95-12322. Limestone 500-kV Substation and Transmission Line  

  • [Federal Register Volume 60, Number 97 (Friday, May 19, 1995)]
    [Notices]
    [Pages 26913-26914]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-12322]
    
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    TENNESSEE VALLEY AUTHORITY
    
    
    Limestone 500-kV Substation and Transmission Line
    
    AGENCY: Tennessee Valley Authority.
    
    ACTION: Notice of no practicable alternative to impacting wetlands.
    
    -----------------------------------------------------------------------
    
    SUMMARY: The Tennessee Valley Authority (TVA) proposes to initially 
    construct three transmission lines connecting to TVA's new 500-kV 
    substation (under construction) at a site in eastern Limestone County, 
    Alabama. An environmental assessment, in accordance with the National 
    Environmental Policy Act, is being prepared. This proposal will result 
    in the disturbance of about 11.8 acres of wetlands as a result of 
    handclearing. No structures would be placed in the wetlands. Consistent 
    with the Executive Order 11990 ``Protection of Wetlands'' and TVA's 
    Wetlands Procedure, it has been determined that no practicable 
    alternative exists. TVA is requesting public comment on the impact to 
    wetlands.
    
    DATES: TVA will consider all relevant comments received by June 2, 1995 
    before a final decision is made on the proposal.
    
    ADDRESSES: Any comments on this proposal should be addressed to Dale 
    Wilhelm, National Environmental Policy Act Liaison, Tennessee Valley 
    Authority, 400 West Summit Hill Drive, Knoxville, Tennessee 37902.
    
    FOR FURTHER INFORMATION CONTACT:
    For additional information on this action, call Hugh S. Barger, 
    Transmission and Power Supply, Tennessee Valley Authority at (615) 751-
    3131.
    
    SUPPLEMENTARY INFORMATION: TVA supplies power over its bulk 500-kV 
    system to north central Alabama through its Madison and Trinity 500-kV 
    substations. Twice in the past 16 years the Madison substation has been 
    virtually isolated from large portions of the transmission network when 
    the Huntsville area transmission system was devastated by tornadoes. 
    However, available bulk power system backup prevented lengthy 
    widespread blackouts..
    
        System contingency studies show that by the summer of 1996 
    isolation or failure of the 500-kV transformer bank at Madison during 
    peak demand would result in a loss of electric service over a wide 
    area. Additionally, by the summer of 1997, loss of the 500-kV 
    transformer bank at Trinity would result in the loss of service to 
    sections of the area served by this substation. Other 
    [[Page 26914]] elements of the existing transmission system could not 
    prevent these single-contingency losses.
        TVA will finish constructing a new 500-kV substation by the summer 
    of 1996 on a site in eastern Limestone county, Alabama. Initially three 
    transmission lines would be connected into the new substation:
    
    1. The existing Browns Ferry-Madison No. 2 500-kV Transmission Line 
    would be looped about 500 feet into the substation. The existing 500-kV 
    line crosses the proposed substation site and no new right-of-way will 
    be required.
    2. The existing Athens-North Huntsville 161-kV Transmission Line would 
    also be looped into the new substation by building a new double-circuit 
    transmission line about 4.5 miles on 100 feet of new right-of-way 
    adjacent to an existing transmission line corridor and 0.4 miles on new 
    right-of-way 100 feet wide (58.9 total acres). An additional 1.5 miles 
    would be underbuilt on rebuilt 500-kV towers in the Browns Ferry-
    Madison and Trinity-Maury 500-kV lines. No new right-of-way would be 
    required in these sections.
    3. A new 161-kV transmission line would be built from the Limestone 
    substation to the Jetport, Alabama, substation in Madison County, a 
    distance of about 9 miles. Approximately 4 miles of the line would be 
    new construction of 5 miles of the existing General Motors-Jetport 161-
    kV line as a single steel pole, double-circuit 161-kV line on existing 
    right-of-way.
    
        Construction of the proposed transmission lines would result in 
    right-of-way clearing and vegetation removal affecting approximately 
    11.8 acres of wetlands. No structures would be placed within the 
    wetlands. Following construction. vegetation on these wetland rights-
    of-way would be managed so as to impede normal successional patterns. 
    This successional intervention on forested wetlands could worsen 
    impacts of previous clearing. Other wetland values an functions 
    unrelated to forest canopy vegetation would remain intact through use 
    of Best Management Practices (BMPs) for construction and maintenance.
        The proposed transmission line routes have been selected to avoid 
    wetlands as much as practical. Crossings of the Moss Spring and 
    Beaverdam Swamp are unavoidable and account for most of the wetland 
    acreage to be impacted.
        Wetland impacts would be further minimized through application of 
    the following BMPs for clearing, construction, and maintenance, on 
    these forested wetlands. These BMPs would include:
    
    1. Identified wetlands, streams, and drainways would not be modified so 
    as to alter natural hydrological patterns.
    2. Naturally occurring hydric soils would not be disturbed or modified 
    in any way that would alter their hydrological properties.
    3. Right-of-way clearing within forested wetlands would be accomplished 
    by hand where possible and would be restricted to the minimal width 
    necessary to allow for construction and operation of the proposed line.
    4. If heavy equipment is required to accomplish right-of-way clearing 
    within forested wetlands, lay-down pads would be used to remove 
    vegetation and string transmission line cable.
    5. Sediment control fencing would be placed downslope from construction 
    activity to trap sediment and prevent its migration into waterways or 
    water bodies.
    6. Within wetland areas or along streams, stumps would not be uprooted 
    or removed.
    7. Future right-of-way maintenance within identified wetlands would be 
    conducted during traditionally dry seasons and would avoid the use of 
    heavy equipment. Chemical maintenance would only be done using 
    chemicals labeled by the Environmental Protection Agency for wetlands 
    use.
    
        Dated: May 12, 1995.
    Jon M. Loney,
    Manager, Environmental Management.
    [FR Doc. 95-12322 Filed 5-18-95; 8:45 am]
    BILLING CODE 8120-01-M
    
    

Document Information

Published:
05/19/1995
Department:
Tennessee Valley Authority
Entry Type:
Notice
Action:
Notice of no practicable alternative to impacting wetlands.
Document Number:
95-12322
Dates:
TVA will consider all relevant comments received by June 2, 1995 before a final decision is made on the proposal.
Pages:
26913-26914 (2 pages)
PDF File:
95-12322.pdf