2020-11120. Texas Eastern Transmission, LP; Notice of Intent To Prepare an Environmental Assessment for the Proposed Appalachia to Market Project and Request for Comments on Environmental Issues  

  • Start Preamble Start Printed Page 31179

    The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Appalachia to Market Project involving construction and operation of facilities by Texas Eastern Transmission, LP (Texas Eastern) in Westmoreland, Berks, and Fayette Counties, Pennsylvania. The Commission will use this EA in its decision-making process to determine whether the project is in the public convenience and necessity.

    This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies about issues regarding the project. The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from its action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires the Commission to discover concerns the public may have about proposals. This process is referred to as “scoping.” The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of issues to address in the EA. To ensure that your comments are timely and properly recorded, please submit your comments so that the Commission receives them in Washington, DC on or before 5:00 p.m. Eastern Time on June 19, 2020.

    You can make a difference by submitting your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. Your input will help the Commission staff determine what issues they need to evaluate in the EA. Commission staff will consider all filed comments during the preparation of the EA.

    If you sent comments on this project to the Commission before the opening of this docket on May 1, 2020, you will need to file those comments in Docket No. CP20-436-000 to ensure they are considered as part of this proceeding.

    This notice is being sent to the Commission's current environmental mailing list for this project. State and local government representatives should notify their constituents of this proposed project and encourage them to comment on their areas of concern.

    If you are a landowner receiving this notice, a pipeline company representative may contact you about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable easement agreement. You are not required to enter into an agreement. However, if the Commission approves the project, that approval conveys with it the right of eminent domain. Therefore, if you and the company do not reach an easement agreement, the pipeline company could initiate condemnation proceedings in court. In such instances, compensation would be determined by a judge in accordance with state law.

    Texas Eastern provided landowners with a fact sheet prepared by the FERC entitled An Interstate Natural Gas Facility On My Land? What Do I Need To Know? This fact sheet addresses a number of typically asked questions, including the use of eminent domain and how to participate in the Commission's proceedings. It is also available for viewing on the FERC website (www.ferc.gov) at https://www.ferc.gov/​resources/​guides/​gas/​gas.pdf.

    Public Participation

    The Commission offers a free service called eSubscription which makes it easy to stay informed of all issuances and submittals regarding the dockets/projects to which you subscribe. These instant email notifications are the fastest way to receive notification and provide a link to the document files which can reduce the amount of time you spend researching proceedings. To sign up go to www.ferc.gov/​docs-filing/​esubscription.asp.

    For your convenience, there are three methods you can use to submit your comments to the Commission. The Commission encourages electronic filing of comments and has staff available to assist you at (866) 208-3676 or FercOnlineSupport@ferc.gov. Please carefully follow these instructions so that your comments are properly recorded.

    (1) You can file your comments electronically using the eComment feature, which is located on the Commission's website (www.ferc.gov) under the link to Documents and Filings. Using eComment is an easy method for submitting brief, text-only comments on a project;

    (2) You can file your comments electronically by using the eFiling feature, which is located on the Commission's website (www.ferc.gov) under the link to Documents and Filings. With eFiling, you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on eRegister. You will be asked to select the type of filing you are making; a comment on a particular project is considered a Comment on a Filing; or

    (3) You can file a paper copy of your comments by mailing them to the following address. Be sure to reference the project docket number (CP20-436-000) with your submission: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 20426.

    Summary of the Proposed Project

    The Appalachia to Market Project would consist of the following facilities and actions, all in Pennsylvania. Specifically, Texas Eastern would construct:

    • Approximately 0.8 mile of 30-inch-diameter pipeline loop [1] in the same-trench as a segment of an abandoned 30-inch-diameter pipe (that would be removed for this project) on the Texas Eastern system in Westmoreland County;
    • one crossover at the existing Bechtelsville pig [2] -launcher site in Berks County;
    • one crossover at the existing Uniontown pig-receiver site in Fayette County; and
    • other related appurtenances.

