2024-11504. Southern California Edison Company; Notice of Intent To Prepare an Environmental Assessment  

  • Start Preamble

    On December 23, 2019, Southern California Edison Company filed a relicense application for the 8.85-megawatt Kaweah Hydroelectric Project No. 298 (project). The project is located on the Kaweah River and East Fork Kaweah River in Tulare County, California.

    In accordance with the Commission's regulations, on April 15, 2020, Commission staff issued a notice that the project was ready for environmental analysis (REA Notice). Based on the information in the record, including comments filed on the REA Notice, staff does not anticipate that licensing the project would constitute a major federal action significantly affecting the quality of the human environment. Therefore, staff intends to prepare an Environmental Assessment (EA) on the application to relicense the project.

    The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by staff and considered in the Commission's final licensing decision.

    The Commission's Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502-6595 or OPP@ferc.gov.Start Printed Page 45878

    The application will be processed according to the following schedule. Revisions to the schedule may be made as appropriate.

    MilestoneTarget date
    Commission issues EAJune 2024.1
    Comments on EAAugust 2024.

    Any questions regarding this notice may be directed to Rebecca Kipp at (202) 502-8846 or rebecca.kipp@ferc.gov.

    Start Signature

    Dated: May 20, 2024.

    Debbie-Anne A. Reese,

    Acting Secretary.

    End Signature End Preamble

    Footnotes

    1.  The Council on Environmental Quality's (CEQ) regulations under 40 CFR 1501.10(b)(1) (2023) require that EAs be completed within 1 year of the federal action agency's decision to prepare an EA. See National Environmental Policy Act, 42 U.S.C. 4321 et seq., as amended by section 107(g)(1)(B)(iii) of the Fiscal Responsibility Act of 2023, Public Law 118-5, 4336a, 137 Stat. 42.

    Back to Citation

    [FR Doc. 2024-11504 Filed 5-23-24; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
05/24/2024
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
2024-11504
Pages:
45877-45878 (2 pages)
Docket Numbers:
Project No. 298-081
PDF File:
2024-11504.pdf