94-8478. Collections From Central Valley Project Power Contractors To Carry Out the Restoration, Improvement, and Acquisition of Environmental Habitat Provisions of the Central Valley Project Improvement Act of 1992

  • [Federal Register Volume 59, Number 68 (Friday, April 8, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-8478]
    
    
    [[Page Unknown]]
    
    [Federal Register: April 8, 1994]
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    Western Area Power Administration
    
     
    
    Collections From Central Valley Project Power Contractors To 
    Carry Out the Restoration, Improvement, and Acquisition of 
    Environmental Habitat Provisions of the Central Valley Project 
    Improvement Act of 1992
    
    AGENCY: Western Area Power Administration, DOE.
    
    ACTION: Notice of final procedures for the assessment and collection of 
    restoration fund payments from the Central Valley Project power 
    contractors.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Central Valley Project (CVP) Improvement Act of 1992 (Act) 
    (Pub. L. 102-575, 106 Stat. 4706 et seq.) establishes in the Treasury 
    of the United States the ``Central Valley Project Restoration Fund'' to 
    carry out the habitat restoration, improvement, and acquisition 
    provisions of the Act. The Act further requires the Secretary of the 
    Interior to assess and collect annual mitigation and restoration 
    payments from CVP water and power contractors. The Secretary of the 
    Interior, through the Bureau of Reclamation (Reclamation), is 
    responsible for determining the CVP water contractors' share and the 
    CVP power contractors' share of the Restoration Fund payments. Because 
    Western Area Power Administration (Western) is responsible for the 
    marketing of CVP power and maintains all CVP power contracts, Western 
    has agreed to assess and collect the total CVP power contractors' share 
    of the Restoration Fund payments, as determined by Reclamation, from 
    the CVP power contractors. By publication of this notice, Western 
    establishes procedures to accomplish the assessment and collection of 
    Restoration Fund payments from the CVP power contractors as required by 
    the Act.
    
    DATES: The final procedures will become effective May 9, 1994 and will 
    remain in effect until superseded.
    
    ADDRESSES: Information regarding this final procedure, including 
    spreadsheet analysis, comments, letters, memorandums, and other 
    supporting documents made or kept by Western for the purpose of 
    developing these procedures, is available for public inspection and 
    copying at Western's Sacramento Area Office located at 1825 Bell 
    Street, suite 105, Sacramento, CA 95825-1097.
    
    FOR FURTHER INFORMATION CONTACT:
    
    James C. Feider, Area Manager, Sacramento Area Office, Western Area 
    Power Administration, 1825 Bell Street, suite 105, Sacramento, CA 
    95825-1097, (916) 649-4418.
    
    SUPPLEMENTARY INFORMATION: Section 3407 of the Act establishes in the 
    Treasury of the United States the ``Central Valley Project Restoration 
    Fund'' to carry out the habitat restoration, improvement, and 
    acquisition provisions of the Act. The Act further requires the 
    Secretary of the Interior to assess and collect annual mitigation and 
    restoration payments from CVP water and power contractors. The 
    Secretary of the Interior, through Reclamation, is responsible for 
    determining and collecting the CVP water contractors' share and the CVP 
    power contractors' share of the annual Restoration Fund payments.
        Because Western is responsible for the marketing of CVP power, 
    Western has agreed to administer the assessment and collection of the 
    Restoration Fund payments from the CVP power contractors. Western has 
    executed a Letter of Agreement with Reclamation to establish procedures 
    for depositing the collections from the CVP power contractors into the 
    Restoration Fund.
        The total power Restoration Fund payment obligation, determined by 
    Reclamation, will be assessed to the CVP power contractors. Every month 
    each CVP power contractor will receive a bill reflecting the amount to 
    be paid into the Restoration Fund. The CVP power contractor will pay 
    that amount to Western, who will deposit all amounts collected from the 
    CVP power contractors into the Restoration Fund.
    
    Acronyms and Definitions
    
        Descriptions of the acronyms and definitions used in this Federal 
    Register notice may be found in the Final Procedures.
    
