[Federal Register Volume 62, Number 84 (Thursday, May 1, 1997)]
[Notices]
[Pages 23811-23812]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 97-11294]
[[Page 23811]]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-361 and 50-362]
Southern California Edison Company; Notice of Consideration of
Issuance of Amendment to Facility Operating Licenses, Proposed No
Significant Hazards Consideration Determination, and Opportunity for a
Hearing
The U.S. Nuclear Regulatory Commission (the Commission) is
considering issuance of an amendment to Facility Operating License Nos.
NPF-10 and NPF-15, issued to Southern California Edison Company (the
licensee) for operation of the San Onofre Nuclear Generating Station
(SONGS), Unit Nos. 2 and 3, located in San Diego County, California.
The proposed amendment would revise Surveillance Requirement (SR)
3.8.1.8 and applicable Bases to Technical Specification (TS) 3.8.1,
``AC Sources--Operating.'' This change will allow credit for overlap
testing for performance of SR 3.8.1.8.
The exigent circumstances for this TS amendment request exists
because it is needed by mid-May 1997 to avoid an unnecessary challenge
to safety systems by performing an actual transfer of the safety-
related buses of the operating unit to the unit auxiliary transformer
of the shutdown unit. This TS amendment will permit preventive
maintenance on the SONGS Unit 3 reserve auxiliary transformers and
associated hardware during this unit's ongoing refueling outage.
Performance of preventive maintenance on these transformers during the
current outage will maintain these components in optimum operational
condition.
Before issuance of the proposed license amendment, the Commission
will have made findings required by the Atomic Energy Act of 1954, as
amended (the Act) and the Commission's regulations.
Pursuant to 10 CFR 50.91(a)(6) for amendments to be granted under
exigent circumstances, the NRC staff must determine that the amendment
request involves no significant hazards consideration. Under the
Commission's regulations in 10 CFR 50.92, this means that operation of
the facility in accordance with the proposed amendment would not (1)
involve a significant increase in the probability or consequences of an
accident previously evaluated; or (2) create the possibility of a new
or different kind of accident from any accident previously evaluated;
or (3) involve a significant reduction in a margin of safety. As
required by 10 CFR 50.91(a), the licensee has provided its analysis of
the issue of no significant hazards consideration, which is presented
below:
1. The proposed change does not involve a significant increase
in the probability or consequences of any accident previously
evaluated.
The proposed change has no impact on any previously evaluated
accident. It allows overlapping testing to assure operation of
different AC power source alignments which have been previously
evaluated.
Therefore, the proposed change will not involve a significant
increase in the probability or consequences of any accident
previously evaluated.
2. The proposed change does not create the possibility of a new
or different kind of accident from any accident previously
evaluated.
The proposed change does not affect facility operation. It only
changes the method of testing of AC power sources.
Therefore, the proposed change will not create the possibility
of a new or different kind of accident from any accident previously
evaluated.
3. The proposed change does not involve a significant reduction
in a margin of safety.
The proposed change allows overlapping testing to assure
operation of different AC power source alignments. Overlap testing
provides an equally valid test of the capability of the alternate
offsite power source.
Therefore, the proposed change will not involve a significant
reduction in a margin of safety.
The NRC staff has reviewed the licensee's analysis and, based on
this review, it appears that the three standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff proposes to determine that the
amendment request involves no significant hazards consideration.
The Commission is seeking public comments on this proposed
determination. Any comments received within 14 days after the date of
publication of this notice will be considered in making any final
determination.
Normally, the Commission will not issue the amendment until the
expiration of the 14-day notice period. However, should circumstances
change during the notice period, such that failure to act in a timely
way would result, for example, in derating or shutdown of the facility,
the Commission may issue the license amendment before the expiration of
the 14-day notice period, provided that its final determination is that
the amendment involves no significant hazards consideration. The final
determination will consider all public and State comments received.
Should the Commission take this action, it will publish in the Federal
Register a notice of issuance. The Commission expects that the need to
take this action will occur very infrequently.
Written comments may be submitted by mail to the Chief, Rules
Review and Directives Branch, Division of Freedom of Information and
Publications Services, Office of Administration, U.S. Nuclear
Regulatory Commission, Washington, DC 20555-0001, and should cite the
publication date and page number of this Federal Register notice.
Written comments may also be delivered to Room 6D22, Two White Flint
North, 11545 Rockville Pike, Rockville, Maryland, from 7:30 a.m. to
4:15 p.m. Federal workdays. Copies of written comments received may be
examined at the NRC Public Document Room, the Gelman Building, 2120 L
Street, NW., Washington, DC.
The filing of requests for hearing and petitions for leave to
intervene is discussed below.
