E8-7175. Notice of License Amendment Request of Crow Butte Resources, Inc., Crawford, NE, and Opportunity To Request a Hearing  

  • Start Preamble

    AGENCY:

    Nuclear Regulatory Commission.

    ACTION:

    Notice of license amendment, and opportunity to request a hearing.

    DATES:

    A request for a hearing must be filed by June 6, 2008.

    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Stephen J. Cohen, Project Manager, Uranium Recovery Licensing Branch, Division of Waste Management and Environmental Protection, Office of Federal and State and Environmental Management Programs, U.S. Nuclear Regulatory Commission, Washington, DC, 20555. Telephone: (301) 415-7182; fax number: (301) 415-5369; e-mail: sjc7@nrc.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Introduction

    The U.S. Nuclear Regulatory Commission (NRC) has received, by letter dated November 27, 2007, a license amendment application from Crow Butte Resources, Inc. (CBR), requesting renewal of its source material license for its in situ leach (ISL) uranium recovery facility located in Crawford, Nebraska. License No. SUA-1534 authorizes the licensee to operate an ISL uranium recovery facility to produce yellowcake. Specifically, the amendment requests that NRC renew CBR's current license for a standard 10-year period.

    An NRC administrative review, documented in a letter to CBR dated March 28, 2008, found the application acceptable to begin a technical review. If the NRC approves the amendment, the Start Printed Page 18824approval will be documented in an amendment to NRC License No.: SUA-1534. However, before approving the proposed amendment, the NRC will need to make the findings required by the Atomic Energy Act of 1954, as amended (the Act), and NRC's regulations. These findings will be documented in a Safety Evaluation Report and an Environmental Assessment.

    II. Opportunity to Request a Hearing

    The NRC hereby provides notice that this is a proceeding on an application for a license amendment regarding renewal of Source Materials License No.: SUA-1534 issued to Crow Butte Resources for its ISL uranium recovery facility in Crawford, NE. Any person whose interest may be affected by this proceeding, and who desires to participate as a party, must file a request for a hearing and a specification of the contentions which the person seeks to have litigated in the hearing, in accordance with the NRC E-Filing rule, which the NRC promulgated in August, 2007, 72 FR 49139 (August 28, 2007). The E-Filing rule requires participants to submit and serve documents over the internet or in some cases to mail copies on electronic storage media. Participants may not submit paper copies of their filings unless they seek a waiver in accordance with the procedures described below.

    To comply with the procedural requirements of E-Filing, at least five (5) days prior to the filing deadline, the petitioner/requestor must contact the Office of the Secretary by e-mail at HEARINGDOCKET@NRC.GOV, or by calling (301) 415-1677, to request (1) a digital Identification (ID) certificate, which allows the participant (or its counsel or representative) to digitally sign documents and access the E-Submittal server for any proceeding in which it is participating; and/or (2) creation of an electronic docket for the proceeding (even in instances in which the petitioner/requestor (or its counsel or representative) already holds an NRC-issued digital ID certificate). Each petitioner/requestor will need to download the Workplace Forms ViewerTM to access the Electronic Information Exchange (EIE), a component of the E-Filing system. The Workplace Forms ViewerTM is free and is available at http://www.nrc.gov/​site-help/​e-submittals/​install-viewer.html. Information about applying for a digital ID certificate is available on NRC's public website at http://www.nrc.gov/​site-help/​e-submittals/​apply-certificates.html.

    Once a petitioner/requestor has obtained a digital ID certificate, had a docket created, and downloaded the EIE viewer, it can then submit a request for hearing or petition for leave to intervene. Submissions should be in Portable Document Format (PDF) in accordance with NRC guidance available on the NRC public website at http://www.nrc.gov/​site-help/​e-submittals.html. A filing is considered complete at the time the filer submits its documents through EIE. To be timely, an electronic filing must be submitted to the EIE system no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of a transmission, the E-Filing system time-stamps the document and sends the submitter an e-mail notice confirming receipt of the document. The EIE system also distributes an e-mail notice that provides access to the document to the NRC Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the documents on those participants separately. Therefore, applicants and other participants (or their counsel or representative) must apply for and receive a digital ID certificate before a hearing request/petition to intervene is filed so that they can obtain access to the document via the E-Filing system.