    Public Notice and Comments
    
        The process used by Western to ensure involvement of interested 
    parties in the development of these final procedures for assessing and 
    collecting Restoration Fund payments from the CVP power contractors is 
    summarized below.
        1. On October 1, 1993, Western issued a letter to all CVP customers 
    announcing Reclamation's determination of a total power Restoration 
    Fund payment obligation of $7,092,800 for fiscal year (FY) 1994.
        2. On October 29, 1993, in a letter to all CVP power customers, 
    Western announced the plans to implement collections from the CVP power 
    contractors for the Restoration Fund on an interim basis, beginning 
    with a November 24, 1993, bill.
        3. A Federal Register notice was published at 58 FR 62343, November 
    26, 1993, officially announcing the proposed procedures for the 
    assessment and collection of the Restoration Fund payments from the CVP 
    power contractors, initiating the public consultation and comment 
    period, announcing the public information forum and public comment 
    forum, and presenting procedures for public participation.
        4. On December 1, 1993, in a letter to all CVP customers and 
    interested parties, Western announced that the public consultation and 
    comment period had begun; announced the dates, times, and locations of 
    the public information forum and the public comment forum; and enclosed 
    a copy of the November 26, 1993, Federal Register notice.
        5. At the public information forum held on December 16, 1993, 
    Western's staff presented the proposed procedures for the assessment 
    and collection of Restoration Fund payments and discussed the 
    methodologies and studies that were used in developing the proposed 
    procedures.
        6. A public comment forum was held on December 16, 1993, to give 
    the public the opportunity to comment for the record. Three persons 
    representing customers made oral comments.
        7. Fifteen comment letters were received during the 30-day 
    consultation and comment period. The consultation and comment period 
    ended December 26, 1993. All formally submitted comments have been 
    considered in the preparation of the final procedures.
        8. On December 30, 1993, copies of all written comments received 
    during the 30-day comment period were sent to all CVP customers and 
    interested parties.
        9. Based on customer comments regarding the proposed assessment and 
    collection method, Western analyzed various alternative methods to 
    address certain concerns. Upon request, Western shared these analyses 
    at a Northern California Power Agency members meeting on January 13, 
    1994, and a CVP Customer Technical Committee Meeting on January 19, 
    1994.
        10. On February 3, 1994, in a letter addressed to the Restoration 
    Fund commentors, Western provided copies of all handouts distributed 
    during the meetings specified in item 9 above.
    
    Comments
    
        During the 30-day consultation and comment period, Western received 
    15 written comments from 14 different sources. In addition, three 
    persons commented during the December 16, 1993, public comment forum.
        Written comments were received from the following sources:
    
    Alameda, City of (California)
    Arvin Edison Water Storage District (California)
    Calaveras Public Power Agency (California)
    Modesto Irrigation District (California)
    Palo Alto, City of (California)
    Petershagen, Mr. George F. (California)
    Redding, City of (California)
    Roseville, City of (California)
    Sacramento Municipal Utility District (California)
    Santa Clara, City of (California)
    Shasta Lake, City of (California)
    Trinity County Public Utility District (California)
    Tuolomne County Public Power Agency (California)
    Westlands Water District (California).
    
        Representatives of the following organizations made oral comments:
    
    Redding, City of (California)
    Roseville, City of (California)
    Sacramento Municipal Utility District (California).
    
        Most of the comments Western received dealt with assessing the 
    total Restoration Fund payment obligation to scheduled or delivered 
    energy, the authority to collect interim bills and assess late payment 
    charges during the interim period, the issuance of separate bills, and 
    establishing a review process for the final procedures. Additional 
    comments were received regarding assessing excess energy and capacity 
    sales, excluding first preference customers from the assessment, 
    assessing project use, changing the amount allocated to power by 
    Reclamation, and conducting an informal workshop. Discussion of the 
    comments will be grouped by these issues, with all other comments 
    placed under the heading of ``Other.'' In some cases Western will 
    address several comments with one response. The comments, paraphrased 
    for brevity, and responses are presented below.
    
    Assessing to Scheduled or Delivered Energy
    
        Comment: The agricultural power users consider Western's proposal 
    to be a fair and equitable method of allocating Restoration Fund 
    payment obligations.
        Comment: The proposal states that total collections will be the 
    same each month which could penalize seasonally diverse customers. It 
    seems appropriate that the collections more nearly reflect monthly 
    revenues.
        Comment: Energy alone is not an adequate assessment factor to 
    reflect utilization of the CVP. Factors such as actual demand and CVP 
    allocation used either separately or together could be more 
    representative than just energy alone.
        Comment: The proposal is likely to foster a market environment in 
    which Western's scheduling power contractors compete against other 
    Western power contractors to minimize the impact of the Restoration 
    Fund. Establish the assessment based on a system-wide per-kilowatthour 
    (kWh) basis.
        Comment: By assessing monthly energy, Western would distort 
    recently approved rates by effectively increasing the energy rate but 
    not the other charges included in bills. This could cause an 
    undesirable and/or unexpected response by customers who have resource 
    flexibility.
        Comment: An assessment of the payment as a fixed surcharge based on 
    a percentage of monthly energy entitlement would totally eliminate the 
    incentive to avoid restoration payments through reducing scheduled 
    energy.
        Comment: Assess the Restoration Fund payment obligation based on 
    total Contract Rate of Delivery (CRD). Under the proposed plan, 
    contract users could direct their energy needs from other sources in 
    order to evade payment of the Restoration Fund assessment leaving 
    customers with limited resource options to pay a larger portion of the 
    payment.
        Comment: The recent CVP rate process found that a 40-percent 
    capacity and 60-percent energy split is most equitable. The Restoration 
    Fund collections should also be assessed in this manner.
        Comment: Western has considered the cost allocation issue in 
    length, in the CVP general rate case proceeding, and determined that 
    the appropriate allocation of revenue requirements (costs) is 40 
    percent to capacity/60 percent to energy. We recommend Western utilize 
    this same methodology to allocate the Restoration Fund costs.
        Comment: Diversify the proposal to collect 50 percent on capacity 
    sales and 50 percent on energy sales; this will distribute and dilute 
    any uncontrollable price signals and discourage defensive gaming.
        Response: Western shares in the concerns of customers who felt the 
    proposed method would (1) penalize seasonally diverse customers, (2) 
    send adverse pricing signals, and/or (3) allow for adverse actions on 
    behalf of certain customer groups. Therefore, Western has decided to 
    prorate the total Restoration Fund payment obligation among actual 
    delivered or scheduled energy and capacity on a 50/50 basis.
        Western considered the comments recommending the allocation be 
    based on actual energy entitlement or CRD. Western believes the 
    assessment should reflect actual use of the CVP power system and not a 
    customer's upper limit on use of the CVP system.
        Western agrees that extensive analyses for the recent CVP rate 
    process indicated that Western's costs are best represented in a 40-
    percent capacity 60-percent energy ratio. Western also agrees that 
    heavily assessing CVP energy costs may send adverse pricing signals. 
    However, as stated above, it is Western's position that the Restoration 
    Fund should be assessed based on the actual use of the resource 
    provided rather than the costs associated with that resource use. The 
    50/50 basis was chosen because it reflects an assessment to both types 
    of long-term power services available from the CVP. Adverse pricing 
    signals that may be caused by an inequitable assessment to capacity or 
    energy will be reduced with a 50-percent delivered or scheduled energy, 
    50-percent delivered or scheduled capacity assessment.
    
    Authority To Assess and Collect Interest on Interim Bills
    
        Comment: Will interest accrue on interim billing or after the 
    public process becomes final?
        Comment: Western does not have the authority to require customers 
    to pay interim bills or assess interest before a final procedure is 
    adopted.
        Comment: Western should formally acknowledge that payment during 
    the interim period is optional.
        Comment: We appreciate your interest to minimize cash flow impacts 
    by starting collections as soon as possible. However, some customers 
    may prefer to wait until the public process is complete. We suggest 
    that the interim procedures be made optional.
        Comment: Current contract provisions do not provide for the 
    assessment of the Restoration Fund fees.
        Response: Western initiated the interim assessment and collection 
    process during the public process to reduce the economic impact to the 
    CVP power contractors, to proactively support the provisions of the 
    Act, and to assist Reclamation. Payments made by the CVP power 
    contractors during the interim period are considered by Western to be 
    optional. Bills not paid during the interim period did not accrue 
    interest. All billing notices sent to the CVP power contractors during 
    the interim period stated, ``Interim billing is not subject to a late 
    charge assessment.'' Although Restoration Fund payments are not 
    included in the CVP power sales contracts, collection is mandated by 
    the Act. Adoption of these final procedures provides Western the legal 
    authority to collect Restoration Fund payments. Interest will accrue on 
    Restoration Fund bills in the first billing cycle 30 days after the 
    publication of the final procedures in the Federal Register.
    
    Separate Billing
    
        Comment: Are the bills separate? Why is there a separate bill 
    versus inclusion in the current power bill from Western?
        Comment: Does the Act mandate monthly payments? What governed the 
    timing of the collection? Could collections be made on a quarterly 
    basis?
        Comment: The Act provides for annual, not monthly, payments to be 
    collected from the CVP water and power customers.
        Comment: We would like to avoid the administrative burden of an 
    additional monthly bill.
        Comment: We support the Western proposal to utilize a separate 
    billing for the Restoration Fund. This approach allows all parties to 
    clearly identify the payments that are being made pursuant to the 
    Central Valley Project Improvement Act.
        Comment: We support the proposed separate billing; this will aid in 
    tracking our share of the Restoration Fund.
        Response: Western will use separate bills to assess the Restoration 
    Fund payments to the CVP power contractors. The Secretary of the 
    Interior, through Reclamation, is responsible for determining and 
    collecting the CVP water contractors' share and the CVP power 
    contractors' share of the annual Restoration Fund payments. Because 
    Western is responsible for the marketing of CVP power, Western has 
    agreed to administer the assessment and collection of the Restoration 
    Fund payments from the CVP power contractors on behalf of Reclamation. 
    Western is assessing the total Restoration Fund payment obligation 
    among the CVP power contractors as a pass-through surcharge from 
    Reclamation. The Restoration Fund assessment is not associated with 
    current CVP rates or power revenues; the funds will not flow through 
    the CVP power repayment study, nor will they be deposited into the 
    Reclamation Fund to be applied to the repayment of CVP investment. In 
    addition, the amounts collected for the Restoration Fund are deposited 
    into a separate Treasury account and late payment interest charges are 
    assessed in a different manner than those imposed by the General Power 
    Contract Provisions included in the CVP power contractors' power sales 
    contracts. Western has adopted assessment and collection of the 
    Restoration Fund payments on a monthly basis to assure adequate cash 
    flow to Reclamation to carry out the goals of the Act.
    