By June 2, 1997, the licensee may file a request for a hearing with
respect to issuance of the amendment to the subject facility operating
license and any person whose interest may be affected by this
proceeding and who wishes to participate as a party in the proceeding
must file a written request for a hearing and a petition for leave to
intervene. Requests for a hearing and a petition for leave to intervene
shall be filed in accordance with the Commission's ``Rules of Practice
for Domestic Licensing Proceedings'' in 10 CFR Part 2. Interested
persons should consult a current copy of 10 CFR 2.714 which is
available at the Commission's Public Document Room, the Gelman
Building, 2120 L Street, NW., Washington, DC, and at the local public
document room located at the Main Library, University of California, PO
Box 19557, Irvine, California 92713. If a request for a hearing or
petition for leave to intervene is filed by the above date, the
Commission or an Atomic Safety and Licensing Board, designated by the
Commission or by the Chairman of the Atomic Safety and Licensing Board
Panel, will rule on the request and/or petition; and the Secretary or
the designated Atomic Safety and Licensing Board will issue a notice of
hearing or an appropriate order.
As required by 10 CFR 2.714, a petition for leave to intervene
shall set forth with particularity the interest of the petitioner in
the proceeding, and how that interest may be affected by the results of
the proceeding. The petition should specifically explain the reasons
why intervention should be permitted with particular reference to the
following factors: (1) The nature of the petitioner's right under the
Act to be
[[Page 23812]]
made a party to the proceeding; (2) the nature and extent of the
petitioner's property, financial, or other interest in the proceeding;
and (3) the possible effect of any order which may be entered in the
proceeding on the petitioner's interest. The petition should also
identify the specific aspect(s) of the subject matter of the proceeding
as to which petitioner wishes to intervene. Any person who has filed a
petition for leave to intervene or who has been admitted as a party may
amend the petition without requesting leave of the Board up to 15 days
prior to the first prehearing conference scheduled in the proceeding,
but such an amended petition must satisfy the specificity requirements
described above.
Not later than 15 days prior to the first prehearing conference
scheduled in the proceeding, a petitioner shall file a supplement to
the petition to intervene which must include a list of the contentions
which are sought to be litigated in the matter. Each contention must
consist of a specific statement of the issue of law or fact to be
raised or controverted. In addition, the petitioner shall provide a
brief explanation of the bases of the contention and a concise
statement of the alleged facts or expert opinion which support the
contention and on which the petitioner intends to rely in proving the
contention at the hearing. The petitioner must also provide references
to those specific sources and documents of which the petitioner is
aware and on which the petitioner intends to rely to establish those
facts or expert opinion. Petitioner must provide sufficient information
to show that a genuine dispute exists with the applicant on a material
issue of law or fact. Contentions shall be limited to matters within
the scope of the amendment under consideration. The contention must be
one which, if proven, would entitle the petitioner to relief. A
petitioner who fails to file such a supplement which satisfies these
requirements with respect to at least one contention will not be
permitted to participate as a party.
Those permitted to intervene become parties to the proceeding,
subject to any limitations in the order granting leave to intervene,
and have the opportunity to participate fully in the conduct of the
hearing, including the opportunity to present evidence and cross-
examine witnesses.
If the amendment is issued before the expiration of the 30-day
hearing period, the Commission will make a final determination on the
issue of no significant hazards consideration. If a hearing is
requested, the final determination will serve to decide when the
hearing is held.
If the final determination is that the amendment request involves
no significant hazards consideration, the Commission may issue the
amendment and make it immediately effective, notwithstanding the
request for a hearing. Any hearing held would take place after issuance
of the amendment.
If the final determination is that the amendment request involves a
significant hazards consideration, any hearing held would take place
before the issuance of any amendment.
A request for a hearing or a petition for leave to intervene must
be filed with the Secretary of the Commission, U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001, Attention: Docketing and
Services Branch, or may be delivered to the Commission's Public
Document Room, the Gelman Building, 2120 L Street, NW., Washington, DC,
by the above date. Where petitions are filed during the last 10 days of
the notice period, it is requested that the petitioner promptly so
inform the Commission by a toll-free telephone call to Western Union at
1-(800) 248-5100 (in Missouri 1-(800) 342-6700). The Western Union
operator should be given Datagram Identification Number N1023 and the
following message addressed to William H. Bateman, Director, Project
Directorate IV-2: petitioner's name and telephone number, date petition
was mailed, plant name, and publication date and page number of this
Federal Register notice. A copy of the petition should also be sent to
the Office of the General Counsel, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, and to T. E. Oubre, Esquire, Southern
California Edison Company, P.O. Box 800, Rosemead, California 91770,
attorney for the licensee.
Nontimely filings of petitions for leave to intervene, amended
petitions, supplemental petitions and/or requests for hearing will not
be entertained absent a determination by the Commission, the presiding
officer or the presiding Atomic Safety and Licensing Board that the
petition and/or request should be granted based upon a balancing of the
factors specified in 10 CFR 2.714(a)(1) (i)-(v) and 2.714(d).
For further details with respect to this action, see the
application for amendments dated April 15, 1997, which is available for
public inspection at the Commission's Public Document Room, the Gelman
Building, 2120 L Street, NW., Washington, DC, and at the local public
document room, located at the Main Library, University of California,
P.O. Box 19557, Irvine, California 92713.
Dated at Rockville, Maryland, this 25th day of April 1997.
For the Nuclear Regulatory Commission.
Mel B. Fields,
Project Manager, Project Directorate IV-2, Division of Reactor Projects
III/IV, Office of Nuclear Reactor Regulation.
[FR Doc. 97-11294 Filed 4-30-97; 8:45 am]
BILLING CODE 7590-01-P