99-11818. Thermal Science, Inc.; Order Imposing Civil Monetary Penalty  

  • [Federal Register Volume 64, Number 90 (Tuesday, May 11, 1999)]
    [Notices]
    [Pages 25376-25383]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 99-11818]
    
    
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [EA 95-009]
    
    
    Thermal Science, Inc.; Order Imposing Civil Monetary Penalty
    
    I
    
        Thermal Science, Inc. (TSI) is the manufacturer and vendor of fire 
    barrier products known generally as Thermo-Lag. TSI began marketing 
    this product in the early 1980s to licensees of the United States 
    Nuclear Regulatory Commission (NRC) for use in nuclear power plants. 
    TSI represented that Thermo-Lag had undergone independent testing by 
    Industrial Testing Laboratories, Inc. (ITL). Using ITL stationery, TSI 
    issued reports in ITL's name, making it appear that the reports were 
    written by ITL, when in fact they were written by TSI. Many NRC 
    licensees thereafter purchased Thermo-Lag to meet the NRC's fire 
    protection requirements, codified in 10 CFR 50.48 and appendix R to 
    part 50.
    
    II
    
        In 1989 the NRC began receiving licensee reports of problems with 
    installed Thermo-Lag. As part of a subsequent NRC investigation, TSI 
    was questioned in the fall of 1991 about the testing and installation 
    of Thermo-Lag. TSI continued to represent that its product had been 
    independently tested by ITL. However, during an NRC inspection of TSI's 
    facility in December
    
    [[Page 25377]]
    
    1991, it was learned that TSI, not ITL, had written the test reports, 
    and that ITL had very limited involvement in the testing process. In 
    1992 the United States Department of Justice began a criminal 
    investigation of the matter, resulting in indictments and a jury trial 
    in the United States District Court for the District of Maryland in 
    1995. The jury acquitted TSI and TSI's President, Ruben Feldman, on all 
    of the criminal charges. A written Notice of Violation and Proposed 
    Imposition of Civil Penalties (Notice) in the amount of $900,000 was 
    subsequently served upon TSI by letter dated October 1, 1996. The 
    Notice sets forth nine violations of 10 CFR 50.5, the NRC's 
    ``Deliberate Wrongdoer'' rule.
        TSI delayed filing a response to the Notice while it sought a 
    preliminary injunction of NRC's administrative process from the United 
    States District Court for the Eastern District of Missouri. The 
    District Court finally denied the injunction request and dismissed 
    TSI's cause of action by opinion dated June 23, 1998, holding that TSI 
    must exhaust its administrative remedies before seeking judicial 
    relief. Thereafter, on July 7, 1998, TSI filed its answer to the 
    Notice. In its answer, TSI set forth its legal objections to the 
    Notice, and denied each of the 10 CFR 50.5 violations. TSI's appeal 
    from the District Court's June 1998 decision is pending before the 
    United States Court of Appeals for the Eighth Circuit. However, by 
    order dated September 10, 1998, the appeals court denied TSI's motion 
    to stay the NRC's administrative proceeding pending the appeal.
    
    III
    
        After consideration of TSI's answer, the NRC staff has determined, 
    as set forth in the Appendix to this Order, that the violations of 10 
    CFR 50.5 occurred as stated in the Notice, and that the penalties 
    proposed for the violations designated in the Notice should be imposed.
    
    IV
    
        In view of the foregoing and pursuant to section 234 of the Atomic 
    Energy Act of 1954, as amended (Act), 42 U.S.C. 2282, and 10 CFR 2.205, 
    it is hereby ordered that:
        TSI pay civil penalties in the amount of $900,000 within 30 days of 
    the date of this Order, in accordance with NUREG/BR-0254. In addition, 
    at the time of making the payment, TSI shall submit a statement 
    indicating when and by what method payment was made, to the Director, 
    Office of Enforcement, U.S. Nuclear Regulatory Commission, One White 
    Flint North, 11555 Rockville Pike, Rockville, MD 20852-2738.
    
    V
    
        TSI may request a hearing within 30 days of the date of this Order. 
    Where good cause is shown, consideration will be given to extending the 
    time to request a hearing. A request for extension of time must be made 
    in writing to the Director, Office of Enforcement, U.S. Nuclear 
    Regulatory Commission, Washington, DC 20555, and include a statement of 
    good cause for the extension. A request for a hearing should be clearly 
    marked as a ``Request for an Enforcement Hearing'' and shall be 
    submitted to the Secretary, U.S. Nuclear Regulatory Commission, ATTN: 
    Rulemakings and Adjudications Staff, Washington, DC 20555. Copies also 
    shall be sent to the Director, Office of Enforcement, U.S. Nuclear 
    Regulatory Commission, Washington, DC 20555, to the Assistant General 
    Counsel for Materials Litigation and Enforcement at the same address, 
    and to the Regional Administrator, NRC Region III, 801 Warrenville 
    Road, Lisle, IL 60532-4351.
        If a hearing is requested, the Commission will issue an Order 
    designating the time and place of the hearing. If TSI fails to request 
    a hearing within 30 days of the date of this Order (or if written 
    approval of an extension of time in which to request a hearing has not 
    been granted), the provisions of this Order shall be effective without 
    further proceedings. If payment has not been made by that time, the 
    matter may be referred to the United States Attorney General for 
    collection.
        In the event TSI requests a hearing as provided above, the issues 
    to be considered at such hearing shall be:
        (a) Whether TSI was in violation of the Commission's requirements 
    as set forth in the Notice referenced in Section II above; and
        (b) whether, on the basis of such violations, this Order should be 
    sustained.
    
        Dated this 3rd day of May, 1999.
    
        For the Nuclear Regulatory Commission.
    William D. Travers,
    Executive Director for Operations.
    