    Establish a Review Process for the Final Procedures
    
        Comment: What would happen if the Act is overturned or its 
    implementation is delayed?
        Comment: Is there a sunset clause? What will happen if Congress 
    increases the limit significantly?
        Comment: Is the proposed procedure permanent for the duration of 
    the Fund?
        Comment: Include an opportunity to reopen the public process in the 
    final methodology, in case of unforeseen problems.
        Comment: Build in the flexibility to review every 2, 3, or 5 years 
    at the longest.
        Comment: We recommend that the final procedures include a statement 
    that Western will automatically reopen the surcharge matter for comment 
    and revision, in conjunction with the CVP's normal 5-year ratemaking 
    process.
        Comment: The assessment method should include a review process to 
    accommodate change and improvements that will become necessary as we 
    gain experience with the method and its effects.
        Response: Western agrees with customer comments and concerns and 
    has included a review process in the final procedures. Minimally, 
    Western will review the assessment method every 5 years from the 
    effective date of the final procedures or if one of the following 
    occurs:
        (1) If there is a significant change to or suspension of the 
    legislation,
        (2) If a material issue arises, or
        (3) If an apparent inequity in the assessment method is discovered.
    
    Assess Excess Capacity and Energy Sales
    
        Comment: Why were Energy Account Number 2 (EA2) and excess capacity 
    sales excluded from the allocation?
        Comment: Does Western do any other sales to Pacific Gas and 
    Electric Company (PG&E)?
        Comment: Entities receiving excess energy may escape an assessment; 
    this will increase the assessment to long-term power contractors, and 
    the increased assessment would be for energy not yet received. This 
    does not appear equitable.
        Comment: Seasonal CVP capacity is provided by CVP generating 
    facilities and ``impacts'' the CVP waterways in the same manner normal 
    sales of CVP capacity and energy might ``impact'' waterways. To 
    disregard an allocation to this type of sale would allow certain 
    customers to benefit from CVP power without paying for a portion of the 
    Restoration Fund.
        Comment: Excess power sales should be assessed because those end 
    users are also benefiting from the CVP.
        Response: Western sells two types of surplus power: surplus energy 
    and surplus capacity. Surplus power is only available for sale by 
    Western after contractual obligations are fulfilled. Western proposed 
    the total power Restoration Fund payment obligation be assessed to the 
    CVP power contractors that purchase power on a long-term basis because 
    Western believes that the assessment should be made on power sales that 
    are predictable during the year and should be billed to customers that 
    are fully benefiting from the CVP resource. By definition, this 
    excludes sales of surplus power because surplus power is not normally 
    available for a period in excess of 1 year.
        Surplus energy is normally sold to PG&E, under contract number 14-
    06-200-2948A, into EA2. Later, Western may repurchase the energy from 
    PG&E at rates that reflect savings incurred by PG&E in the original 
    purchase price from Western. If EA2 sales are assessed a portion of the 
    total power Restoration Fund payment obligation, the increased cost to 
    PG&E would be reflected in the repurchase of the energy upon withdrawal 
    from EA2, which would result in a higher cost for energy. Such higher 
    costs will be passed on to the CVP power customers in future power 
    rates or the revenue adjustment clause.
        Excess capacity sales may be offered to scheduling utilities 
    normally at rates that reflect Western's costs associated with 
    capacity. Revenues from these sales increase the total revenue 
    available for CVP repayment. If the excess capacity sales included the 
    Restoration Fund assessment, less revenue would be available for the 
    repayment of CVP investment. Furthermore, Western's excess capacity 
    sales compete in the market and the addition of the Restoration Fund 
    assessment may make this service noncompetitive.
    
    Exclude First Preference Customers From the Assessment
    
        Comment: Western's proposed procedures for the collection of 
    Restoration Fund payments provides for two exclusions: EA2 sales and 
    excess capacity sales. A third exclusion should be added for first 
    preference customers because these customers' counties natural 
    resources were appropriated to build facilities of the CVP and because 
    the fish and wildlife restoration goals for the Trinity River are not 
    funded by the Restoration Fund, but by the Trinity River Basin Fish and 
    Wildlife Restoration Program (Pub. L. 98-541).
        Response: The Act was designed to benefit many interests within the 
    State of California. In section 3402 of the Act, Congress provided for 
    a wide variety of purposes. These purposes include the protection, 
    restoration, and enhancement of fish, wildlife, and associated habitats 
    in the Central Valley and Trinity River basins of California; an 
    attempt to achieve a reasonable balance among competing demands for the 
    use of CVP water; and other benefits to particular areas of the State 
    of California, and to the State as a whole. Because the Act and the 
    Restoration Fund were designed to service varied interests, including 
    those within the first preference customers' home counties, Western has 
    chosen not to make payment into the Restoration Fund connected to 
    benefits to be received from the Restoration Fund.
        The first preference customers have, by legislation, been allowed a 
    significant benefit over other preference entities in Western's service 
    area. Other preference entities must compete for an allocation of 
    Federal power under each marketing plan, and many eligible preference 
    entities receive no allocation. Congress sought to compensate these 
    counties for the natural resources appropriated when the Trinity and 
    New Melones facilities were constructed by allowing them this first 
    preference. In all other respects, the first preference customers are 
    to be treated as any other CVP preference power customer. See, Trinity 
    County Public Utilities District, et al. v. Harrington, 781 F.2d 163 
    (9th Cir. 1986). Western has chosen not to administratively extend 
    benefits of the first preference customers by excusing them from 
    payments made into the Restoration Fund.
    