    A person filing electronically may seek assistance through the “Contact Us” link located on the NRC website at http://www.nrc.gov/​site-help/​e-submittals.html or by calling the NRC technical help line, which is available between 8:30 a.m. and 4:15 p.m., Eastern Time, Monday through Friday. The help line number is (800) 397-4209 or locally, (301) 415-4737.

    Participants who believe that they have a good cause for not submitting documents electronically must file a motion, in accordance with 10 CFR 2.302(g), with their initial paper filing requesting authorization to continue to submit documents in paper format. Such filings must be submitted by: (1) First class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention: Rulemaking and Adjudications Staff; or (2) courier, express mail, or expedited delivery service to the Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852, Attention: Rulemaking and Adjudications Staff. Participants filing a document in this manner are responsible for serving the document on all other participants. Filing is considered complete by first-class mail as of the time of deposit in the mail, or by courier, express mail, or expedited delivery service upon depositing the document with the provider of the service.

    Non-timely requests and/or petitions and contentions will not be entertained absent a determination by the Commission, the presiding officer, or the Atomic Safety and Licensing Board that the petition and/or request should be granted and/or the contentions should be admitted based on a balancing of the factors specified in 10 CFR 2.309(c)(1)(i)-(viii). To be timely, filings must be submitted no later than 11:59 p.m. Eastern Time on the due date.

    Documents submitted in adjudicatory proceedings will appear in NRC's electronic hearing docket which is available to the public at http://ehd.nrc.gov/​EHD_​Proceeding/​home.asp, unless excluded pursuant to an order of the Commission, an Atomic Safety and Licensing Board, or a Presiding Officer. Participants are requested not to include social security numbers in their filings. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, participants are requested not to include copyrighted materials in their submission.

    The formal requirements for documents contained in 10 CFR 2.304(c)-(e) must be met. If the NRC grants an electronic document exemption in accordance with 10 CFR 2.302(g)(3)), then the requirements for paper documents, set forth in 10 CFR 2.304(b) must be met.

    In accordance with 10 CFR 2.309(b), a request for a hearing must be filed by June 6, 2008.

    In addition to meeting other applicable requirements of 10 CFR 2.309, the general requirements involving a request for a hearing filed by a person other than an applicant must state:

    1. The name, address, and telephone number of the requester;

    2. The nature of the requester's right under the Act to be made a party to the proceeding;

    3. The nature and extent of the requester's property, financial or other interest in the proceeding;

    4. The possible effect of any decision or order that may be issued in the proceeding on the requester's interest; and

    5. The circumstances establishing that the request for a hearing is timely in accordance with 10 CFR 2.309(b).

    In accordance with 10 CFR 2.309(f)(1), a request for hearing or petitions for Start Printed Page 18825leave to intervene must set forth with particularity the contentions sought to be raised. For each contention, the request or petition must:

    1. Provide a specific statement of the issue of law or fact to be raised or controverted;

    2. Provide a brief explanation of the basis for the contention;

    3. Demonstrate that the issue raised in the contention is within the scope of the proceeding;

    4. Demonstrate that the issue raised in the contention is material to the findings that the NRC must make to support the action that is involved in the proceeding;

    5. Provide a concise statement of the alleged facts or expert opinions which support the requester's/petitioner's position on the issue and on which the requester/petitioner intends to rely to support its position on the issue; and

    6. Provide sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact. This information must include references to specific portions of the application (including the applicant's environmental report and safety report) that the requester/petitioner disputes and the supporting reasons for each dispute, or, if the requester/petitioner believes the application fails to contain information on a relevant matter as required by law, the identification of each failure and the supporting reasons for the requester's/petitioner's belief.