    Appendix--Evaluation and Conclusion
    
        On October 1, 1996, the NRC issued a Notice of Violation and 
    Proposed Imposition of Civil Penalty (Notice) for violations of NRC 
    requirements identified during an investigation of Thermal Science, 
    Inc. (TSI). The Notice set forth nine violations (designated A through 
    I) of 10 CFR 50.5. TSI's response to the Notice, filed on July 7, 1998, 
    was devoted largely to two legal objections to the Notice: (1) NRC 
    lacks authority to impose a civil penalty on a non-licensee like TSI; 
    and (2) NRC's administrative proceeding is criminal rather than civil, 
    and thus violates the Double Jeopardy Clause of the United States 
    Constitution. These objections repeat those made in TSI's request for a 
    preliminary injunction, filed with the United States District Court for 
    the Eastern District of Missouri. The district court dismissed TSI's 
    injunction request in June 1998. The NRC staff has reviewed TSI's legal 
    objections and finds that they do not bar this administrative action 
    for the following reasons.
        The question of whether the Atomic Energy Act of 1954, as amended, 
    42 U.S.C. 2011 et seq. (AEA) provides the NRC with authority to impose 
    civil penalties on non-licensees was examined at the time 10 CFR 50.5 
    was promulgated. See 56 FR 40664-670 (August 15, 1991). As discussed 
    therein, 10 CFR 50.5 was issued under the general authority of AEA 
    sections 161b and 161i, pursuant to which the Commission may issue any 
    regulation deemed necessary to protect public health. Absent from these 
    statutory provisions is any limitation to whom such regulations may be 
    made applicable. Moreover, in evaluating the general powers conferred 
    on the Commission by Congress, federal courts have uniformly found the 
    AEA's provisions quite broad. In passing the AEA, Congress enacted a 
    regulatory scheme which is virtually unique in the degree to which 
    broad responsibility is reposed in the administering agency, free of 
    close prescription in its charter as to how it shall proceed in 
    achieving the statutory objectives.
        Siegel v. AEC, 400 F.2d 778, 783 (D.C. Cir. 1968). See also Power 
    Reactor Development Co. v. International Union of Elec. Radio and Mach. 
    Workers AFL-CIO, 367 U.S. 396 (1961). In exercising its broad 
    rulemaking authority, the Commission explicitly made 10 CFR 50.5 
    applicable to, among others, any ``supplier'' who provided to one or 
    more NRC licensees ``materials, or other goods or services,'' relating 
    to licensed activities. 10 CFR 50.5(a). As detailed in the Notice, TSI 
    qualifies as such a ``supplier.'' Accordingly, TSI is properly subject 
    to the regulation, even though TSI is not an NRC license.
        TSI's Double Jeopardy argument is contrary to the Supreme Court's 
    holding in Hudson v. U.S., 118 S.Ct. 488 (1997). The Court there held 
    that while a second ``criminal prosecution'' for the same conduct is 
    prohibited, civil penalties based on the alleged criminal conduct may 
    be lawfully imposed
    
    [[Page 25378]]
    
    unless ``the clearest proof'' shows that the statute authorizing the 
    civil penalty can only be construed as a criminal sanction. Hudson, 118 
    S.Ct. at 493. In making this determination, only the ``statute on its 
    face'' is to be evaluated (Id., at 494), and if the statute confers 
    sanction authority upon an administrative agency this is ``prima facie 
    evidence that Congress intended to provide for a civil sanction.'' Id., 
    at 495. In this regard, the Court distinguished between the ``infamous 
    punishment of imprisonment'' imposed following a judicial trial, and 
    money penalties. Id., at 495-96.
        Applying Hudson to the facts here, the October 1, 1996 Notice 
    informed TSI that the NRC proposed to impose civil penalties pursuant 
    to section 234 of the AEA, 42 U.S.C. 2282, and 10 CFR 
    2.205.1 Reading AEA section 234, which is titled ``Civil 
    Monetary Penalties For Violations of Licensing Requirements,'' there 
    can be no doubt that it provides for civil, not criminal, sanctions. 
    Persons are subject to ``civil'' penalties of up to $100,000 ``to be 
    imposed by the Commission.'' 42 U.S.C. 2282(a). Unpaid penalties 
    imposed by the Commission ``may be collected by civil action.'' 42 
    U.S.C. 2282(b). Even when a penalty matter is referred to the United 
    States Attorney General for collection, the Attorney General is only 
    ``authorized to institute a civil action.'' 42 U.S.C. 2282(c). Section 
    234 provides only for monetary penalties, with no provisions for 
    imprisonment, and does not contain the word ``criminal.'' 2 
    Similarly, 10 CFR 2.205 provides only for the imposition of civil 
    penalties, and specifies the procedures by which a person charged with 
    violations may contest those violations by requesting an administrative 
    hearing. Accordingly, any administrative action taken by the Commission 
    against TSI pursuant to the Notice will necessarily be civil rather 
    than criminal in nature. In these circumstances the Double Jeopardy 
    Clause does not bar the administrative action even though it arises 
    from some of the same conduct for which TSI was criminally tried in 
    1995.
    ---------------------------------------------------------------------------
    
        \1\ 10 CFR 2.205 is the NRC regulation implementing the 
    statutory authority of 42 U.S.C. 2282. The regulation was also 
    issued under the authority, inter alia, of AEA sections 161 b, i, 
    and o, 42 U.S.C. 2201 (b), (i), and (o). See preamble to 10 CFR Part 
    2.
        \2\ Section 234 thus stands in sharp contrast to the criminal 
    provisions of the AEA, set forth in sections 221-223, 42 U.S.C. 
    2271-2273, which either refer to ``criminal violations,'' or specify 
    terms of imprisonment as punishment.
    ---------------------------------------------------------------------------
    
        With respect to the facts upon which the staff based its proposed 
    action, TSI's response to the Notice denied the nine violations. The 
    NRC's evaluation and conclusion regarding TSI's factual denial are as 
    follows:
    
    Restatement of Violation A
    
        A. Contrary to 10 CFR 50.5, TSI deliberately made statements in an 
    October 5, 1991 letter to the NRC which it knew contained inaccurate 
    and incomplete information material to the NRC, as evidenced by the 
    following examples:
        1. In its October 5, 1991 letter, TSI stated that Thermo-Lag had 
    been ``. . . extensively tested by independent testing laboratories on 
    many occasions. . . .'' See TSI Letter of October 5, 1991, at 1. TSI's 
    statement was incomplete and inaccurate in that the NRC later 
    determined during an inspection at TSI's offices that test reports 
    bearing the logo of Industrial Testing Laboratories, Inc. (ITL) were 
    actually drafted by TSI, typed by TSI, and issued by TSI. ITL's role 
    was limited to having one of its representatives witness data 
    acquisition on the date of the test, and verify furnace temperature 
    readouts, without having had any involvement in the construction or 
    approval of the test article. Thus, with respect to ITL, the statement 
    that Thermo-Lag had been ``. . . extensively tested by independent 
    testing laboratories on many occasions. . . .'' misrepresented the 
    respective roles of TSI and ITL in Thermo-Lag testing.
        2. In its October 5, 1991 letter, TSI stated that Thermo-Lag 
    provides ``a fire barrier of consistent performance[]'' when installed 
    ``in accordance with the instruction manuals in concert with training 
    programs of Thermal Science,'' and that this performance had ``been 
    proven by independent testing on multiple occasions.'' See TSI Letter 
    of October 5, 1991, at 2. This statement was inaccurate in that most of 
    the configurations tested by TSI, in those tests that were submitted to 
    the NRC, were not installed in accordance with the TSI instruction 
    manual.
        3. In TSI's ``Response To The United States Nuclear Regulatory 
    Commission's Letter Dated 10 September 1991,'' attached to its October 
    5, 1991 letter, TSI provided results from 1986 tests conducted by 
    Underwriter's Laboratory (UL) regarding ampacity derating tests of one-
    hour and three-hour Thermo-Lag fire barrier systems, and stated that 
    the values obtained by the UL tests reflected ``the most current and 
    conservative results of tests . . .'' and were ``the most conservative 
    information available to us.'' \3\ See TSI Response at 6 and 12. These 
    statements were inaccurate in that TSI was aware of an alternate 
    baseline UL ampacity derating test that was more current and provided 
    more conservative values than the test results submitted to the NRC on 
    October 5, 1991.
    ---------------------------------------------------------------------------
    
        \3\ This answer responded to NRC Question I.A.5., ``What are 
    ampacity deratings for 1-hour fire rated THERMO-LAG fire barrier 
    systems[,]'' and NRC Question I.B.5., ``What are ampacity deratings 
    for 3-hour fire rated THERMO-LAG fire barrier systems[,].'' See NRC 
    letter to TSI dated September 10, 1991, Enclosure at 1.
    ---------------------------------------------------------------------------
    
        These statements were material to the NRC because they were made by 
    TSI: (1) In response to concerns the NRC had raised about the quality 
    and adequacy of Thermo-Lag, including specific concerns about the 
    nature of the testing performed to qualify Thermo-Lag for use in 
    nuclear power plants; and (2) to influence the NRC's investigation into 
    whether Thermo-Lag met NRC's fire barrier requirements and guidelines. 
    (01011)
        This is a Severity Level I violation (Supplement VII) Civil 
    Penalty--$100,000
    
    Summary of TSI's Answer to Violation A
    
        In denying Violation A, TSI stated that at all times it acted and 
    intended to act in accordance with all applicable requirements. TSI 
    stated that no false statements were ever deliberately made by its 
    representatives, and that its representatives ``never deliberately 
    omitted to disclose any material information to the NRC.'' In support 
    of its denial, TSI referenced the fact that based on the evidence 
    presented at the criminal trial in 1995, the jury acquitted TSI of all 
    charges.
    
    NRC Evaluation of TSI's Answer to Violation A
    
        TSI's brief pro forma answer on the facts provides no rebuttal or 
    other information regarding the detailed allegations made in Violation 
    A. The answer makes no attempt to explain why the allegations are 
    incorrect. In the absence of new information, the NRC staff continues 
    to believe that violations of NRC requirements occurred as alleged in 
    Violation A, that these violations are properly classified as Severity 
    Level 1, and that these violations carry a high degree of regulatory 
    significance. Accordingly, the NRC staff finds that the proposed civil 
    penalty of $100,000 should be imposed for Violation A.
    
    Restatement of Violation B
    
        B. Contrary to 10 CFR 50.5, during an October 17, 1991 meeting with 
    the NRC Staff, Mr. Rubin Feldman, the President of TSI, deliberately 
    made oral statements to the NRC that he knew
    
    [[Page 25379]]
    
    contained inaccurate information material to the NRC. With respect to 
    the participation of ITL in the fire barrier testing of Thermo-Lag, the 
    following exchange took place:
    
        Mr. West (NRC): You mentioned in your [October 5, 1991] letter--
    in fact, you provided us with an enclosure that identifies quite a 
    few tests that had been sponsored, presumably, by TSI. It looks like 
    the bulk of the tests were actually done at your facility, although 
    there seemed to be some involvement of a testing outfit called ITL, 
    Industrial Testing Laboratory. We are not familiar with it; it's not 
    UL or Southwest. Could you fill us in on who ITL is and tell us what 
    involvement they have in each test, in terms of planning, conduct 
    and report writing and documentation base?
        Mr. Feldman: Industrial Test Laboratories is a St. Louis-based 
    laboratories. . . . We needed a third part (sic) observing the 
    various phases of the testing. We have asked them if they would be 
    willing to do that. They indicated that they would, so they 
    officiated during the phases of the testing. That's how the reports 
    were published.
    
        Tr. at 167-8 (emphasis added). The discussion about ITL continued 
    as follows:
    
        Mr. West: . . . What I'm trying to find out is, I think we need 
    to decide if their [ITL's] involvement in the test really would 
    constitute the independence for the test.
        Mr. Feldman: They were very independent. They reviewed all the 
    data. They analyzed all the data. It was as independent as you can 
    make it.
    
