        Take notice that on May 11, 1995, NorAm Gas Transmission Company 
    (NGT), 1600 Smith Street, Houston, Texas 77002, filed in Docket No. 
    CP95-494-000 a request pursuant to Section 157.205 of the Commission's 
    Regulations to construct and operate a new delivery point to Arkla, a 
    division of NorAm Energy Corp., to serve a rural residential customer 
    in Coal County, Oklahoma under NGT's blanket certificate issued in 
    Docket No. CP82-384-000, pursuant to Section 7 of the Natural Gas Act, 
    all as more fully set forth in the request on file with the Commission 
    and open to public inspection.
        NGT proposes to construct one 1-inch tap, valve setting and 1-inch 
    regulator on NGT's Line 638 in Coal County, Oklahoma. NGT states that 
    Arkla would install a meter and second cut regulator to provide service 
    to a rural residential customer. The estimated volumes to be delivered 
    through this tap are approximately 85 MMBtu of natural gas per year and 
    1 MMBtu of natural gas per day, it is indicated. NGT states that NGT 
    would transport natural gas service to Arkla within Arkla's 
    entitlements under NGT's tariffs. NGT states that the establishment of 
    this delivery point is not prohibited by NGT's existing tariff and NGT 
    has sufficient capacity to accomplish deliveries at this new delivery 
    point without detriment or disadvantage to NGT's other customers. NGT 
    states that the estimated cost to install these facilities is $1,800, 
    which would be reimbursed by Arkla.
        Any person or the Commission's staff may, within 45 days after 
    issuance of the instant notice by the Commission, file pursuant to Rule 
    214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
    intervene or notice of intervention and pursuant to Section 157.205 of 
    the Regulations under the Natural Gas Act (18 CFR 157.205) a protest to 
    the request. If no protest is filed within the time allowed therefor, 
    the proposed activity shall be deemed to be authorized effective the 
    day after the time allowed for filing a protest. If a protest is filed 
    and not withdrawn within 30 days after the time allowed for filing a 
    protest, the instant request shall be treated as an application for 
    authorization pursuant to Section 7 of the Natural Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 95-12310 Filed 5-18-95; 8:45 am]
    BILLING CODE 6717-01-M
    
    

Document Information

Published:
05/19/1995
Department:
Energy Department
Entry Type:
Notice
Document Number:
95-12310
Pages:
26881-26881 (1 pages)
Docket Numbers:
Docket No. CP95-494-000
PDF File:
95-12310.pdf