2023-09941. Natural Gas Pipeline Company of America LLC; Notice of Request Under Blanket Authorization and Establishing Intervention and Protest Deadline
-
Start Preamble
Take notice that on April 26, 2023, Natural Gas Pipeline Company of America LLC (NGPA), 3250 Lacey Road, Suite 700, Downers Grove, Illinois 60515, filed in the above referenced docket, a prior notice request pursuant to sections 157.205 and 157.208(b) of the Federal Energy Regulatory Commission's regulations under the Natural Gas Act (NGA), and NGPA's blanket certificate issued in Docket No. CP82–402–000, for authorization to perform a miscellaneous rearrangement project that involves (1) the replacement of approximately 1.10-mile-long, 36-inch-diameter portion of Natural's Herscher Discharge Line (HDL) that currently traverses the center of Burlington Northern Santa Fe Railway Company's (BNSF) property in Will County, Illinois with a 2.18-mile-long, 36-inch-diameter pipe located on the southern and western borders of BNSF's property; (2) the automation of an existing mainline valve (MLV) 607 located in Will County, Illinois; and (3) the installation of a new automated MLV GL608 located in Grundy County, Illinois (HDL Relocation Project). The proposed relocation of HDL was requested by BNSF to accommodate construction of a new intermodal rail car switching yard by BNSF on that property. This Project will not result in the reduction of system capacity or the termination of any services and will not affect the quality of service provided to any shipper on the NGPA system. The estimated cost for the project is $14,000,000, all as more fully set forth in the request which is on file with the Commission and open to public inspection.
In addition to publishing the full text of this document in the Federal Register , the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page ( www.ferc.gov) using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission's Public Reference Room. For assistance, contact the Federal Energy Regulatory Commission at FercOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TTY (202) 502–8659.
Any questions concerning this request should be directed to Francisco Tarin, Director, Regulatory, for Kinder Morgan Inc., as Operator of Natural Gas Pipeline Company of America LLC, 2 North Nevada Avenue, Colorado Springs, Colorado 80903, at (719) 667–7515, or francisco_tarin@kindermorgan.com.Start Printed Page 30119
Public Participation
There are three ways to become involved in the Commission's review of this project: you can file a protest to the project, you can file a motion to intervene in the proceeding, and you can file comments on the project. There is no fee or cost for filing protests, motions to intervene, or comments. The deadline for filing protests, motions to intervene, and comments is 5:00 p.m. Eastern Time on July 3, 2023. How to file protests, motions to intervene, and comments is explained below.
Protests
Pursuant to section 157.205 of the Commission's regulations under the NGA,[1] any person[2] or the Commission's staff may file a protest to the request. If no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission.
Protests must comply with the requirements specified in section 157.205(e) of the Commission's regulations, [3] and must be submitted by the protest deadline, which is July 3, 2023. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor.
Interventions
Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission's Rules of Practice and Procedure [4] and the regulations under the NGA [5] by the intervention deadline for the project, which is July 3, 2023. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https://www.ferc.gov/resources/guides/how-to/intervene.asp.
All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission's Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties.
Comments
Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit your comments on or before July 3, 2023. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding.
How To File Protests, Interventions, and Comments
There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP23–255–000 in your submission.
(1) You may file your protest, motion to intervene, and comments by using the Commission's eFiling feature, which is located on the Commission's website ( www.ferc.gov) under the link to Documents and Filings. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making; first select “General” and then select “Protest”, “Intervention”, or “Comment on a Filing”; or [6]
(2) You can file a paper copy of your submission by mailing it to the address below. Your submission must reference the Project docket number CP23–255–000.
To file via USPS: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426
To file via any other method: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852
The Commission encourages electronic filing of submissions (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FercOnlineSupport@ferc.gov.
Protests and motions to intervene must be served on the applicant either by mail or email (with a link to the document) at: Francisco Tarin, Director, Regulatory, for Kinder Morgan Inc., as Operator of Natural Gas Pipeline Company of America LLC, 2 North Nevada Avenue, Colorado Springs, Colorado 80903, or francisco_tarin@kindermorgan.com. Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online.
Tracking the Proceeding
Throughout the proceeding, additional information about the project will be available from the Commission's Office of External Affairs, at (866) 208–FERC, or on the FERC website at www.ferc.gov using the “eLibrary” link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to www.ferc.gov/docs-filing/esubscription.asp.
Start SignatureDated: May 4, 2023.
Kimberly D. Bose,
Secretary.
Footnotes
2. Persons include individuals, organizations, businesses, municipalities, and other entities. 18 CFR 385.102(d).
Back to Citation6. Additionally, you may file your comments electronically by using the eComment feature, which is located on the Commission's website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project.
Back to Citation[FR Doc. 2023–09941 Filed 5–9–23; 8:45 am]
BILLING CODE 6717–01–P
Document Information
- Published:
- 05/10/2023
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 2023-09941
- Pages:
- 30118-30119 (2 pages)
- Docket Numbers:
- Docket No. CP23-255-000
- PDF File:
- 2023-09941.pdf