    NUCLEAR REGULATORY COMMISSION
    [Docket No. 50-247]
    
     
    
    Consolidated Edison Company of New York, Inc.; Environmental 
    Assessment and Finding of No Significant Impact
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of an exemption from certain requirements of 10 
    CFR part 50, Appendix J. Paragraph III.D.3, Type C tests, to the 
    Consolidated Edison Company of New York, Inc. (the licensee), for the 
    Indian Point Nuclear Generating Unit No. 2, located in Westchester 
    County, New York.
    
    Environmental Assessment
    
    Identification of Proposed Action
    
        The licensee would be exempt from the requirements of 10 CFR part 
    50, appendix J. Paragraph III.D.3, to the extent that an extension 
    would be allowed for performing Type C leak rate tests on containment 
    isolation valves. These leak rate tests are currently required to be 
    performed at intervals no greater than 2 years. The exemption would 
    allow Type C leak rate tests to be performed at intervals no greater 
    than 30 months.
        By letter dated January 28, 1994, the licensee requested an 
    amendment to the Technical Specifications (TSs) and an exemption from 
    the Code of Federal Regulations (CFR) requirements to allow Type C leak 
    rate tests to be performed at intervals no greater than 30 months.
    
    Need for the Proposed Action
    
        The licensee commenced operating on 24-month fuel cycles, instead 
    of the previous 18-month fuel cycles, starting with fuel cycle 12. Fuel 
    cycle 12 started in April 1993. The requirements of 10 CFR part 50, 
    appendix J, Paragraph III.D.3, indicate the Type C leak rate tests must 
    be performed during each reactor shutdown for refueling at intervals no 
    greater than 2 years (24 months). In order to conform with this 
    regulation, the licensee could be required to shutdown Indian Point 
    Nuclear Generating Unit No. 2 and enter a forced outage prior to the 
    next refueling outage.
        The NRC staff had previously recognized that certain regulations 
    would not accommodate fuel cycles longer than 18 months. Consequently, 
    the NRC staff issued Generic Letter (GL) 91-04, ``Changes in Technical 
    Specification Surveillance Intervals to Accommodate a 24-Month Fuel 
    Cycle.'' This GL provides guidance to licensees on how to prepare 
    requests for TS amendments and regulation exemptions which are needed 
    to accommodate 24-month fuel cycles. The licensee's letter of January 
    28, 1994, followed the guidance of GL 91-04.
    
    Environmental Impacts of the Proposed Action
    
        The proposed exemption does not increase the probability or 
    consequences of accidents previously analyzed and the proposed 
    exemption does not affect facility radiation levels or facility 
    radiological effluents. The requested exemption is based, in part, on 
    increasing the margin to the allowed combined leakage limit for Type B 
    and C tests by 25 percent. In addition, the licensee has reviewed the 
    results of previous leak rate tests performed at Indian Point Nuclear 
    Generating Unit No. 2, and provided a basis for concluding that 
    containment leakage will be maintained within acceptable limits with a 
    maximum test interval of 30 months. The NRC staff has determined that 
    the licensee's submittal is consistent with the guidance provided in GL 
    91-04. Therefore, the Commission concludes that there are no 
    significant radiological environmental impacts associated with the 
    proposed exemption.
        With regard to potential nonradiological impacts, the proposed 
    exemption only involves leak rate tests on containment isolation 
    valves. It does not affect nonradiological plant effluents and has no 
    other environmental impact. Therefore, the Commission concludes that 
    there is no significant nonradiological environmental impact associated 
    with the proposed exemption.
    
    Alternatives to the Proposed Action
    
        Since the Commission has concluded that there are no significant 
    environmental effects that would result from the proposed exemption, 
    any alternatives with equal or greater environmental impacts need not 
    be evaluated. The principal alternative would be to deny the licensee's 
    request for exemption. Such action would not reduce the environmental 
    impacts of plant operations.
    
    Alternate Use of Resources
    
        This action does not involve the use of any resources not 
    previously considered in the ``Final Environmental Statements Related 
    to the Operation of Indian Point Nuclear Generating Plant Unit No. 2,'' 
    dated September 1972.
    
    Agencies and Persons Consulted
    
        The NRC staff reviewed the licensee's submittal that supports the 
    proposed exemption discussed above. The NRC staff consulted with the 
    State of New York regarding the environmental impact of the proposed 
    exemption. The State of New York had no comments regarding this 
    proposed action.
    
    Finding of No Significant Impact
    
        Based upon the foregoing environmental assessment, the Commission 
    concludes that the proposed action will not have a significant effect 
    on the quality of the human environment. Accordingly, the Commission 
    has determined not to prepare an environmental impact statement for the 
    exemption under consideration.
        For further details with respect to this action, see the licensee's 
    application for exemption dated January 28, 1994, which is available 
    for public inspection at the Commission's Public Document Room, 2120 L 
    Street, NW., Washington, DC 20555, and at the White Plains Public 
    Library, 100 Martine Avenue, White Plains, New York 10610.
    
        Detailed at Rockville, Maryland, this 6th day of May 1994.
    
        For the Nuclear Regulatory Commission.
    Robert A. Capra,
    Director, Project Directorate I-1, Division of Reactor Projects-I/II, 
    Office of Nuclear Reactor Regulation.
    [FR Doc. 94-11655 Filed 5-12-94; 8:45 am]
    BILLING CODE 7590-01-M
    
    
    

Document Information

Published:
05/13/1994
Department:
Nuclear Regulatory Commission
Entry Type:
Uncategorized Document
Document Number:
94-11655
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: May 13, 1994, Docket No. 50-247