    Project Use
    
        Comment: Are project use sales being assessed?
        Comment: Wouldn't the amount charged to preference customers be 
    less if project use was assessed by Western?
        Response:  Project use is assessed by Reclamation in the amount 
    allocated to the water contractors. Because the allocation percentage 
    used by Reclamation to determine the total power Restoration Fund 
    payment obligation if for commercial power only, and does not include 
    project use, these sales will not be assessed.
    
    Changing the Amount Allocated to Power by Reclamation
    
        Comment: Revise the proposed procedures and eliminate any reference 
    of the willingness to pay whatever Reclamation requests into the 
    Restoration Fund. Congress, not Reclamation, determined the amount to 
    be allocated to power and water.
        Comment: The 18 percent that Reclamation has assessed to power 
    needs to be addressed and made more equitable to all CVP users by 
    placing a larger portion on water users and less on electric 
    contractors.
        Comment: Establish a balancing account to ensure sufficient funds 
    by collecting 10 percent more than Reclamation assesses.
        Response: Western does not have the legal authority to increase or 
    decrease the amount allocated to power by Reclamation. The Act states, 
    ``* * * the Secretary shall assess and collect annual mitigation and 
    restoration fund payments * * * that will result in collection, during 
    each fiscal year, of an amount that can be reasonably expected to equal 
    the amount appropriated each year * * * the Secretary shall require the 
    CVP water and power contractors to make such additional annual payments 
    as are necessary to yield * * * the amount required * * *.'' Although 
    Western has in the past and will in the future attempt to work with 
    Reclamation to assure that Restoration Fund allocations are reasonable, 
    Reclamation has final authority under the Act to determine the level of 
    allocations. Western is collecting the Restoration Fund assessment to 
    the CVP power contractors under the terms of an agreement between 
    Western and Reclamation. Issues regarding the amount allocated to power 
    by Reclamation should be addressed to Reclamation.
    
    Conduct an Informal Workshop Prior to Publication of Final Procedures
    
        Comment: An informal workshop might help to develop a mutually 
    acceptable surcharge for the CVP power customers.
        Comment: Allowing only 5 days between the public information 
    meeting and public comment forum and the final written comments is too 
    restrictive. We urge you to extend the comment period or hold an 
    additional workshop prior to publishing the final procedures in the 
    Federal Register.
        Response: Western believes that interested parties had adequate 
    time to comment on its proposed procedures. In response to customer 
    comments regarding the proposed assessment and collection method, 
    Western attended informal workshops and analyzed various alternative 
    methods to address certain concerns. Upon request, Western shared these 
    analyses at a Northern California Power Agency members meeting on 
    January 13, 1994, and a CVP Customer Technical committee meeting on 
    January 19, 1994. On February 3, 1994, in a letter addressed to the 
    Restoration Fund commentors, Western provided copies of all handouts 
    distributed during the above-mentioned meetings.
    
    Other
    
        Comment: Will Restoration Fund payment impact the current CVP 
    rates?
        Response: No. Western is assessing the total power Restoration Fund 
    payment obligation among the CVP power contractors as a pass-through 
    surcharge from Reclamation. The Restoration Funds are not associated 
    with current CVP rates or power revenues; the funds will not flow 
    through the CVP power repayment study nor will they be deposited into 
    the Reclamation Fund to be applied to the repayment of CVP investment.
        Comment: The proposed procedure involves retroactive billing which 
    is precedent setting and undesirable.
        Response: Western has revised the final procedures. Under the final 
    procedures, CVP power contractors will know the amount of the 
    Restoration Fund assessment at the time the power purchase is made. The 
    assessment month is now defined as the period 1 month prior to the 
    billing month. This is consistent with Western's other current power 
    billing practices.
        Comment: The assessment to the power contractors should be based on 
    CVP revenue requirements.
        Response: Western feels that basing the Restoration Fund assessment 
    on revenue requirements would reflect the cost of the resources rather 
    than the use of those resources. It is Western's position that the 
    Restoration Fund should be assessed based on the actual use of the 
    resource provided rather than the costs associated with that resource.
        Comment: Western's assessment includes both water and electric 
    contract users, therefore users with both water and power contracts 
    receive a double assessment.
        Response: The Act requires an assessment to both CVP power and 
    water contractors. While this type of customer may or may not be the 
    only customers receiving two separate Restoration Fund assessments, 
    these customers are receiving the benefit of two clearly separable 
    resources.
    