    The Appalachia to Market Project would provide up to 18,000 dekatherms per day of firm natural gas transportation service to UGI Utilities Inc. at an existing delivery point near Reading, Pennsylvania. The general location of the project facilities is shown in appendix 1.[3]

    Start Printed Page 31180

    Land Requirements for Construction

    The proposed project has been designed to minimize impacts by replacing existing pipeline and installing crossovers at previously existing aboveground facilities within and directly adjacent to Texas Eastern's existing right-of-way. Construction of the proposed facilities would disturb about 16.2 acres of land for the aboveground facilities and the pipeline. Following construction, Texas Eastern would maintain 12.9 acres for permanent operation of the project's facilities. The entire proposed 0.8-mile Delmont Loop pipeline route parallels existing pipeline, utility, or road rights-of-way with the exception of the proposed launcher and receiver barrels, which will convert 3.6 acres of land use from open land to industrial/commercial.

    The EA Process

    The EA will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings:

    • geology and soils;
    • water resources and wetlands;
    • vegetation and wildlife;
    • threatened and endangered species;
    • cultural resources;
    • land use;
    • air quality and noise;
    • public safety; and
    • cumulative impacts.

    Commission staff will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas.

    The EA will present Commission staff's independent analysis of the issues. The EA will be available in electronic format in the public record through eLibrary [4] and the Commission's website (https://www.ferc.gov/​industries/​gas/​enviro/​eis.asp). If eSubscribed, you will receive instant email notification when the EA is issued. The EA may be issued for an allotted public comment period. Commission staff will consider all comments on the EA before making recommendations to the Commission. To ensure Commission staff have the opportunity to address your comments, please carefully follow the instructions in the Public Participation section, beginning on page 2 of this notice.

    With this notice, the Commission is asking agencies with jurisdiction by law and/or special expertise with respect to the environmental issues of this project to formally cooperate in the preparation of the EA.[5] Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice.

    Consultation Under Section 106 of the National Historic Preservation Act

    In accordance with the Advisory Council on Historic Preservation's implementing regulations for section 106 of the National Historic Preservation Act, the Commission is using this notice to initiate consultation with the Pennsylvania State Historic Preservation Office, and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project's potential effects on historic properties.[6] The EA for this project will document findings on the impacts on historic properties and summarize the status of consultations under section 106.

    Environmental Mailing List

    The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries and newspapers. This list also includes all affected landowners (as defined in the Commission's regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. Commission staff will update the environmental mailing list as the analysis proceeds to ensure that Commission notices related to this environmental review are sent to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project.

    If the Commission issues the EA for an allotted public comment period, a Notice of Availability of the EA will be sent to the environmental mailing list and will provide instructions to access the electronic document on the FERC's website (www.ferc.gov).

    If you need to make changes to your name/address, or if you would like to remove your name from the mailing list, please return the attached “Mailing List Update Form” (appendix 2).

    Additional Information

    Additional information about the project is available from the Commission's Office of External Affairs, at (866) 208-FERC, or on the FERC website at www.ferc.gov using the eLibrary link. Click on the eLibrary link, click on General Search and enter the docket number in the Docket Number field, excluding the last three digits (i.e., CP20-436). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or (866) 208-3676, or for TTY, contact (202) 502-8659. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings.

    Public sessions or site visits will be posted on the Commission's calendar located at www.ferc.gov/​EventCalendar/​EventsList.aspx along with other related information.

    Start Signature

    Dated: May 18, 2020.

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    Footnotes

    1.  A pipeline loop is a segment of pipe constructed parallel to an existing pipeline to increase capacity.

    Back to Citation

    2.  A pig is a tool that the pipeline company inserts into and pushes through the pipeline for cleaning the pipeline, conducting internal inspections, or other purposes.

    Back to Citation

    3.  The appendices referenced in this notice will not appear in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at www.ferc.gov using the link called “eLibrary” or from the Commission's Public Reference Room, 888 First Street NE, Washington, DC 20426, or call (202) 502-8371. For instructions on connecting to eLibrary, refer to the last page of this notice.

    Back to Citation

    4.  For instructions on connecting to eLibrary, refer to the last page of this notice.

    Back to Citation

    5.  The Council on Environmental Quality regulations addressing cooperating agency responsibilities are at Title 40, Code of Federal Regulations, Part 1501.6.

    Back to Citation

    6.  The Advisory Council on Historic Preservation's regulations are at Title 36, Code of Federal Regulations, Part 800. Those regulations define historic properties as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register of Historic Places.

    Back to Citation

    [FR Doc. 2020-11120 Filed 5-21-20; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
05/22/2020
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2020-11120
Pages:
31179-31180 (2 pages)
Docket Numbers:
Docket No. CP20-436-000
PDF File:
2020-11120.Pdf