag containing the 
    impurities including the source material. This derived slag would be 
    sold as an aggregate with no restrictions, because the concentrations 
    of uranium and thorium would be, on average, well below the NRC's 10 
    CFR Sec. 40.13(a) ``unimportant quantity'' limit. The concentration of 
    source material in the derived slag is less than in SMC's slag because 
    it is diluted with other inert materials (such as lime and alumina) 
    during the smelting process. The latest decommissioning funding plan 
    also proposes that SMC sell the baghouse dust domestically for other 
    purposes (e.g., cement manufacturing) without restriction because the 
    contaminated baghouse dust would also be, on average, less than 0.05 
    percent of source material by weight. By letter dated June 24, 1996, 
    SMC requested permission for the proposed domestic sale of the baghouse 
    dust; the staff is currently reviewing the request. Finally, under the 
    new decommissioning funding plan, SMC would decontaminate and 
    decommission the remainder of the Newfield site to conform to the NRC's 
    unrestricted release limits; contaminated structures, soils, and 
    radioactive wastes generated during decontamination and decommissioning 
    would be sent to a licensed disposal facility. SMC calculated the cost 
    for executing the decommissioning activities described in the 1995 
    modified decommissioning plan to be slightly less than $750,000.
        The NRC has held a Letter of Credit for $750,000 from SMC, pursuant 
    to 10 CFR Sec. 40.36(c)(2), since 1990. On February 26, 1997, at SMC's 
    request, the NRC drew upon the Letter of Credit and is currently 
    holding the funds in trust. 5 Because SMC has in place the 
    required decommissioning funding plan and a financial assurance 
    mechanism which encompasses the cost estimates to perform the actions 
    proposed in the decommissioning funding plan, SMC is considered to be 
    in compliance with 10 CFR Sec. 40.36 until such time as the NRC 
    determines whether the submitted decommissioning funding plan is 
    acceptable (as discussed below). Therefore, the issue being decided 
    herein is whether the licensee's current decommissioning funding plan 
    is acceptable.
    ---------------------------------------------------------------------------
    
        \5\ To facilitate its planned exit from bankruptcy proceedings 
    and with the Bankruptcy Court's approval, SMC requested by letter 
    dated October 25, 1996, that the NRC draw upon the existing Letter 
    of Credit.
    ---------------------------------------------------------------------------
    
    B. Acceptability of Decommissioning Funding Plan
    
        In SECY-96-210, dated October 1, 1996, the NRC staff informed the 
    Commission of its concerns regarding the acceptability of SMC's 
    decommissioning funding plan and described its plan to resolve the 
    associated issues. As part of its plan, the staff informed the 
    Commission of its intent to permit interim acceptance of the 
    decommissioning funding plan to allow renewal of the license; however, 
    the staff's plan also requires that SMC present adequate evidence 
    (e.g., obtaining NRC approval of an export license application) 
    regarding the marketability of the slag within one year after renewal 
    of License SMB-743. If SMC cannot provide such evidence, the NRC will 
    reconsider the acceptability of the licensee's decommissioning funding 
    plan. This could include requiring the plan's revision to include a 
    different approach for decommissioning and disposal of the radioactive 
    slag (e.g., in-situ disposal). The NRC transmitted a copy of SECY-96-
    210 to the Petitioner as an enclosure to the November 14, 1996 
    acknowledgement letter.
    
    [[Page 23287]]
    
        In the Petitioner's February 7, 1997 supplementary letter, the 
    Petitioner elaborates upon his belief that the current decommissioning 
    funding plan should be considered unacceptable and the licensee is not 
    in compliance with the regulations in 10 CFR Sec. 40.36 by stating that 
    SMC's proposed plans to disposition the slags are neither 
    technologically nor financially viable.
        The Petitioner argues that the NRC has already stated that the sale 
    of ferro-columbium slag is not viable, as referenced in the Draft 
    Environmental Impact Statement on Decommissioning of the Shieldalloy 
    Metallurgical Corporation, Cambridge, Ohio (NUREG-1543, July 1996) 
    (Draft EIS). This is not correct.
        The respective viabilities of the Newfield and Cambridge ferro-
    columbium slags for use in steel production are considered by the NRC 
    to be different in each case. As stated below, the Newfield ferro-
    columbium slag was produced using the same process that produced a 
    previously marketed Newfield ferro-vanadium slag, demonstrating that 
    the process using the Newfield ferro-columbium slag appears to be 
    viable. In contrast, the Cambridge ferro-columbium slag was produced 
    using a different process and different feedstock materials. 
    Consequently, the metallurgical properties of the Cambridge slags have 
    not yet been demonstrated to be technologically viable. For this 
    reason, the export sale alternative was not included for consideration 
    in the Draft EIS for decommissioning of the Cambridge site.
        With regard to the previously marketed ferro-vanadium slag, SMC 
    delivered, on average, 7000 tons of ferro-vanadium slag per year to the 
    domestic steel industry from 1991 to 1995, with the highest annual 
    amount reaching 9000 tons. By comparison, SMC currently stores 
    approximately 70,000 tons of ferro-columbium slag at its Newfield site. 
    The licensed ferro-columbium slag at the Newfield site was produced in 
    a manner similar to the ferro-vanadium slag. SMC's extensive 
    metallurgical evaluations indicate that the ferro-columbium slag has 
    metallurgical properties relating to the proposed steel process that 
    are similar, if not superior, to relevant properties of the ferro-
    vanadium slag.
        The NRC staff acknowledges the Petitioner's statement that the 
    domestic use of ferro-columbium slag would likely require an NRC or 
    Agreement State license for possession and use, thus possibly 
    constraining domestic commercial interest in the product and thereby 
    impacting the financial viability of the slag product. However, SMC is 
    marketing the material to international locations where regulatory 
    conditions may be less of a factor in determining the product's 
    financial viability. As part of any international export application 
    and prior to issuance of an export license, the NRC will inform the 
    importing government of the proposed importation and use of the product 
    containing the source material, in accordance with the International 
    Atomic Energy Agency's Code of Practice on the International 
    Transboundary Movement of Radioactive Waste.
        Finally, the Petitioner argues that the only potential customer SMC 
    has been able to locate, to date, has been in Trinidad. Because of 
    internal country concerns, the customer purchasing the material 
    canceled its order, and SMC has been unable to develop a new market 
    during the succeeding years, thus significantly decreasing viability of 
    the product. The NRC agrees with the Petitioner that this raises a 
    concern as to the viability of the proposed decommissioning funding 
    plan and therefore grants the Petitioner's request in part. The NRC 
    intends to require, in the form of a license condition as part of any 
    future license renewal, that SMC provide additional proof (in the form 
    of an NRC-approved export application) of the viability of the proposed 
    disposition method within one year of the license's renewal. If such 
    proof is not forthcoming within the time limit, the NRC staff plans to 
    issue an order requiring the submission of a new decommissioning 
    funding plan along with appropriate mechanisms for financial assurance. 
    Furthermore, the NRC will include a condition in any renewed SMC 
    license requiring SMC to provide financial assurance commensurate in 
    value for the costs of offsite disposal for future source material 
    possession increases. These two conditions are intended to prevent SMC 
    from continuing to accumulate licensed material at the site in 
    perpetuity without adequate financial assurance.
    
    IV. Conclusion
    
        The staff has carefully considered the request of the Petitioner. 
    For the reasons discussed above, I conclude that no substantial public 
    health and safety concerns warrant NRC action concerning the request. 
    However, because the staff is proposing to impose certain restrictions 
    on the licensee for reasons similar to those presented by the 
    Petitioner, I grant the Petitioner's request to that extent and deny it 
    in other respects.
        A copy of this Decision will be placed in the Commission's Public 
    Document Room, Gelman Building, 2120 L Street, NW, Washington, DC, and 
    at the Local Public Document Room for the named facility. A copy of 
    this Decision will also be filed with the Secretary for the 
    Commission's review as provided in 10 CFR Sec. 2.206(c) of the 
    Commission's regulations.
        As provided by this regulation, the Decision will constitute the 
    final action of the Commission 25 days after issuance, unless the 
    Commission, on its own motion, institutes a review of the Decision 
    within that time.
    
        Dated at Rockville, Maryland, this 15 day of April 1997.
    
        For the Nuclear Regulatory Commission.
    Carl J. Paperiello,
    Director, Office of Nuclear Material Safety and Safeguards.
    [FR Doc. 97-10975 Filed 4-28-97; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
04/29/1997
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
97-10975
Pages:
23284-23287 (4 pages)
Docket Numbers:
Docket No. 040-07102
PDF File:
97-10975.pdf