    Changes to Proposed Procedures
    
        Western has considered all comments received during the 30-day 
    consultation and comment period from the CVP customers and interested 
    parties and has made changes to the proposed procedures. While the 
    decisions outlined in the final procedures may not reflect a consensus 
    on every issue, Western believes the final procedures to be an 
    equitable distribution of the total Restoration Fund payment obligation 
    among the CVP power customers. The final procedures will provide the 
    mechanism required to assess and collect an amount that can be 
    reasonably expected to equal the amount appropriated by Congress and 
    allocated to power by Reclamation.
        The proposed procedures provided that the total power Restoration 
    Fund payment obligation assigned by Reclamation be prorated over the FY 
    to determine a total monthly obligation. Each month the total monthly 
    obligation was assessed to the CVP power contractors as a ratio of the 
    individual power contractor's delivered or scheduled energy to the 
    total delivered or scheduled energy recorded in the assessment month. 
    The assessment month was previously defined as the month 2 months prior 
    to the billing month. This definition has been changed; the assessment 
    month will be 1 month prior to the billing month. In the final 
    procedures, the total power restoration fund payment obligation will be 
    assessed on a 50/50 basis to both delivered or scheduled energy and 
    capacity. An energy and capacity multiplier will be derived from the 
    prior FY actual delivered or scheduled energy and capacity, adjusted 
    for any anticipated changes to the CVP power contractor base. The 
    multiplier will then be applied during the assessment month to each 
    power contractor's actual current year delivered or scheduled energy 
    and capacity.
        The final procedures include a mid-year review of the assessment 
    method. If the actual amount assessed is 25 percent greater or less 
    than the projected assessments, Western will adjust the energy and 
    capacity multipliers. The CVP power contractors will be notified by 
    letter, and the adjusted multipliers will be applied for the remaining 
    months of the current FY. All other deviations in the amounts actually 
    collected or assessed will be rolled into the following FY assessment. 
    Finally, Western has agreed to review the final procedures at a minimum 
    of every 5 years or to accommodate for unforeseen changes or problems.
    
    Interim Billing Adjustments
    
        The total power Restoration Fund payment obligation assigned by 
    Reclamation to the CVP power contractors for FY 1994 is $7,092,800. In 
    an effort to implement collections for the Restoration Fund, Western 
    began issuing bills during an interim period on November 24, 1993. The 
    total power Restoration Fund payment obligation was prorated among the 
    CVP power contractors, and since November 1993, each CVP power 
    contractor has received a bill reflecting this prorated amount. The 
    amount assessed and collected from the CVP power contractors during the 
    interim period will be compared retroactively to the amount that should 
    be assessed and collected under the terms of the final procedures, as 
    follows:
        Western will prorate the FY 1994 total Restoration Fund payment 
    obligation of $7,092,800 assessing 50 percent of the total to delivered 
    or scheduled energy and 50 percent to delivered or scheduled capacity. 
    This results in an equal assessment of $3,546,400 to delivered or 
    scheduled energy and capacity. Western has determined the FY 1993 total 
    delivered or scheduled energy and capacity and has made adjustments for 
    anticipated changes to the CVP power contractor base. The FY 1994 
    energy multiplier will be equal to $3,546,400 divided by the adjusted 
    delivered or scheduled energy of 7,314,510 megawatt-hours, or 0.48 
    mills/kWh. The FY 1994 capacity multiplier will be equal to $3,546,400 
    divided by the adjusted delivered or scheduled capacity of 14,373 
    megawatts, or $0.25/kilowatt-year. These multipliers will then be 
    applied to each CVP power contractor's actual energy and capacity since 
    October 1, 1993, to determine the total Restoration Fund payment due 
    from the contractor.
        The total Restoration Fund payment due will be netted with the 
    total Restoration Fund payments assessed and collected during the 
    interim period. Any resulting increase/decrease will be assessed in the 
    first Restoration Fund bill issued after the final procedures become 
    effective, which is 30 days after the publication of this notice in the 
    Federal Register. If a CVP power contractor has paid more during the 
    interim period than should have been collected under the terms of the 
    final procedures, that CVP power contractor will not receive an 
    additional FY 1994 assessment until the over-collection meets the 
    current FY 1994 obligation. Late payment charges will accrue on 
    delinquent Restoration Fund payments in accordance with the terms 
    outlined in the final procedures.
    
    Final Procedures
    
    Acronyms and Definitions
    
        As used herein, the following acronyms and definitions apply:
    
    Assessment Month: The service month which is 1 month prior to the 
    billing month. The data derived from this service month will serve as 
    the basis for calculating the monthly Restoration Fund bills.
    Billing Month: The month each CVP power contractor will be billed for 
    the Restoration Fund payment.
    CVP: Central Valley Project.
    CVP Power Contractor: Any entity purchasing firm capacity and/or energy 
    from Western for a period in excess of 1 year.
    CVP Power Contractor's Restoration Fund Payment: The amount recorded as 
    payable on the CVP power contractor's Restoration Fund bill.
    FY: Fiscal year beginning October 1 and ending September 30.
    kWh: Kilowatthour.
    Reclamation: Bureau of Reclamation, United States Department of the 
    Interior.
    Restoration Fund: The Central Valley Project Restoration Fund created 
    by section 3407 of Public Law 102-575, 106 Stat. 4726 et seq.
    Restoration Fund Bill: The instrument prepared and issued monthly by 
    Western as a mechanism for collecting the Restoration Fund payments 
    from the CVP power contractors.
    Total Power Restoration Fund Payment Obligation: The total annual 
    Restoration Fund payment obligation calculated and assigned to the CVP 
    power contractors by Reclamation.
    Western: Western Area Power Administration, United States Department of 
    Energy.
    