        Tr. at 170 (emphasis added.)
        Mr. Feldman's statements were inaccurate and misrepresented the 
    respective roles of ITL and TSI in Thermo-Lag testing. Mr. Feldman knew 
    that ITL did not function as an independent tester of Thermo-Lag, and 
    that ITL's role was limited to having one of its representatives 
    witness data acquisition on the date of the test, and verify furnace 
    temperature readouts, without having any involvement in the 
    construction or approval of the fire barrier/raceway test article.
        Mr. Feldman's statements were material to the NRC because Mr. 
    Feldman made them, on behalf of TSI: (1) in response to concerns the 
    NRC had raised about the quality and adequacy of Thermo-Lag, including 
    specific concerns about the nature of the relationship between TSI and 
    ITL regarding the testing performed to qualify Thermo-Lag as 1-hour and 
    3-hour fire barrier material for use in nuclear power plants; (2) to 
    influence the NRC's investigation into whether Thermo-Lag met NRC's 
    fire protection requirements and guidelines; and (3) to persuade the 
    NRC that, for those Thermo-Lag tests in which ITL had involvement, ITL 
    had acted as an independent, third-party reviewer and analyzer of all 
    the test data. (02011).
        This is a Severity Level I violation (Supplement VII) Civil 
    Penalty--$100,000
    
    Summary of TSI's Answer to Violation B
    
        In denying Violation B, TSI stated that at all times it acted and 
    intended to act in accordance with all applicable requirements. TSI 
    stated that no false statements were ever deliberately made by its 
    representatives, and that its representatives ``never deliberately 
    omitted to disclose any material information to the NRC.'' In support 
    of its denial, TSI referenced the fact that based on the evidence 
    presented at the criminal trial in 1995, the jury acquitted TSI of all 
    charges.
    
    NRC Evaluation of TSI's Answer to Violation B
    
        TSI's brief pro forma answer on the facts provides no rebuttal or 
    other information regarding the detailed allegations made in Violation 
    B. The answer makes no attempt to explain why the allegations are 
    incorrect. In the absence of new information, the NRC staff continues 
    to believe that violations of NRC requirements occurred as alleged in 
    Violation B, that these violations are properly classified as Severity 
    Level 1, and that these violations carry a high degree of regulatory 
    significance. Accordingly, the NRC staff finds that the proposed civil 
    penalty of $100,000 should be imposed for Violation B.
    
    Restatement of Violation C
    
        C. Contrary to 10 CFR 50.5, TSI deliberately submitted inaccurate 
    information material to the NRC on November 12, 1991, in response to 
    NRC questions sent to TSI by letter dated October 31, 1991, as 
    evidenced by the following examples:
        1. The NRC asked TSI to ``provide copies of all TSI correspondence 
    and documents related to UL Project Report 86-NK-23826, File R-6-802, 
    dated January 27, 1987'' dealing with ampacity derating testing used to 
    qualify Thermo-Lag as 1-hour and 3-hour rated fire barrier material. 
    See NRC letter of October 31, 1991, Enclosure at 1, Question 7. In 
    partial response, TSI submitted ITL Report 82-355-F-1 and ITL Report 
    84-10-5. See TSI's ``Partial Response To The United States Nuclear 
    Regulatory Commission's Letter Dated 31 October 1991'' (attached to 
    TSI's letter dated November 12, 1991), Answer 7-2 (2), at 9, and 
    Attachment 4. This response was inaccurate in that TSI knew ITL Report 
    82-355-F-1 misrepresented the respective roles of TSI and ITL in the 
    testing of Thermo-Lag. This report's cover sheet carries the ITL logo, 
    indicating that the report was written by ITL. This report is TSI 
    Technical Note 111782, with an ITL cover sheet attached to it. TSI 
    Technical Note 111782 had been written and issued by TSI in November 
    1981. ITL had no involvement in creating or issuing ITL Report 82-355-
    F-1, did not witness the subject ampacity test, and had no role in 
    documenting or analyzing the test results.
        2. Regarding ITL Report 84-10-5, TSI's November 12, 1991 response 
    was further inaccurate in that TSI knew that this ITL Report also 
    misrepresented the respective roles of TSI and ITL in the testing of 
    Thermo-Lag. The report's headings and titles indicate that the report 
    was written by ITL. In fact, TSI wrote ITL Report 84-10-5, using ITL 
    stationery that TSI had obtained from ITL. Section 2 of the report 
    represents that ITL compared the test data to baseline data obtained in 
    an October 1981 test (a reference to the test reported in ITL Report 
    82-355-F-1). In fact, no such data comparison was performed by ITL.
        The inaccurate information TSI submitted to the NRC on November 12, 
    1991, in the form of the ``ITL'' reports, was material to the NRC 
    because TSI's submittal was made: (1) In response to concerns the NRC 
    had raised about the quality and adequacy of Thermo-Lag, including 
    specific concerns about the ampacity derating testing used to qualify 
    Thermo-Lag as 1-hour and 3-hour rated fire barrier material for use in 
    nuclear power plants; and (2) to influence the NRC's investigation into 
    whether Thermo-Lag met NRC's fire protection requirements. (03011)
        This is a Severity Level I violation (Supplement VII) Civil 
    Penalty--$100,000
    
    Summary of TSI's Answer to Violation C
    
        In denying Violation C, TSI stated that at all times it acted and 
    intended to act in accordance with all applicable requirements. TSI 
    stated that no false statements were ever deliberately made by its 
    representatives, and that its representatives ``never deliberately 
    omitted to disclose any material information to the NRC.'' In support 
    of its denial, TSI referenced the fact that based on the evidence 
    presented at the criminal trial in 1995, the jury acquitted TSI of all 
    charges.
    
    [[Page 25380]]
    
    NRC Evaluation of TSI's Answer to Violation C
    
        TSI's brief pro forma answer on the facts provides no rebuttal or 
    other information regarding the detailed allegations made in Violation 
    C. The answer makes no attempt to explain why the allegations are 
    incorrect. In the absence of new information, the NRC staff continues 
    to believe that violations of NRC requirements occurred as alleged in 
    Violation C, that these violations are properly classified as Severity 
    Level 1, and that these violations carry a high degree of regulatory 
    significance. Accordingly, the NRC staff finds that the proposed civil 
    penalty of $100,000 should be imposed for Violation C.
    
    Restatement of Violation D
    
        D. Contrary to 10 CFR 50.5, TSI deliberately submitted inaccurate 
    information material to the NRC on December 3, 1991, in further 
    response to NRC questions sent to TSI by letter dated October 31, 1991, 
    as evidenced by the following examples:
        1. The NRC asked TSI to ``provide full copies of ITL fire test 
    reports 82-11-80 and 82-11-81, including daily work sheets, quality 
    assurance documentation, and thermocouple temperature records.'' NRC 
    letter of October 31, 1991, Enclosure at 3, Question 19. This request 
    was generated by Mr. Feldman's offer to provide the quality control 
    records attached to ITL reports 82-11-80 and 82-11-81, which were 
    needed to answer a question concerning test article construction. See 
    October 17, 1991 transcript, at 89-90; 190-91. In response, TSI 
    submitted complete copies of ITL Report 82-11-80 and ITL Report 82-11-
    81, which were the generic 1-hour and 3-hour test reports used to 
    qualify Thermo-Lag as 1-hour and 3-hour fire barrier material for use 
    in nuclear power plants. See  TSI's ``Supplemental Response To The 
    Remaining Questions Contained In The United States Nuclear Regulatory 
    Commission's Letter Dated 31 October 1991'' (attached to TSI's letter 
    dated December 3, 1991), Answer 19, at 9, and Enclosures 8 and 9. This 
    response was inaccurate in that TSI knew ITL Report 82-11-80 
    misrepresented the respective roles of TSI and ITL in the testing of 
    Thermo-Lag. The Proprietary Rights statement of TSI, included as part 
    of the report, stated that the report was prepared by ITL. In fact, the 
    report was not prepared by ITL. TSI wrote ITL Report 82-11-80, using 
    ITL stationery that TSI had obtained from ITL. Section 3 of ITL Report 
    82-11-80 states that the subject testing was performed ``under the 
    supervision and total control of Industrial Testing Laboratories, of 
    St. Louis, Missouri, an independent testing laboratory.'' In fact, the 
    test was conducted under the supervision and control of TSI, with an 
    ITL representative merely witnessing the test and verifying furnace 
    temperature readouts.
        2. Regarding ITL Report 82-11-81, TSI's December 3, 1991 response 
    was further inaccurate in that TSI knew that this ITL Report also 
    misrepresented the respective roles of TSI and ITL in the testing of 
    Thermo-Lag. The Proprietary Rights statement of TSI, included as part 
    of the report, stated that the report was prepared by ITL. In fact, the 
    report was not prepared by ITL. TSI wrote ITL Report 82-11-81, using 
    ITL stationery that TSI had obtained from ITL. Section 3 of ITL Report 
    82-11-81 stated that the subject testing was performed ``under the 
    supervision and total control of Industrial Testing Laboratories, of 
    St. Louis, Missouri, an independent testing laboratory.'' In fact, the 
    test was conducted under the supervision and control of TSI, with ITL 
    representative Donald Storment merely witnessing the tests and 
    verifying furnace temperature readouts, which took place between 
    September 10 and October 12, 1982. Moreover, several daily work sheet 
    pages from Section 7 of the report are represented as having been 
    signed by Mr. Storment. In fact, those pages contain replicated 
    signatures of Mr. Storment, which TSI added to the report without the 
    knowledge or consent of either ITL or Mr. Storment. For the daily work 
    sheets that Mr. Storment did sign, TSI instructed Mr. Storment to 
    backdate those sheets to make it appear that he had witnessed TSI work 
    performed in August and early September of 1982, when, in fact, Mr. 
    Storment had not witnessed that work.
        The inaccurate information TSI submitted to the NRC on December 3, 
    1991 was material to the NRC because TSI's submittal was made: (1) In 
    response to concerns the NRC had raised about the quality and adequacy 
    of Thermo-Lag, including specific questions about the test articles 
    discussed in ITL Reports 82-11-80 and 82-11-81, which were generic 
    tests TSI had used to qualify Thermo-Lag as 1-hour and 3-hour rated 
    fire barrier material for use in nuclear power plants; and (2) to 
    influence the NRC's investigation into whether Thermo-Lag met NRC's 
    fire protection requirements. (04011)
        This is a Severity Level I violation (Supplement VII)
        Civil Penalty--$100,000
    
    Summary of TSI's Answer to
    Violation D
    
        In denying Violation D, TSI stated that at all times it acted and 
    intended to act in accordance with all applicable requirements. TSI 
    stated that no false statements were ever deliberately made by its 
    representatives, and that its representatives ``never deliberately 
    omitted to disclose any material information to the NRC.'' In support 
    of its denial, TSI referenced the fact that based on the evidence 
    presented at the criminal trial in 1995, the jury acquitted TSI of all 
    charges.
    
    NRC Evaluation of TSI's Answer to Violation D
    
        TSI's brief pro forma answer on the facts provides no rebuttal or 
    other information regarding the detailed allegations made in Violation 
    D. The answer makes no attempt to explain why the allegations are 
    incorrect. In the absence of new information, the NRC staff continues 
    to believe that violations of NRC requirements occurred as alleged in 
    Violation D, that these violations are properly classified as Severity 
    Level 1, and that these violations carry a high degree of regulatory 
    significance. Accordingly, the NRC staff finds that the proposed civil 
    penalty of $100,000 should be imposed for Violation D.
    
    Restatement of Violation E
    
        E. Contrary to 10 CFR 50.5, TSI deliberately made a statement in a 
    May 8, 1992 letter to the NRC which it knew contained inaccurate 
    information material to the NRC. In this letter, TSI stated that its 
    ongoing test program at Omega Point Laboratories was ``under the total 
    control of Omega Point.'' See TSI Letter of May 8, 1992, at 2. This 
    statement was inaccurate in that this test program was not under the 
    total control of Omega Point Laboratories. For example, the 
    construction of the test articles and placement of the test 
    thermocouples was under TSI's control.
        This statement was material to the NRC because TSI submitted it: 
    (1) In response to concerns the NRC had raised about the quality and 
    adequacy of Thermo-Lag, including specific concerns about the 
    misleading nature of the ``ITL'' reports; and (2) to persuade the NRC 
    that TSI was now subjecting Thermo-Lag to truly independent testing. 
    (05011)
        This is a Severity Level I violation (Supplement VII) Civil 
    Penalty--$100,000
    
    [[Page 25381]]
    
    Summary of TSI's Answer to     Violation E
    
        In denying Violation E, TSI stated that at all times it acted and 
    intended to act in accordance with all applicable requirements. TSI 
    stated that no false statements were ever deliberately made by its 
    representatives, and that its representatives ``never deliberately 
    omitted to disclose any material information to the NRC.'' In support 
    of its denial, TSI referenced the fact that based on the evidence 
    presented at the criminal trial in 1995, the jury acquitted TSI of all 
    charges.
    
