    DEPARTMENT OF ENERGY
    
    Federal Energy Regulatory Commission
    
    
    Notice Accepting Application for Filing and Requesting 
    Interventions and Protests
    
    May 14, 1999.
        Take notice that the following hydroelectric application has been 
    filed with the Commission and is available for public inspection:
        a. Type of Application: Minor License.
        b. Project No.: 11541-001.
        c. Date Filed: February 26, 1999.
        d. Applicant: Atlanta Power Company, Inc.
        e. Name of Project: Atlanta Power Station Hydroelectric Project.
        f. Location: On the Middle Fork Boise River in Elmore County, 
    Idaho, near the town of Atlanta within the Boise National Forest 
    (T5N,R11E, sections 5, 4, 3, 2, and 11 Boise Meridian).
        g. Filed Pursuant to: Federal Power Act 16 U.S.C. Secs. 791(a)-
    825(r).
        h. Applicant Contact: Lynn E. Stevenson, President Atlanta Power 
    Company, Inc., Box 100, Fairfield, ID (208) 352-4692.
        Michael C. Creamer, Esq. Givens Pursley LLP, 277 N. 6th Street, 
    suite 200, P.O. Box 2720, Boise, ID 83701 (208) 388-1200.
        i. FERC Contact: Gaylord W. Hoisington, E-mail address 
    [email protected], or telephone (202) 219-2756.
        j. Deadline for filing motions to intervene and protest: 60 days 
    from the issuance date of this notice.
    
    [[Page 27534]]
    
        All documents (original and eight copies) should be filed with: 
    David P. Boergers, Secretary, Federal Energy Regulatory Commission, 888 
    First Street, NE., Washington, DC 20426.
        The Commission's Rules of Practice and Procedure require all 
    intervenors filing documents with the Commission to serve a copy of 
    that document on each person whose name appears on the official service 
    list for the project. Further, if an intervenor files comments or 
    documents with the Commission relating to the merits of an issue that 
    may affect the responsibilities of a particular resource agency, they 
    must also serve a copy of the documents on that resource agency.
        k. Status of Environmental Analysis: This application is not ready 
    for environmental analysis at this time.
        l. Description of the Project: The proposed project would consist 
    of the existing Atlanta Power Station facilities located at the Forest 
    Service's Kirby Dam, consisting of: (1) A penstock intake structure; a 
    powerhouse, containing a single generating unit with a capacity of 187 
    kilowatts; and (3) other appurtenances.
        m. Locations of the application: A copy of the application is 
    available for inspection and reproduction at the Commission's Public 
    Reference Room, located at 888 First Street, NE, Room 2A, Washington, 
    DC 20426, or by calling (202) 208-1371. The application may be viewed 
    on http://www.ferc.fed.us/rims.htm (call (202) 208-2222 for 
    assistance). A copy is also available for inspection and reproduction 
    at the address in item h above.
        n. Individuals desiring to be included on the Commission's mailing 
    list should so indicate by writing to the Secretary of the Commission.
        Protests or Motions to Intervene--Anyone may submit a protest or a 
    motion to intervene in accordance with the requirements of Rules of 
    Practice and Procedure, 18 CFR 385.210, .211 and .214. In determining 
    the appropriate action to take, the Commission will consider all 
    protests filed, but only those who file a motion to intervene in 
    accordance with the Commission's Rules may become a party to the 
    proceeding. Any protests or motions to intervene must be received on or 
    before the specified deadline date for the particular application.
        Filing and Service of Responsive Documents--The application is not 
    ready for environmental analysis at this time; therefore, the 
    Commission is not now requesting comments, recommendations, terms and 
    conditions, or prescriptions.
        When the application is ready for environmental analysis, the 
    Commission will issue a public notice requesting comments, 
    recommendations, terms and conditions, or prescriptions.
        All filings must (1) bear in all capital letters the title 
    ``PROTEST'' or ``MOTION TO INTERVENE;'' (2) set forth in the heading 
    the name of the applicant and the project number of the application to 
    which the filing responds; (3) furnish the name, address, and telephone 
    number of the person protesting or intervening; and (4) otherwise 
    comply with the requirements of 18 CFR 385.2001 through 385.2005. 
    Agencies may obtain copies of the application directly from the 
    applicant. Any of these documents must be filed by providing the 
    original and the number of copies required by the Commission's 
    Regulations to: The Secretary and an additional copy must be sent to 
    the Director, Division of Project Review, Office of Hydropower 
    Licensing, at the above-mentioned address. A copy of any protest or 
    motion to intervene must be served upon each representative of the 
    applicant specified in the particular application.
    Linwood A. Watson, Jr.,
    Acting Secretary.
    [FR Doc. 99-12673 Filed 5-19-99; 8:45 am]
    BILLING CODE 6717-01-M
    
    
    

Document Information

Published:
05/20/1999
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number: