DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP98-362-000]
Northern Border Pipeline Company; Notice of Request Under Blanket
Authorization
April 24, 1998.
Take notice that on April 17, 1998, Northern Border Pipeline
Company (Northern Border), 1111 South 103rd Street, Nebraska 68134-
1000, filed in Docket No. CP98-362-000, a request pursuant to Section
157.205 and 157.212 of the Commission's Regulations under the Natural
Gas Act (18 CFR 157.205 and 157.212) for authorization to construct and
operate three tie-over lines on its pipeline system for the existing
delivery points of Beaman, Tama and Amana in Iowa, under Northern
Border's blanket certificate issued in docket No. CP84-420-000,
pursuant to 18 CFR Part 157, Subpart F of the Natural Gas Act, all as
more fully set forth in the request which is on file with the
Commission and open to public inspection.
Northern Border proposes to construct and operate three tie-over
lines on its pipeline system for the existing delivery points of
Beaman, Tama and Amana. It is stated that at Beaman a 2-inch tap would
be installed on the 36-inch pipeline and approximately twenty feet
[[Page 23768]]
of 2-inch pipe would extend from the tap to the 6-inch line serving the
town of Beaman. It is further stated that at Tama a 2-inch tap would be
installed on the 36-inch pipeline and approximately twenty feet of 2-
inch pipe would extend from the tap to the 3-inch rise off of the tap
on the 30-inch pipeline. Northern border further states that at Amana a
4-inch tap would be installed on the 36-inch pipeline and approximately
twenty feet of 2-inch pipe would extend from the tap to the 6-inch line
serving Amana. Northern Border states that the estimated cost of the
proposed facilities is $26,803.
Northern Border states that during construction of its expansion/
extension this summer, it would take out of service its existing 30-
inch pipeline between Ventura, Iowa and Harper, Iowa while the tie-in
of the cross-over lines between the 30-inch and 36-inch lines are
completed. It is further stated that during the period that the 30-inch
pipeline is out of service the contract volumes currently being shipped
on its system would be transported through the 36-inch line.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) motion to
intervene or notice of intervention and pursuant to Section 157.205 of
the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to
the request. If no protest is filed within the time allowed therefor,
the proposed activity shall be deemed to be authorized effective the
day after the time allowed for filing a protest. If a protest is filed
and not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 98-11457 Filed 4-29-98; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 04/30/1998
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 98-11457
- Pages:
- 23767-23768 (2 pages)
- Docket Numbers:
- Docket No. CP98-362-000
- PDF File:
-
98-11457.pdf