    In addition, in accordance with 10 CFR 2.309(f)(2), contentions must be based on documents or other information available at the time the petition is to be filed, such as the application, supporting safety analysis report, environmental report or other supporting document filed by an applicant or licensee, or otherwise available to the petitioner. On issues arising under the National Environmental Policy Act, the requester/petitioner shall file contentions based on the applicant's environmental report. The requester/petitioner may amend those contentions or file new contentions if there are data or conclusions in the NRC draft, or final environmental impact statement, environmental assessment, or any supplements relating thereto, that differ significantly from the data or conclusions in the applicant's documents. Otherwise, contentions may be amended or new contentions filed after the initial filing only with leave of the presiding officer.

    Each contention shall be given a separate numeric or alpha designation within one of the following groups:

    1. Technical—primarily concerns issues relating to matters discussed or referenced in the Safety Evaluation Report for the proposed action.

    2. Environmental—primarily concerns issues relating to matters discussed or referenced in the Environmental Report for the proposed action.

    3. Miscellaneous—does not fall into one of the categories outlined above.

    If the requester/petitioner believes a contention raises issues that cannot be classified as primarily falling into one of these categories, the requester/petitioner must set forth the contention and supporting bases, in full, separately for each category into which the requester/petitioner asserts the contention belongs with a separate designation for that category.

    Requesters/petitioners should, when possible, consult with each other in preparing contentions and combine similar subject matter concerns into a joint contention, for which one of the co-sponsoring requesters/petitioners is designated the lead representative. Further, in accordance with 10 CFR 2.309(f)(3), any requester/petitioner that wishes to adopt a contention proposed by another requester/petitioner must do so, in accordance with the E-Filing rule, within ten days of the date the contention is filed, and designate a representative who shall have the authority to act for the requester/petitioner.

    In accordance with 10 CFR 2.309(g), a request for hearing and/or petition for leave to intervene may also address the selection of the hearing procedures, taking into account the provisions of 10 CFR 2.310.

    III. Further Information

    Documents related to this action, including the application for amendment and supporting documentation, are available electronically at the NRC's Electronic Reading Room at http://www.nrc.gov/​reading-rm/​adams.html. From this site, you can access the NRC's Agencywide Document Access and Management System (ADAMS), which provides text and image files of NRC's public documents. The ADAMS accession numbers for the documents related to this notice are: Request for License Renewal Transmittal Letter (ML073470645), License Renewal Application (combined technical and environmental reports), Part 1 (ML073480266), License Renewal Application (combined technical and environmental reports), Part 2 (ML073480267), and the acceptance review letter dated March 28, 2008 (ML080720341). If you do not have access to ADAMS or if there are problems in accessing the documents located in ADAMS, contact the NRC Public Document Room (PDR) Reference staff at 1-800-397-4209, 301-415-4737 or by email to pdr@nrc.gov.

    These documents may also be viewed electronically on the public computers located at the NRC's Public Document Room (PDR), O 1 F21, One White Flint North, 11555 Rockville Pike, Rockville, MD 20852. The PDR reproduction contractor will copy documents for a fee.

    Start Signature

    Dated at Rockville, MD, this 31st day of March, 2008.

    For the Nuclear Regulatory Commission.

    William vonTill,

    Branch Chief, Uranium Recovery Licensing Branch, Division of Waste Management and Environmental Protection, Office of Federal and State Materials and Environmental Management Programs.

    End Signature End Supplemental Information

    [FR Doc. E8-7175 Filed 4-4-08; 8:45 am]

    BILLING CODE 7590-01-P

Document Information

Published:
04/07/2008
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Action:
Notice of license amendment, and opportunity to request a hearing.
Document Number:
E8-7175
Dates:
A request for a hearing must be filed by June 6, 2008.
Pages:
18823-18825 (3 pages)
Docket Numbers:
Docket No.: 40-8943
PDF File: