95-12037. Pacific Northwest-Pacific Southwest Intertie ProjectNotice of Order Confirming and Approving an Extension of the Existing Step One Firm and Nonfirm Transmission Service Rate  

  • [Federal Register Volume 60, Number 95 (Wednesday, May 17, 1995)]
    [Notices]
    [Pages 26433-26434]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-12037]
    
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    Western Area Power Administration
    
    
    Pacific Northwest-Pacific Southwest Intertie Project--Notice of 
    Order Confirming and Approving an Extension of the Existing Step One 
    Firm and Nonfirm Transmission Service Rate
    
    AGENCY: Western Area Power Administration, DOE.
    
    ACTION: Notice is given of Rate Order No. WAPA-69 extending until 
    October 1, 1996, Rate Schedules INT-FT1 and INT-NFT1 for firm and 
    nonfirm transmission service over the Western Area Power Administration 
    (Western) Pacific Northwest-Pacific Southwest Intertie Project (AC 
    Intertie) transmission system.
    
    FOR FURTHER INFORMATION CONTACT:
    Mr. J. Tyler Carlson, Area Manager, Phoenix Area Office, Western Area 
    Power Administration, P.O. Box 6457, Phoenix, AZ 85005, (602) 352-2521.
    
    SUPPLEMENTARY INFORMATION: By Amendment No. 3 to Delegation Order No. 
    0204-108, published November 10, 1993 (58 FR 59716), the Secretary of 
    Energy delegated (1) the authority to develop long term power and 
    transmission rates on a nonexclusive basis to the Administrator of 
    Western; (2) the authority to confirm, approve, and place such rates in 
    effect on an interim basis to the Deputy Secretary; and (3) the 
    authority to confirm, approve, and place into effect on a final basis, 
    to remand, or to disapprove such rates to the Federal Energy Regulatory 
    Commission (FERC). Existing Department Of Energy (DOE) procedures for 
    public participation in rate adjustments (10 CFR Part 903) became 
    effective on September 18, 1985 (50 FR 37837). Pursuant to Delegation 
    Order No. 0204-108, FERC, in the order issued March 24, 1994, in Docket 
    No. EF93-5191-000, confirmed and approved Rate Schedules INT-FT1 and 
    INT-NFT1 for firm and nonfirm transmission service by the AC Intertie 
    administered by Western's Phoenix Area Office (66 FERC para.62,180). 
    The existing step one rate was approved for the period August 1, 1993, 
    through September 30, 1995. The existing step two rate was approved for 
    the period October 1, 1995, through July 31, 1998.
        The existing step two rates were to be automatically implemented on 
    October 1, 1995. However, Western will not implement the existing step 
    two rates at this time. A Stipulation Agreement was executed by Western 
    and the customers and filed with FERC on December 28, 1993, agreeing to 
    re-examine the issues from the last rate adjustment. In addition to re-
    examining these issues, Western is also investigating different rate 
    design alternatives since two new transmission line segments will be 
    energized on January 1, 1996. Western needs additional time for 
    resolution of these issues along with current customer issues. 
    Therefore, Western proposes to extend the existing step one AC Intertie 
    transmission service rates until October 1, 1996. During this time, 
    Western will be holding a series of public meetings with the AC 
    Intertie customers.
        The purpose of Rate Order No. WAPA-69 is to extend Rate Schedules 
    INT-FT1 and INT-NFT1 until October 1, 1996, to allow time for the 
    coordination and resolution of these issues and other rate adjustment 
    processes.
    
        Issued in Washington, DC, April 28, 1995.
    Bill White,
    Deputy Secretary.
    Rate Order No. WAPA-69
    
        In the matter of: Western Area Power Administration, Rate 
    Adjustment for Phoenix Area Office AC Intertie Project
    
    Order Confirming and Approving an Extension of the AC Intertie Project 
    Firm and Nonfirm Transmission Service Rate
    
    April 28, 1995.
        Transmission rates for the Pacific Northwest-Pacific Southwest 
    Intertie Project (AC Intertie) are established pursuant to the 
    Department of Energy Organization Act (42 U.S.C. 7101 et seq.); and 
    the Reclamation Act of 1902 (32 Stat. 388 et seq.), as amended and 
    supplemented by subsequent enactments, particularly section 9(c) of 
    the Reclamation Project Act of 1939 (43 U.S.C. 485h(c)), and section 
    8 of the Act of August 31, 1964 (16 U.S.C. 837g), and other acts 
    specifically applicable to the project system involved, were 
    transferred to and vested in the Secretary of Energy (Secretary).
        By Amendment No. 3 to Delegation Order No. 0204-108, published 
    November 10, 1993 (58 FR 59716), the Secretary delegated (1) the 
    authority to develop long term power and transmission rates on a 
    nonexclusive basis to the Administrator of Western; (2) the 
    authority to confirm, approve, and place such rates in effect on an 
    interim basis to the Deputy Secretary; and (3) the authority to 
    [[Page 26434]] confirm, approve, and place into effect on a final 
    basis, to remand, or to disapprove such rates to the Federal Energy 
    Regulatory Commission (FERC). Existing the Department of Energy 
    (DOE) procedures for public participation in rate adjustments (10 
    CFR Part 903) became effective on September 18, 1985 (50 FR 37837). 
    This rate extension is issued pursuant to the Delegation Order and 
    the rate extension procedures in 10 CFR Part 903. FERC is not 
    required to confirm and approve this rate extension by reason of 10 
    CFR Part 903.23(b), which states that existing rates may be extended 
    on a temporary basis by the Deputy Secretary.
    
    Background
    
        Pursuant to Delegation Order No. 0204-108, FERC, in the order 
    issued July 14, 1993, in Docket No. EF93-4151-000, confirmed and 
    approved Rate Schedule INT-FT1 for firm transmission service and 
    INT-NFT1 for nonfirm transmission service in the AC Intertie 
    administered by Western's Phoenix Area Office (PAO). The step one 
    and step two rates were approved for the period from August 1, 1993, 
    through July 31, 1998.
    
    Discussion
    
        On July 14, 1993, the Acting Assistant Secretary of Energy for 
    Energy Efficiency and Renewable Energy of DOE, approved the existing 
    rates on an interim basis for firm and nonfirm transmission service. 
    The existing step one and step two rates for firm and nonfirm 
    transmission service were placed in effect on August 1, 1993. Step 
    one of the firm transmission service rate was approved to be in 
    effect through September 30, 1995, and step two of the existing 
    rates was to become effective on October 1, 1995, and continue 
    through July 31, 1998. The FERC confirmed and approved the rates on 
    a final basis for both firm and nonfirm transmission service on 
    March 24, 1994.
        During the last AC Intertie rate adjustment process (WAPA-56), 
    the Colorado River Commission of Nevada, the Arizona Power 
    Authority, the Arizona Subcontractor Group, the Arizona Power 
    Pooling Association, Inc., and Salt River Project Agricultural 
    Improvement and Power District filed Motions to Intervene and 
    Protest FERC's confirmation and approval of the AC Intertie rates 
    described in Rate Order No. WAPA-56, in Docket No. EF93-4191-000. On 
    December 28, 1993, Western filed a Stipulation Agreement signed by 
    Western and these customers in which the intervenors withdrew their 
    protests and Western agreed to re-examine the issues raised as well 
    as commence a new rate adjustment process during fiscal year 1995.
        Western proposes to extend the existing step one AC Intertie 
    transmission service rates until October 1, 1996. Western is 
    investigating different rate design alternatives since two new 
    transmission line segments will be energized on January 1, 1996. 
    Western needs additional time for resolution of these issues along 
    with current customer issues. Even though it is anticipated that the 
    firm transmission service rate adjustment will be placed in effect 
    by December 31, 1995, the extension of the existing step one AC 
    Intertie firm and nonfirm transmission service rates is through 
    March 1, 1996, to allow for flexibility in the upcoming rate 
    adjustment process. During this time, Western will be holding a 
    series of public meetings with AC Intertie customers.
    
    Order
    
        In view of the foregoing and pursuant to the authority delegated 
    to me by the Secretary, I hereby confirm and approve for a period 
    effective October 1, 1995, until October 1, 1996, the existing step 
    one Rate Schedules INT-FT1 and INT-NFT1 for firm and nonfirm 
    transmission service over the AC Intertie transmission system.
    
        Issued in Washington, DC, April 28, 1995.
    Bill White,
    Deputy Secretary.
    [FR Doc. 95-12037 Filed 5-16-95; 8:45 am]
    BILLING CODE 6450-01-P
    
    

Document Information

Published:
05/17/1995
Department:
Western Area Power Administration
Entry Type:
Notice
Action:
Notice is given of Rate Order No. WAPA-69 extending until October 1, 1996, Rate Schedules INT-FT1 and INT-NFT1 for firm and nonfirm transmission service over the Western Area Power Administration (Western) Pacific Northwest-Pacific Southwest Intertie Project (AC Intertie) transmission system.
Document Number:
95-12037
Pages:
26433-26434 (2 pages)
PDF File:
95-12037.pdf