    NRC Evaluation of TSI's Answer to Violation E
    
        TSI's brief pro forma answer on the facts provides no rebuttal or 
    other information regarding the allegations made in Violation E. The 
    answer makes no attempt to explain why the allegations are incorrect. 
    In the absence of new information, the NRC staff continues to believe 
    that violations of NRC requirements occurred as alleged in Violation E, 
    that these violations are properly classified as Severity Level 1, and 
    that these violations carry a high degree of regulatory significance. 
    Accordingly, the NRC staff finds that the proposed civil penalty of 
    $100,000 should be imposed for Violation E.
    
    Restatement of Violation F
    
        F. Contrary to 10 CFR 50.5, TSI deliberately made statements in a 
    June 16, 1992 letter to the NRC which it knew contained inaccurate 
    information material to the NRC, including but not limited to the 
    following examples:
        1. TSI stated that its continuing test program at Omega Point 
    Laboratories was ``under the total control of Omega Point.'' See TSI 
    Letter of June 16, 1992, at 2. This statement was inaccurate in that 
    this test program was not under the total control of Omega Point. For 
    example, the construction of the test articles and placement of the 
    test thermocouples was under TSI's control.
        2. TSI stated that the tests were being conducted in accordance 
    with, among other criteria, the ``applicable prerequisites of'' NRC 
    Generic Letter 86-10. See TSI Letter of June 16, 1992, at 3. This 
    statement was inaccurate in that these tests were not being conducted 
    in accordance with the guidance of NRC Generic Letter 86-10.
        These statements were material to the NRC because TSI submitted 
    them: (1) In response to concerns the NRC had raised about the quality 
    and adequacy of Thermo-Lag, including specific concerns about the 
    misleading nature of the ``ITL'' reports; and (2) to persuade the NRC 
    that TSI was now subjecting Thermo-Lag to truly independent testing. 
    (06011)
        This is a Severity Level I violation (Supplement VII) Civil 
    Penalty--$100,000
    
    Summary of TSI's Answer to     Violation F
    
        In denying Violation F, TSI stated that at all times it acted and 
    intended to act in accordance with all applicable requirements. TSI 
    stated that no false statements were ever deliberately made by 
    representatives, and that its representatives ``never deliberately 
    omitted to disclose any material information to the NRC.'' In support 
    of its denial, TSI referenced the fact that based on the evidence 
    presented at the criminal trial in 1995, the jury acquitted TSI of all 
    charges.
    
    NRC Evaluation of TSI's Answer to Violation F
    
        TSI's brief pro forma answer on the facts provides no rebuttal or 
    other information regarding the detailed allegations made in Violation 
    F. The answer makes no attempt to explain why the allegations are 
    incorrect. In the absence of new information, the NRC staff continues 
    to believe that violations of NRC requirements occurred as alleged in 
    Violation F, that these violations are properly classified as Severity 
    Level 1, and that these violations carry a high degree of regulatory 
    significance. Accordingly, the NRC staff finds that the proposed civil 
    penalty of $100,000 should be imposed for Violation F.
    
    Restatement of Violation G
    
        G. Contrary to 10 CFR 50.5, TSI deliberately made a statement in a 
    June 22, 1992 letter to the NRC which it knew contained inaccurate 
    information material to the NRC. In this letter, TSI stated that the 
    TSI-sponsored tests conducted at Omega Point Laboratories were ``under 
    their (Omega Point Laboratories') total control, which also included 
    quality control during construction.'' See TSI Letter of June 22, 1992, 
    at 2. This statement was inaccurate in that (1) TSI knew that the test 
    program was not under the total control of Omega Point and that (2) TSI 
    knew that quality control during construction of the test articles was 
    not under the total control of Omega Point.
        This statement was material to the NRC because TSI submitted it: 
    (1) In response to concerns the NRC had raised about the quality and 
    adequacy of Thermo-Lag, including specific concerns about the 
    misleading nature of the ``ITL'' reports; and (2) to persuade the NRC 
    that TSI was now subjecting Thermo-Lag to truly independent testing. 
    (07011)
        This is a Severity Level I violation (Supplement VII) Civil 
    Penalty--$100,000
    
    Summary of TSI's Answer to Violation G
    
        In denying Violation G, TSI stated that at all times it acted and 
    intended to act in accordance with all applicable requirements. TSI 
    stated that no false statements were ever deliberately made by its 
    representatives, and that its representatives ``never deliberately 
    omitted to disclose any material information to the NRC.'' In support 
    of its denial, TSI referenced the fact that based on the evidence 
    presented at the criminal trial in 1995, the jury acquitted TSI of all 
    charges.
    
    NRC Evaluation of TSI's Answer to Violation G
    
        TSI's brief pro forma answer on the facts provides no rebuttal or 
    other information regarding the allegations made in Violation G. The 
    answer makes no attempt to explain why the allegations are incorrect. 
    In the absence of new information, the NRC staff continues to believe 
    that violations of NRC requirements occurred as alleged in Violation G, 
    that these violations are properly classified as Severity Level 1, and 
    that these violations carry a high degree of regulatory significance. 
    Accordingly, the NRC staff finds that the proposed civil penalty of 
    $100,000 should be imposed for Violation G.
    
