99-11608. Reliant Energy Gas Transmission Company; Notice of Request Under Blanket Authorization
[Federal Register Volume 64, Number 89 (Monday, May 10, 1999)]
[Notices]
[Page 25032]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 99-11608]
[[Page 25032]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP99-371-000]
Reliant Energy Gas Transmission Company; Notice of Request Under
Blanket Authorization
May 4, 1999.
Take notice that on April 29, 1999, Reliant Energy Gas Transmission
Company (``REGT''), 1111 Louisiana Street, Houston, Texas 77002-5231,
filed in Docket No. CP99-371-000 a request pursuant to Sections 157.205
and 157.211 of the Commission's Regulations (18 CFR 157.205 and 157.211
under the Natural Gas Act (NGA) for authorization to construct and
operate delivery point facilities in Arkansas under REGT's blanket
certificate issued in Docket Nos. CP82-384-000 and CP82-384-001,
pursuant to Section 7 of the NGA, all as more fully set forth in the
request which is filing may be viewed on the web at http://
www.ferc.fed.us/online/htm (call 202-208-2222 for assistance).
REGT specifically proposes to install a 6-inch meter station, 3-
inch regulator, and approximately 200 feet of 6-inch pipe on Line LT-1
in Lafayette County, Arkansas to provide additional service to Entergy
Couch power plant. It is stated that the maximum deliverable volumes
will be 7,300 Mdth equivalent annually and 20 MDth equivalent on a peak
day. It is asserted that the cost of these new facilities is estimated
to be $138,097.
Any person or the Commission's Staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rule (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to section 157.205 of
the Regulations under the NGA (18 CFR 157.205) a protest to the
request. If no protest is filed within the time allowed therefor, the
proposed activity shall be deemed to be authorized effective the date
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the NGA.
Linwood A. Watson, Jr.,
Acting Secretary.
[FR Doc. 99-11608 Filed 5-7-99; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 05/10/1999
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 99-11608
- Pages:
- 25032-25032 (1 pages)
- Docket Numbers:
- Docket No. CP99-371-000
- PDF File:
-
99-11608.pdf