2019-06837. Standard Review Plan (SRP) 13.4, Operational Programs  

  • Start Preamble

    AGENCY:

    Nuclear Regulatory Commission.

    ACTION:

    Standard review plan-final section revision; issuance.

    SUMMARY:

    The U.S. Nuclear Regulatory Commission (NRC) is issuing final Revision 4 to Section 13.4, “Operational Programs” of NUREG-0800, “Standard Review Plan (SRP) for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition.”

    DATES:

    The effective date of this SRP update is April 8, 2019.

    ADDRESSES:

    Please refer to Docket ID NRC-2018-0196 when contacting the NRC about the availability of information regarding this document. You may obtain publicly-available information related to this document using any of the following methods:

    • Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2018-0196. Address questions about NRC dockets IDs in Regulations.gov to Jennifer Borges; telephone: 301-287-9127; email: Jennifer.Borges@nrc.gov. For technical questions, contact the individual(s) listed in the FOR FURTHER INFORMATION CONTACT section of this document.
    • NRC's Agencywide Documents Access and Management System (ADAMS): You may obtain publicly-available documents online in the ADAMS Public Documents collection at http://www.nrc.gov/​reading-rm/​adams.html. To begin the search, select “Begin Web-based ADAMS Search.” For problems with ADAMS, please contact the NRC's Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or by email to pdr.resource@nrc.gov. The final revision, is available in ADAMS under the following Accession No. ML18344A032.
    • NRC's PDR: You may examine and purchase copies of public documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
    Start Further Info

    FOR FURTHER INFORMATION CONTACT:

    Mark D. Notich, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-3053, email: Mark.Notich@nrc.gov.

    End Further Info End Preamble Start Supplemental Information

    SUPPLEMENTARY INFORMATION:

    I. Background

    On September 11, 2018 (83 FR 45995), the NRC published for public comment proposed Revision 4 of Section 13.4, “Operational Programs” of NUREG-0800, “Standard Review Plan (SRP) for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition.” The public comment period closed on November 13, 2018.

    II. Backfitting and Issue Finality

    Chapter 13 of the SRP provides guidance to the staff for conduct of operations under part 52 of title 10 of the Code of Federal Regulations (10 CFR). Section 13.4 of the SRP provides information on operational programs that must be addressed during the review of combined license (COL), early site permit (ESP), standard design certification, and operating license (OL) applications.

    Issuance of this SRP section revision does not constitute backfitting as defined in 10 CFR 50.109 (the Backfit Rule) nor is it inconsistent with the issue finality provisions in 10 CFR part 52. The NRC's position is based upon the following considerations.

    1. The SRP positions do not constitute backfitting, inasmuch as the SRP is guidance direct to the NRC staff with respect to its regulatory responsibilities.

    The SRP provides guidance to the NRC staff on how to review an application for NRC regulatory approval in the form of licensing. Changes in guidance intended for use by only the staff are not matters that constitute backfitting as that term is defined in 10 CFR 50.109(a)(1) or involve the issue finality provisions of 10 CFR part 52.

    2. Backfitting and issue finality—with certain exceptions discussed below—do not apply to current or future applicants.

    Applicants and potential applicants are not, with certain exceptions, the subject of either the Backfit Rule or any issue finality provisions under 10 CFR part 52. This is because neither the Backfit Rule nor the issue finality provisions under 10 CFR part 52 were intended to apply to every NRC action that substantially changes the expectations of current and future applicants.

    The exceptions to the general principle are applicable whenever a 10 CFR part 50 operating license applicant references a construction permit or a 10 CFR part 52 combined license applicant references a license (e.g., an early site permit) or an NRC regulatory approval (e.g., a design certification rule) for which specified issue finality provisions apply.

    The NRC staff does not currently intend to impose the positions represented in this final SRP section in a manner that constitutes backfitting or is inconsistent with any issue finality provision of 10 CFR part 52. If in the future the NRC staff seeks to impose a position stated in this SRP section in a manner that would constitute backfitting or be inconsistent with these issue finality provisions, the NRC staff must make the showing as set forth in the Backfit Rule or address the regulatory criteria set forth in the applicable issue finality provision, as applicable, that would allow the staff to impose the position.

    3. The NRC staff has no intention to impose the SRP positions on existing nuclear power plant licensees either now or in the future (absent a voluntary request for a change from the licensee, holder of a regulatory approval or a design certification applicant).

    The NRC staff does not intend to impose or apply the positions described in this final SRP section to existing (already issued) licenses (e.g., operating licenses and combined licenses) and regulatory approvals. Hence, the issuance of this SRP guidance—even if considered guidance subject to the Backfit Rule or the issue finality provisions in 10 CFR part 52—would not need to be evaluated as if it were a backfit or as being inconsistent with issue finality provisions. If, in the future, the NRC staff seeks to impose a position in the SRP on holders of already issued licenses in a manner that would constitute backfitting or does not provide issue finality as described in the applicable issue finality provision, then the staff must make a showing as set forth in the Backfit Rule or address the criteria in the applicable issue finality provision, as applicable, that would allow the staff to impose the position.

    III. Congressional Review Act

    The Office of Management and Budget makes the determination that the United States Nuclear Regulatory Commission action titled NUREG-0800, “Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants; LWR Edition,” Revision 4 of SRP 13.4, “Operational Programs” is non-major under the Congressional Review Act.

    Start Signature
    Start Printed Page 13969

    Dated at Rockville, Maryland, this 3rd day of April 2019.

    For the Nuclear Regulatory Commission.

    Jennivine K. Rankin,

    Acting Chief, Division of Licensing, Siting, and Environmental Analysis, Licensing Branch 3, Office of New Reactors.

    End Signature End Supplemental Information

    [FR Doc. 2019-06837 Filed 4-5-19; 8:45 am]

    BILLING CODE 7590-01-P

Document Information

Effective Date:
4/8/2019
Published:
04/08/2019
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Action:
Standard review plan-final section revision; issuance.
Document Number:
2019-06837
Dates:
The effective date of this SRP update is April 8, 2019.
Pages:
13968-13969 (2 pages)
Docket Numbers:
NRC-2018-0196
PDF File:
2019-06837.pdf