    Restatement of Violation H
    
        H. Contrary to 10 CFR 50.5, TSI deliberately made a statement in a 
    July 29, 1992 letter to the NRC which it knew contained inaccurate 
    information material to the NRC. In this letter, TSI stated that the 
    1986 ampacity testing ``was done by Underwriters Laboratories [sic] in 
    Chicago under its [Underwriters Laboratory's] total control.'' TSI 
    Letter of July 29, 1992, at 4. This statement was inaccurate in that 
    TSI knew that the referenced ampacity testing was not under the total 
    control of Underwriters Laboratory.
        This statement was material to the NRC because TSI submitted it: 
    (1) In response to concerns the NRC had raised about the quality and 
    adequacy of Thermo-Lag, including specific concerns about the ampacity 
    derating testing used to qualify Thermo-Lag as 1-hour and 3-hour rated 
    fire barrier material for use in nuclear power plants; and (2) to 
    influence how the NRC disseminated information to the nuclear
    
    [[Page 25382]]
    
    industry about the performance of Thermo-Lag products. (08011)
        This is a Severity Level I violation (Supplement VII) Civil 
    Penalty--$100,000
    
    Summary of TSI's Answer to     Violation H
    
        In denying Violation H, TSI stated that at all times it acted and 
    intended to act in accordance with all applicable requirements. TSI 
    stated that no false statements were ever deliberately made by its 
    representatives, and that its representatives ``never deliberately 
    omitted to disclose any material information to the NRC.'' In support 
    of its denial, TSI referenced the fact that based on the evidence 
    presented at the criminal trial in 1995, the jury acquitted TSI of all 
    charges.
    
    NRC Evaluation of TSI's Answer to Violation H
    
        TSI's brief pro forma answer on the facts provides no rebuttal or 
    other information regarding the allegations made in Violation H. The 
    answer makes no attempt to explain why the allegations are incorrect. 
    In the absence of new information, the NRC staff continues to believe 
    that violations of NRC requirements occurred as alleged in Violation H, 
    that these violations are properly classified as Severity Level 1, and 
    that these violations carry a high degree of regulatory significance. 
    Accordingly, the NRC staff finds that the proposed civil penalty of 
    $100,000 should be imposed for Violation H.
    
    Restatement of Violation I
    
        I. Contrary to 10 CFR 50.5, on or about August 31, 1992, TSI 
    deliberately submitted to the NRC ITL Reports 85-6-283, 85-2-382, 85-5-
    314, 85-11-227, 86-7-472, 87-5-435, 87-6-350, 85-1-106, and 85-4-377. 
    These reports misrepresented the respective roles of TSI and ITL in the 
    testing of Thermo-Lag. TSI knew these reports contained inaccurate 
    information material to the NRC, as evidenced by the following 
    examples:
        1. Regarding ITL Report 85-6-283, the report's headings and titles 
    indicate that the report was prepared by ITL. This information was 
    inaccurate in that TSI wrote this report, using ITL stationery that TSI 
    had obtained from ITL. Section 3 of the report stated that the subject 
    testing was conducted ``under the direct supervision and total control 
    of Industrial Testing Laboratories, Inc.'' In fact, the test had been 
    conducted under the supervision and control of TSI, with an ITL 
    representative merely witnessing the test and verifying furnace 
    temperature readouts. Page (i) of the report represents that the ITL 
    representative witnessing the test (Dave Siegel) was a professional 
    engineer. However, subsequent NRC review has determined that Dave 
    Siegel was not a professional engineer, did not have a college degree, 
    and that TSI was aware of his lack of qualifications. Page (i) of the 
    report also represents that Allan Siegel reviewed, approved, and signed 
    the report on behalf of ITL. However, subsequent NRC review has 
    determined that page (i) contains the replicated signature of Allan 
    Siegel, which TSI added to the report without the knowledge or consent 
    of Allan Siegel. Daily work sheets contained in Section 6 of the report 
    were altered by TSI to make it appear that Dave Siegel witnessed TSI's 
    construction of the test article on May 17, 1985, when in fact Dave 
    Siegel only witnessed the test itself, which was performed on June 19, 
    1985. Similarly, in Section 7 of the report, TSI forged the initials of 
    Dave Siegel on work sheets to make it appear that Dave Siegel was 
    present on May 17, 1985, when TSI constructed the test article.
        2. Regarding ITL Report 85-2-382, the report's headings and titles 
    indicate that the report was prepared by ITL. This information was 
    inaccurate in that TSI wrote this report, using ITL stationery that TSI 
    had obtained from ITL. Section 3 of the report stated that the subject 
    testing was conducted ``under the direct supervision and total control 
    of Industrial Testing Laboratories, Inc.'' In fact, the test had been 
    conducted under the supervision and control of TSI, with an ITL 
    representative merely witnessing the test and verifying furnace 
    temperature readouts.
        3. Regarding ITL Report 85-5-314, the report's headings and titles 
    indicate that the report was prepared by ITL. This information was 
    inaccurate in that TSI wrote this report, using ITL stationery that TSI 
    had obtained from ITL. Section 3 of the report stated that the subject 
    testing was conducted ``under the direct supervision and total control 
    of Industrial Testing Laboratories, Inc.'' In fact, the test had been 
    conducted under the supervision and control of TSI, with an ITL 
    representative merely witnessing the test and verifying furnace 
    temperature readouts. Page (i) of the report represents that the ITL 
    representative witnessing the test (Mike White) was a professional 
    engineer. This is inaccurate in that Mr. White was not a professional 
    engineer, and at that time TSI knew that Mr. White was not a 
    professional engineer. Among the daily work sheets contained in Section 
    6 of the report are ones signed by Mike White, regarding test article 
    work performed by TSI on May 14, 1985. These work sheets are inaccurate 
    in that Mr. White was present only during the test itself on May 21, 
    1985. In fact, TSI instructed Mr. White to backdate the work sheets he 
    signed to make it appear that he had witnessed TSI May 14 work when, in 
    fact, he had not witnessed that work.
        4. Regarding ITL Report 85-11-227, the report's headings and titles 
    indicate that the report was prepared by ITL. This information was 
    inaccurate in that TSI wrote this report, using ITL stationery that TSI 
    had obtained from ITL. Section 3 of the report stated that the subject 
    testing was conducted ``under the direct supervision and total control 
    of Industrial Testing Laboratories, Inc.'' In fact, the test had been 
    conducted under the supervision and control of TSI, with an ITL 
    representative merely witnessing the test and verifying furnace 
    temperature readouts. Among the daily work sheets contained in Section 
    6 of the report are ones signed by Mike White, regarding test article 
    work performed by TSI on November 8, 1985. Section 6 is inaccurate in 
    that Mr. White was present only during the test itself on November 19, 
    1985. In fact, Mr. White was instructed by TSI to sign work sheets to 
    make it appear that he had witnessed TSI's November 8 work when, in 
    fact, he had not witnessed that work.
        5. Regarding ITL Report 86-7-472, the report's headings and titles 
    indicate that the report was prepared by ITL. This information was 
    inaccurate in that TSI wrote this report, using ITL stationery that TSI 
    had obtained from ITL. Section 3 of the report stated that the subject 
    testing was conducted on August 1, 1986 ``under the direct supervision 
    and total control of Industrial Testing Laboratories, Inc.'' In fact, 
    the test had been conducted under the supervision and control of TSI, 
    with an ITL representative merely witnessing the test and verifying 
    furnace temperature readouts. Contained within this report is a 
    ``Verification of Application'' document dated July 31, 1986 and signed 
    by R. A. Lohman on behalf of TSI. This document refers to ITL Test 
    Article No. 86-7-472. This information was inaccurate in that there 
    were never any ITL test articles, as ITL neither built nor helped to 
    assemble any of the articles tested by TSI.
        6. Regarding ITL Report 87-5-435, the report's headings and titles 
    indicate that the report was prepared by ITL. This information was 
    inaccurate in that TSI wrote this report, using ITL stationery that TSI 
    had obtained from ITL. Section 3 of the report stated that the subject
    
