96-12919. Northwest Pipeline Corporation, et al.; Natural Gas Certificate Filings  

  • [Federal Register Volume 61, Number 101 (Thursday, May 23, 1996)]
    [Notices]
    [Pages 25865-25866]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 96-12919]
    
    
    
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    [Docket No. CP96-501-000, et al.]
    
    
    Northwest Pipeline Corporation, et al.; Natural Gas Certificate 
    Filings
    
    May 15, 1996.
        Take notice that the following filings have been made with the 
    Commission:
    
    1. Northwest Pipeline Corporation
    
    [Docket No. CP96-501-000]
    
        Take notice that, on May 6, 1996, Northwest Pipeline Corporation 
    (Northwest), 295 Chipeta Way, Salt Lake City, Utah 84108, filed an 
    abbreviated application in Docket No. CP96-501-000, pursuant to section 
    7(b) of the Natural Gas Act and Section 157.7(a) of the Commission's 
    regulations, for authorization to remove its previously abandoned in-
    place, 10-inch diameter South Seattle Lateral crossing and adjacent 10-
    inch diameter lateral loop line crossing of Madsen Creek, in Section 
    26, T23N, R5E, King County, Washington, all as more fully set forth in 
    the application, which is on file with the Commission and open to 
    public inspection.
        Northwest states that it relocated and replaced the above 
    referenced 175-foot long Madsen Creek crossing segments in 1993, 
    pursuant to its blanket certificate authority in Docket No. CP82-433 
    (20 FERC para. 62,412), but did not remove the two replaced and exposed 
    pipeline segments. Instead, these pipeline segments were abandoned in-
    place in order to avoid further damage to the Madsen Creek ravine.
        Northwest states that (as reported in Docket No. CP82-433) it 
    intended to remove these pipeline segments in 1994, as part of the 
    project area restoration, but the planned restoration was not completed 
    and the pipeline segments were not removed, due to Northwest's 
    prolonged negotiations with King County over plans for the restoration 
    and bank stabilization of the Madsen Creek ravine. According to 
    Northwest, it has reached agreement with King County regarding the 
    restoration and bank stabilization plans for the Madsen Creek ravine, 
    and now plans to remove the two exposed pipeline segments in July of 
    1996. Northwest states that (consistent with the plans negotiated with 
    King County) it seeks the requisite Commission approvals to remove the 
    previously abandoned pipeline segments, and estimates that the project 
    will cost approximately $45,000.
        Comment date: June 5, 1996, in accordance with Standard Paragraph F 
    at the end of this notice.
    
    2. K N Interstate Gas Transmission Company
    
    [Docket No. CP96-509-000]
    
        Take notice that on May 7, 1996, K N Interstate Transmission 
    Company (K N Interstate), P. O. Box 281304, Lakewood, Colorado 80228, 
    filed in Docket No. CP96-509-000 a request pursuant to Sections 157.205 
    and 157.212 of the Commission's Regulations under the Natural Gas Act 
    (18 CFR 157.205, 157.212) for authorization to install and operate 
    nineteen new delivery taps and appurtenant facilities located in 
    Colorado, Kansas, Nebraska and Wyoming under K N Interstate's blanket 
    certificate issued in Docket No. CP83-140-000 et. al. pursuant to 
    Section 7 of the Natural Gas Act, all as more fully set forth in the 
    request that is on file with the Commission and open to public 
    inspection.
        K N Interstate states that the proposed delivery points would be 
    located on its main transmission system in Colorado, Kansas, Nebraska 
    and Wyoming. The counties involved are Phillips and Yuma Counties in 
    Colorado; Norton and Scott Counties in Kansas; Adams, Clay, Franklin, 
    Hall, Harlan, Keith, Phelps, Stanton, Thayer and Webster Counties in 
    Nebraska; and Goshen and Platte Counties in Wyoming. These proposed 
    taps will be added as delivery points under an existing transportation 
    service agreement between K N Interstate and K N Energy, Inc. (K N) and 
    will be used by K N to facilitate natural gas delivery to direct retail 
    customers.
        K N Interstate states that these new delivery facilities are not 
    prohibited by its existing tariff and that it has sufficient capacity 
    to accomplish deliveries without detriment or disadvantage to other 
    customers. The proposed delivery facilities will not have an effect on 
    K N Interstate's peak day and annual deliveries and the total volumes 
    delivered will be within the current maximum transportation quantities 
    set forth in K N Interstate's transportation service agreement with K 
    N.
        Comment date: July 1, 1996, in accordance with Standard Paragraph G 
    at the end of this notice.
    
    3. NorAm Gas Transmission Company
    
    [Docket No. CP96-513-000]
    
        Take notice that on May 8, 1996, NorAm Gas Transmission Company 
    (NGT), 1600 Smith Street, Houston, Texas 77002, filed in Docket No. 
    CP96-513-000 a request pursuant to Sections 157.205 and 157.211 of the 
    Commission's Regulations under the Natural Gas Act (18 CFR 157.205, 
    157.211) for authorization to construct
    
    [[Page 25866]]
    
    and operate certain facilities in Texas under NGT's blanket certificate 
    issued in Docket No. CP82-384-000, et al., pursuant to Section 7 of the 
    Natural Gas Act, all as more fully set forth in the request that is on 
    file with the Commission and open to public inspection.
        NGT proposes to design, install, construct and operate a dual 6 
    inch meter and appurtenant facilities, 1.5 miles of 8-inch pipeline and 
    a high pressure tap and valve assembly necessary to deliver gas. The 
    proposed delivery lateral will interconnect with NGT's line AM-47 in 
    Russell Survey, Marion County, Texas. This subject line, AM-199, will 
    be used to deliver natural gas to Southwestern Electric Power Company's 
    electric generating plant near Avinger, Texas. The estimated volumes to 
    be delivered to this delivery tap are approximately 12,000 MMBtu per 
    day or an estimated 4,380,000 MMBtu on an annual basis. The subject 
    delivery lateral will be constructed at an estimated cost of 
    approximately $500,985.
        Comment date: July 1, 1996, in accordance with Standard Paragraph G 
    at the end of this notice.
    
    4. Williams Natural Gas Company
    
    [Docket No. CP96-515-000]
    
        Take notice that on May 8, 1996, Williams Natural Gas Company 
    (WNG), P.O. Box 3288, Tulsa, Oklahoma 74101, filed in Docket No. CP96-
    515-000 a request pursuant to Sections 157.205 and 157.216 of the 
    Commission's Regulations under the Natural Gas Act (18 CFR 157.205, 
    157.216) for authorization to abandon certain facilities originally 
    installed for the receipt of transportation gas in Logan, Creek and 
    Payne Counties, Oklahoma under WNG's blanket certificate issued in 
    Docket No. CP82-479-000 pursuant to Section 7 of the Natural Gas Act, 
    all as more fully set forth in the request that is on file with the 
    Commission and open to public inspection.
        WNG proposes to abandon by removal measuring and appurtenant 
    facilities originally installed for receipt of transportation gas from 
    Associated Gas, Inc. located in Logan County, Oklahoma; Engasco, Inc. 
    and PanEnergy Field Services, Inc. located in Creek County, Oklahoma; 
    and TAG Petroleum, Inc. located in Payne County, Oklahoma. WNG states 
    that the subject facilities are no longer needed. WNG estimates the 
    total abandonment cost to be approximately $4,900 with a salvage value 
    of $650.
        Comment date: July 1, 1996, in accordance with Standard Paragraph G 
    at the end of this notice.
    
    Standard Paragraphs
    
        F. Any person desiring to be heard or make any protest with 
    reference to said filing should on or before the comment date file with 
    the Federal Energy Regulatory Commission, 888 First Street, N.E., 
    Washington, D.C. 20426, a motion to intervene or a protest in 
    accordance with the requirements of the Commission's Rules of Practice 
    and Procedure (18 CFR 385.211 and 385.214) and the Regulations under 
    the Natural Gas Act (18 CFR 157.10). All protests filed with the 
    Commission will be considered by it in determining the appropriate 
    action to be taken but will not serve to make the protestants parties 
    to the proceeding. Any person wishing to become a party to a proceeding 
    or to participate as a party in any hearing therein must file a motion 
    to intervene in accordance with the Commission's Rules.
        Take further notice that, pursuant to the authority contained in 
    and subject to jurisdiction conferred upon the Federal Energy 
    Regulatory Commission by Sections 7 and 15 of the Natural Gas Act and 
    the Commission's Rules of Practice and Procedure, a hearing will be 
    held without further notice before the Commission or its designee on 
    this filing if no motion to intervene is filed within the time required 
    herein, if the Commission on its own review of the matter finds that a 
    grant of the certificate is required by the public convenience and 
    necessity. If a motion for leave to intervene is timely filed, or if 
    the Commission on its own motion believes that a formal hearing is 
    required, further notice of such hearing will be duly given.
        Under the procedure herein provided for, unless otherwise advised, 
    it will be unnecessary for the applicant to appear or be represented at 
    the hearing.
        G. Any person or the Commission's staff may, within 45 days after 
    the issuance of the instant notice by the Commission, file pursuant to 
    Rule 214 of the Commission's Procedural Rules (18 CFR 385.214) a motion 
    to intervene or notice of intervention and pursuant to Section 157.205 
    of the Regulations under the Natural Gas Act (18 CFR 157.205) a protest 
    to the request. If no protest is filed within the time allowed 
    therefore, the proposed activity shall be deemed to be authorized 
    effective the day after the time allowed for filing a protest. If a 
    protest is filed and not withdrawn within 30 days after the time 
    allowed for filing a protest, the instant request shall be treated as 
    an application for authorization pursuant to Section 7 of the Natural 
    Gas Act.
    Lois D. Cashell,
    Secretary.
    [FR Doc. 96-12919 Filed 5-22-96; 8:45 am]
    BILLING CODE 6717-01-P
    
    

Document Information

Published:
05/23/1996
Department:
Energy Department
Entry Type:
Notice
Document Number:
96-12919
Dates:
June 5, 1996, in accordance with Standard Paragraph F at the end of this notice.
Pages:
25865-25866 (2 pages)
Docket Numbers:
Docket No. CP96-501-000, et al.
PDF File:
96-12919.pdf