    Determination of the Total Power Restoration Fund Payment Obligation
    
        Reclamation is responsible for determining the total power 
    Restoration Fund payment obligation for the CVP power and water 
    contractors. Prior to each FY Reclamation will, by written 
    communication, provide to Western's Area Manager, Sacramento Area 
    Office, the amount determined to be the total power Restoration Fund 
    payment obligation, and a detailed explanation of the computation of 
    the amount. Upon receiving the written communication from Reclamation, 
    Western will notify the CVP power contractors of the total power 
    Restoration Fund payment obligation, and the multipliers to be used in 
    assessing that obligation to the CVP power contractors.
    
    Assessing the Total Power Restoration Fund Payment Obligation
    
        Each FY, Western will prorate the total power Restoration Fund 
    payment obligation to both delivered or scheduled energy and capacity. 
    Western will assess 50 percent of the total power Restoration Fund 
    payment obligation to delivered or scheduled energy and 50 percent to 
    delivered or scheduled capacity. Western will determine an energy and 
    capacity multiplier based on the prior FY total delivered or scheduled 
    energy and capacity amounts, adjusted for any anticipated changes in 
    the CVP power contractor base. The total power Restoration Fund payment 
    obligation for the current FY to be prorated to energy will be divided 
    by the adjusted prior FY delivered or scheduled energy to determine the 
    energy multiplier. The same process will be repeated using the total 
    power Restoration Fund payment obligation prorated to capacity divided 
    by the adjusted prior FY delivered or scheduled capacity to determine 
    the capacity multiplier. During the assessment month, these multipliers 
    will then be applied to each CVP power contractor's scheduled or 
    delivered energy and capacity to determine the power contractor's 
    Restoration Fund payment. The total amount recorded in the assessment 
    month will be reflected in the CVP power contractor's Restoration Fund 
    bill.
    
    Assessing the Total Power Restoration Fund Payment Obligation
    
        Reclamation is responsible for determining the total power 
    Restoration Fund payment obligation for the CVP power and water 
    contractors. Prior to each FY Reclamation will, by written 
    communication, provide to Western's Area Manager, Sacramento Area 
    Office, the amount determined to be the total power Restoration fund 
    payment obligation, and a detailed explanation of the computation of 
    the amount. Upon receiving the written communication from Reclamation, 
    Western will notify the CVP power contractors of the total power 
    Restoration Fund payment obligation, and the multipliers to be used in 
    assessing that obligation to the CVP power contractors.
    
    Assessing the Total Power Restoration Fund Payment Obligation
    
        Reclamation is responsible for determining the total power 
    Restoration Fund payment obligation for the CVP power and water 
    contractors. Prior to each FY Reclamation will, by written 
    communication, provide to Western's Area Manager, Sacramento Area 
    Office, the amount determined to be the total power Restoration fund 
    payment obligation, and a detailed explanation of the computation of 
    the amount. Upon receiving the written communication from Reclamation, 
    Western will notify the CVP power contractors of the total power 
    Restoration Fund payment obligation, and the multipliers to be used in 
    assessing that obligation to the CVP power contractors.
    
    Assessing the Total Power Restoration Fund Payment Obligation
    
        Reclamation is responsible for determining the total power 
    Restoration Fund payment obligation for the CVP power and water 
    contractors. Prior to each FY Reclamation will, by written 
    communication, provide to Western's Area Manager, Sacramento Area 
    Office, the amount determined to be the total power Restoration fund 
    payment obligation, and a detailed explanation of the computation of 
    the amount. Upon receiving the written communication from Reclamation, 
    Western will notify the CVP power contractors of the total power 
    Restoration Fund payment obligation, and the multipliers to be used in 
    assessing that obligation to the CVP power contractors.
    
    Assessing the Total Power Restoration Fund Payment Obligation
    
        Reclamation is responsible for determining the total power 
    Restoration Fund payment obligation for the CVP power and water 
    contractors. Prior to each FY Reclamation will, by written 
    communication, provide to Western's Area Manager, Sacramento Area 
    Office, the amount determined to be the total power Restoration fund 
    payment obligation, and a detailed explanation of the computation of 
    the amount. Upon receiving the written communication from Reclamation, 
    Western will notify the CVP power contractors of the total power 
    Restoration Fund payment obligation, and the multipliers to be used in 
    assessing that obligation to the CVP power contractors.
    
