2016-10823. Defense Federal Acquisition Regulation Supplement: Multiyear Contract Requirements (DFARS Case 2015-D009)
-
Start Preamble
AGENCY:
Defense Acquisition Regulations System, Department of Defense (DoD).
ACTION:
Final rule.
SUMMARY:
DoD is issuing a final rule amending the Defense Federal Acquisition Regulation Supplement (DFARS) to implement a section of the National Defense Authorization Act for Fiscal Year 2015 and a section of the Department of Defense Appropriations Act, 2015, which address various requirements for multiyear contracts.
DATES:
Effective May 10, 2016.
Start Further InfoFOR FURTHER INFORMATION CONTACT:
Mr. Christopher Stiller, telephone 571-372-6176.
End Further Info End Preamble Start Supplemental InformationSUPPLEMENTARY INFORMATION:
I. Background
DoD published a proposed rule in the Federal Register at 80 FR 81499 on December 30, 2015, to amend the DFARS to implement section 816 of the National Defense Authorization Act for Fiscal Year 2015 (Pub. L. 113-291) and section 8010 of the Department of Defense Appropriations Act, 2015 (Division C, Title VIII of Pub. L. 113-235), which address various requirements for multiyear contracts. There were no public comments submitted in response to the proposed rule. There are no changes from the proposed rule made in the final rule.
II. Applicability to Contracts at or Below the Simplified Acquisition Threshold (SAT) and for Commercial Items, Including Commercially Available Off-the-Shelf (COTS) Items
This rule does not add any new provisions or clauses or impact any existing provisions or clauses.
III. Executive Orders 12866 and 13563
Executive Orders (E.O.s) 12866 and 13563 direct agencies to assess all costs and benefits of available regulatory alternatives and, if regulation is necessary, to select regulatory approaches that maximize net benefits (including potential economic, Start Printed Page 28731environmental, public health and safety effects, distributive impacts, and equity). E.O. 13563 emphasizes the importance of quantifying both costs and benefits, of reducing costs, of harmonizing rules, and of promoting flexibility. This is not a significant regulatory action and, therefore, was not subject to review under section 6(b) of E.O. 12866, Regulatory Planning and Review, dated September 30, 1993. This rule is not a major rule under 5 U.S.C. 804.
IV. Regulatory Flexibility Act
A final regulatory flexibility analysis (FRFA) has been prepared consistent with the Regulatory Flexibility Act, 5 U.S.C. 601, et seq. The FRFA is summarized as follows:
The purpose of this rule is to implement section 816 of the National Defense Authorization Act for Fiscal Year 2015 and section 8010 of the Department of Defense Appropriations Act, 2015, which address various requirements for multiyear contracts. The rule will amend the Defense Federal Acquisition Regulation Supplement to require the head of agency to—
- Provide written notice to the congressional defense committees at least 30 days before termination of any multiyear contract; and
- For defense acquisition programs specifically authorized by law to be carried out using multiyear authority, ensure the Secretary of Defense certifies to Congress certain conditions for the multiyear contract have been met no later than 30 days before entry into the contract.
No comments were received from the public regarding the initial regulatory flexibility analysis.
The rule is not expected to impact small entities, because the rule applies to multiyear contract authorities for specific major defense acquisition programs for which small entities would not have the capacity or infrastructure to fulfill or sustain. Small entities may perform under multiyear contracts as subcontractors; however, the rule invokes requirements that apply at the prime contract level.
This rule does not create any new reporting or recordkeeping requirements.
There are no known significant alternatives to the rule. The impact of this rule on small business is not expected to be significant because it only affects DoD internal operating procedures.
V. Paperwork Reduction Act
The rule does not contain any information collection requirements that require the approval of the Office of Management and Budget under the Paperwork Reduction Act (44 U.S.C. chapter 35).
Start List of SubjectsList of Subjects in 48 CFR Part 217
- Government procurement
Jennifer Hawes,
Editor, Defense Acquisition Regulations System.
Therefore, 48 CFR part 217 is amended as follows:
Start PartPART 217—SPECIAL CONTRACTING METHODS
End Part Start Amendment Part1. The authority citation for 48 CFR part 217 continues to read as follows:
End Amendment Part Start Amendment Part2. Revise section 217.170(b) to read as follows:
End Amendment PartGeneral.* * * * *(b) The head of the agency must provide written notice to the congressional defense committees at least 30 days before termination of any multiyear contract (section 8010 of Division C, Title VIII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and similar sections in subsequent DoD appropriations acts).
* * * * *3. Amend section 217.172—
End Amendment Part Start Amendment Parta. In paragraph (c), by removing “ 10 U.S.C. 2306b(i)(3)” and adding “10 U.S.C. 2306b(i)(1)” in its place;
End Amendment Part Start Amendment Partb. In paragraph (e)(1), by removing the word “and”;
End Amendment Part Start Amendment Partc. In paragraph (e)(2), by removing the period and adding a semicolon in its place;
End Amendment Part Start Amendment Partd. By adding paragraphs (e)(3), (4), and (5);
End Amendment Part Start Amendment Parte. In paragraph (h) introductory text, by removing “under the authority described in paragraph (b) of this section:” and adding “for a defense acquisition program that has been specifically authorized by law to be carried out using multiyear contract authority:” in its place;
End Amendment Part Start Amendment Partf. In paragraph (h)(2) introductory text, by removing “March 1 of the year in which the Secretary requests legislative authority to enter” and adding “30 days before entry” in its place and by removing “ 10 U.S.C. 2306b(i)(1)(A) through (G)” and adding “10 U.S.C. 2306b(i)(3)” in its place;
End Amendment Part Start Amendment Partg. In paragraph (h)(2)(i)—
End Amendment Part Start Amendment Parti. By removing “FAR 17.105” and adding “FAR 17.105-1” in its places;
End Amendment Part Start Amendment Partii. By adding a comma after “(5)”; and
End Amendment Part Start Amendment Partiii. By removing “10 U.S.C. 2306b(i)(1)(A)” and adding “10 U.S.C. 2306b(i)(3)(A)” in its place;
End Amendment Part Start Amendment Parth. In paragraph (h)(2)(ii), by removing “ 10 U.S.C. 2306b(i)(1)(B)” and adding “10 U.S.C. 2306b(i)(3)(B)” in its place;
End Amendment Part Start Amendment Parti. In paragraph (h)(2)(iii), by removing “ 10 U.S.C. 2306b(i)(1)(C)” and adding “10 U.S.C. 2306b(i)(3)(C)” in its place;
End Amendment Part Start Amendment Partj. In paragraph (h)(2)(iv), by removing “ 10 U.S.C. 2306b(i)(1)(D)” and adding “10 U.S.C. 2306b(i)(3)(D)” in its place;
End Amendment Part Start Amendment Partk. In paragraph (h)(2)(v), by removing “ 10 U.S.C. 2306b(i)(1)(E)” and adding “10 U.S.C. 2306b(i)(3)(E)” in its place;
End Amendment Part Start Amendment Partl. In paragraph (h)(2)(vi), by removing “ 10 U.S.C. 2306b(i)(1)(F)” and adding “10 U.S.C. 2306b(i)(3)(F)” in its place;
End Amendment Part Start Amendment Partm. In paragraph (h)(2)(vii), by removing “ 10 U.S.C. 2306b(i)(1)(G)” and adding “10 U.S.C. 2306b(i)(3)(G)” in its place;
End Amendment Part Start Amendment Partn. In paragraph (h)(3), by removing “ 10 U.S.C. 2306b(i)(4)(A)” and adding “10 U.S.C. 2306b(i)(5)(A)” in its place;
End Amendment Part Start Amendment Parto. In paragraph (h)(4), by removing “ 10 U.S.C. 2306b(i)(4)(B)” and adding “10 U.S.C. 2306b(i)(5)(B)” in its place;
End Amendment Part Start Amendment Partp. In paragraph (h)(5), by removing “ 10 U.S.C. 2306b(i)(5)” and adding “10 U.S.C. 2306b(i)(6)” in its place;
End Amendment Part Start Amendment Partq. In paragraph (h)(6), by removing “ 10 U.S.C. 2306b(i)(6)” and adding “10 U.S.C. 2306b(i)(7)” in its place;
End Amendment Part Start Amendment Partr. Removing paragraph (h)(7);
End Amendment Part Start Amendment Parts. Redesignating paragraph (h)(8) as (h)(7); and
End Amendment Part Start Amendment Partt. In newly redesignated paragraph (h)(7) introductory text, adding “( 10 U.S.C. 2306b(i)(4))” after “law's specific savings requirement” before the period.
End Amendment PartThe additions read as follows:
Multiyear contracts for supplies.* * * * *(e) * * *
(3) Cancellation provisions in the contract do not include consideration of recurring manufacturing costs of the contractor associated with the production of unfunded units to be delivered under the contract;
(4) The contract provides that payments to the contractor under the contract shall not be made in advance of incurred costs on funded units; and
(5) The contract does not provide for a price adjustment based on a failure to award a follow-on contract (section 8010 of Division C, Title VIII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and similar sections in subsequent DoD appropriations acts).
* * * * *[FR Doc. 2016-10823 Filed 5-9-16; 8:45 am]
BILLING CODE 5001-06-P
Document Information
- Effective Date:
- 5/10/2016
- Published:
- 05/10/2016
- Department:
- Defense Acquisition Regulations System
- Entry Type:
- Rule
- Action:
- Final rule.
- Document Number:
- 2016-10823
- Dates:
- Effective May 10, 2016.
- Pages:
- 28730-28731 (2 pages)
- Docket Numbers:
- Docket DARS-2015-0067
- RINs:
- 0750-AI80: Multiyear Contract Requirements (DFARS Case 2015-D009)
- RIN Links:
- https://www.federalregister.gov/regulations/0750-AI80/multiyear-contract-requirements-dfars-case-2015-d009-
- Topics:
- Government procurement
- PDF File:
- 2016-10823.pdf
- CFR: (2)
- 48 CFR 217.170
- 48 CFR 217.172