    [[Page 25383]]
    
    testing was conducted ``under the direct supervision and total control 
    of Industrial Testing Laboratories, Inc.'' In fact, the test had been 
    conducted under the supervision and control of TSI, with an ITL 
    representative merely witnessing the test and verifying furnace 
    temperature readouts.
        7. Regarding ITL Report 87-6-350, the report's headings and titles 
    indicate that the report was prepared by ITL. This information was 
    inaccurate in that TSI wrote this report, using ITL stationery that TSI 
    had obtained from ITL. Section 3 of the report stated that the subject 
    testing was conducted ``under the direct supervision and total control 
    of Industrial Testing Laboratories, Inc.'' In fact, the test had been 
    conducted under the supervision and control of TSI, with an ITL 
    representative merely witnessing the test and verifying furnace 
    temperature readouts.
        8. Regarding ITL Report 85-1-106, the report's headings and titles 
    indicate that the report was prepared by ITL. This information was 
    inaccurate in that TSI wrote this report, using ITL stationery that TSI 
    had obtained from ITL. Section 3 of the report stated that the subject 
    testing was conducted ``under the direct supervision and total control 
    of Industrial Testing Laboratories, Inc.'' In fact, the test had been 
    conducted under the supervision and control of TSI, with an ITL 
    representative merely witnessing the test and verifying furnace 
    temperature readouts.
        9. Regarding ITL Report 85-4-377, the report's headings and titles 
    indicate that the report was prepared by ITL. This information was 
    inaccurate in that TSI wrote this report, using ITL stationery that TSI 
    had obtained from ITL. Page (i) of the report represents that the ITL 
    representative witnessing the test (Clarence Bester) was a professional 
    engineer. This is inaccurate in that Mr. Bester was not a professional 
    engineer. Section 3 of the report stated that the subject testing was 
    conducted ``under the direct supervision and total control of 
    Industrial Testing Laboratories, Inc.'' In fact, the test had been 
    conducted under the supervision and control of TSI, with an ITL 
    representative merely witnessing the test and verifying furnace 
    temperature readouts.
        The reports TSI submitted to the NRC on or about August 31, 1992 
    were material to the NRC because they were submitted by TSI: (1) In 
    response to concerns the NRC had raised about the quality and adequacy 
    of Thermo-Lag products; (2) in the context of an ongoing NRC 
    investigation into concerns about the quality and performance of 
    Thermo-Lag products; and (3) to influence the NRC's investigation into 
    whether Thermo-Lag products met the fire barrier requirements of 10 CFR 
    50.48 and 10 CFR part 50, appendix R. (09011)
        This is a Severity Level I violation (Supplement VII)
        Civil Penalty--$100,000
    
    Summary of TSI's Answer to Violation I
    
        In denying Violation I, TSI stated that at all times it acted and 
    intended to act in accordance with all applicable requirements. TSI 
    stated that no false statements were ever deliberately made by its 
    representatives, and that its representatives ``never deliberately 
    omitted to disclose any material information to the NRC.'' In support 
    of its denial, TSI referenced the fact that based on the evidence 
    presented at the criminal trial in 1995, the jury acquitted TSI of all 
    charges.
    
    NRC Evaluation of TSI's Answer to Violation I
    
        TSI's brief pro forma answer on the facts provides no rebuttal or 
    other information regarding the detailed allegations made in Violation 
    I. The answer makes no attempt to explain why the allegations are 
    incorrect. In the absence of new information, the NRC staff continues 
    to believe that violations of NRC requirements occurred as alleged in 
    Violation I, that these violations are properly classified as Severity 
    Level 1, and that these violations carry a high degree of regulatory 
    significance. Accordingly, the NRC staff finds that the proposed civil 
    penalty of $100,000 should be imposed for Violation I.
    
    NRC Conclusion
    
        The NRC has concluded that the violations alleged in the Notice 
    occurred as stated. TSI did not provide any basis for reducing the 
    severity level of the violations, and did not provide any basis for 
    mitigation of the proposed civil penalties. Consequently, the proposed 
    civil penalty in the amount of $900,000 should be imposed on TSI.
    
    [FR Doc. 99-11818 Filed 5-10-99; 8:45 am]
    BILLING CODE 7590-01-P
    
    
    

Document Information

Published:
05/11/1999
Department:
Nuclear Regulatory Commission
Entry Type:
Notice
Document Number:
99-11818
Pages:
25376-25383 (8 pages)
Docket Numbers:
EA 95-009
PDF File:
99-11818.pdf