    Collection of CVP Power Contractor's Restoration Fund Bill
    
        Each CVP power contractor will receive a Restoration Fund bill on 
    or about the 25th, but no later than the 30th, of each billing month 
    designating the amount payable. Within 20 days of the date shown on the 
    Restoration Fund bill, the total amount payable as set forth on the 
    bill will be due. The first Restoration Fund billing cycle, for each 
    FY, will begin at least 30 days after (1) October 1 or (2) the date 
    written notification of the total power Restoration Fund payment 
    obligation is received from Reclamation, whichever occurs later.
    
    Payment Due Date
    
        All CVP power contractors' Restoration Fund payments are due and 
    payable by the CVP power contractors before the close of business on 
    the 20th calendar day after the date of issuance of each Restoration 
    Fund bill or the next business day thereafter if said day is a 
    Saturday, Sunday, or Federal holiday.
    
    Late Payment Charges Assessed to Delinquent Restoration Fund Payments
    
        Western will calculate and assess late payment charges on all CVP 
    power Restoration Fund payment obligations which are not paid in full 
    by the due date as specified above. The late payment charge will be the 
    interest accrued on all unpaid balances and will be compounded 
    quarterly at the average prime interest rate values published in the 
    Federal Reserve Bulletin for each calendar quarter.
    
    Deposit of CVP Power Contractor's Restoration Fund Payments into the 
    Restoration Fund
    
        On or about the 21st day of the month following each billing month, 
    Western will deposit all of the CVP power contractors' Restoration Fund 
    payments received, including late payment charges, into the Restoration 
    Fund.
    
    Adjustment to Collections
    
        By April 30, Western will review the Restoration Fund assessments, 
    for the period October 1 through March 31. If the actual amount being 
    assessed is 25 percent greater or less than projected assessments, 
    Western will adjust the delivered or scheduled energy and capacity 
    multipliers for the remaining months of the current FY. The CVP power 
    contractors will be notified by letter, no later than May 15, of any 
    adjustment to the multipliers. Beginning June 1, and continuing 
    throughout the balance of the current FY, the adjusted multipliers will 
    be applied to the CVP power contractors' delivered or scheduled energy 
    and capacity. All other deviations, in the amounts actually collected 
    or assessed, will be rolled into the following FY and added to or 
    subtracted from the amount to be assessed in that FY.
    
    Review Process
    
        Minimally, Western will review the assessment method every 5 years 
    or if one of the following occurs:
        (1) If there is a significant change to or suspension of the 
    legislation,
        (2) If a material issue arises, or
        (3) If an apparent inequity in the assessment method is discovered.
    
    Availability of Information
    
        Information regarding this final procedure, including spreadsheet 
    analysis, comments, letters, memorandums, and other supporting 
    documents made or kept by Western for the purpose of developing these 
    procedures, is available for public inspection and copying at Western's 
    Sacramento Area Office located at 1825 Bell Street, suite 105, 
    Sacramento, CA 95825-1097.
    
    Regulatory Flexibility Analysis
    
        Pursuant to the Regulatory Flexibility Act of 1980, 5 U.S.C. 601 et 
    seq., each agency, when required to publish proposed procedures, is 
    further required to prepare and make available for public comment an 
    initial regulatory flexibility analysis to describe the impact of the 
    procedures on small entities. Western has determined that (1) This 
    rulemaking relates to services offered by Western and, therefore, is 
    not a rule within the purview of the Act and (2) the impacts of an 
    assessment from Western would not cause a substantial adverse economic 
    impact to such entities. The requirements of this Act can be waived if 
    the head of the agency certifies that the rule will not, if 
    promulgated, have a significant economic impact on a substantial number 
    of small entities. By execution of this Federal Register notice, 
    Western's Administrator certifies that no significant economic impact 
    on a substantial number of small entities will occur.
    
    Executive Order 12866
    
        DOE has determined that this is not a significant regulatory action 
    because it does not meet the criteria of Executive Order 12866, 58 FR 
    51735. Western has an exemption from centralized regulatory review 
    under Executive Order 12866; accordingly, no clearance of this 
    procedure by the Office of Management and Budget is required.
    
    Environmental Evaluation
    
        In compliance with the National Environmental Policy Act of 1969, 
    42 U.S.C. 4321 et seq., and the Council on Environmental Quality 
    Regulations (40 CFR part 1500-1508), Reclamation is performing a 
    programmatic environmental impact statement (PEIS) on implementation of 
    the Act. Western is a cooperating agency in that PEIS. The proposed 
    procedures for the Restoration Fund payments covered by this notice 
    fall within Western's routine activities and operations categorical 
    exclusion issued January 7, 1993, and will have no environmental 
    impact.
    
        Issued at Golden, Colorado, March 30, 1994.
    William H. Clagett,
    Administrator.
    [FR Doc. 94-8478 Filed 4-7-94; 8:45 am]
    BILLING CODE 6450-01-M
    
    
    

Document Information

Effective Date:
5/9/1994
Published:
04/08/1994
Department:
Western Area Power Administration
Entry Type:
Uncategorized Document
Action:
Notice of final procedures for the assessment and collection of restoration fund payments from the Central Valley Project power contractors.
Document Number:
94-8478
Dates:
The final procedures will become effective May 9, 1994 and will remain in effect until superseded.
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: April 8, 1994