94-12859. Bellefonte Nuclear Plant; Environmental Assessment and Finding of No Significant Impact  

  • [Federal Register Volume 59, Number 101 (Thursday, May 26, 1994)]
    [Unknown Section]
    [Page 0]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 94-12859]
    
    
    [[Page Unknown]]
    
    [Federal Register: May 26, 1994]
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    NUCLEAR REGULATORY COMMISSION
    
    [Docket Nos. 50-438 and 50-439]
    
     
    
    Bellefonte Nuclear Plant; Environmental Assessment and Finding of 
    No Significant Impact
    
        The U.S. Nuclear Regulatory Commission (the Commission) is 
    considering issuance of extensions of the latest construction 
    completion dates specified in Construction Permit Nos. CPPR-122 and 
    CPPR-123 issued to Tennessee Valley Authority (TVA, applicant) for the 
    Bellefonte Nuclear Plant (BLN), Units 1 and 2, respectively. The 
    facility is located at the applicant's site on the west shore of 
    Guntersville Reservoir, about 6 miles east-northeast of Scottsboro, 
    Alabama.
    
    Environmental Assessment
    
    Identification of Proposed Action
    
        The proposed action would extend the latest construction completion 
    date of Construction Permit No. CPPR-122 from July 1, 1994 to October 
    1, 2001 and the latest construction completion date of Construction 
    Permit No. CPPR-123 from July 1, 1996 to October 1, 2004. The proposed 
    action is in response to the applicant's request dated April 19, 1994.
    
    The Need for the Proposed Action
    
        The proposed action is needed because the construction of the 
    facility is not yet fully completed. The applicant requested the 
    extensions because construction activities had been deferred in 1988 
    due, in part, to a lower than expected load forecast. On March 23, 
    1993, TVA notified NRC that it planned to resume completion activities 
    120 days from the date of the letter. As a result of the delay from the 
    inactivity during the construction deferral, TVA is unable to complete 
    the construction of the two units before the expiration dates of the 
    construction permits, therefore extensions are now necessary. In 
    addition, pursuant to the provisions of the Energy Policy Act of 1992, 
    TVA is currently engaged in an Integrated Resource Planning (IRP) 
    process to consider the least cost options for providing an adequate 
    supply of electricity to TVA's customers. As part of this planning 
    process, TVA will evaluate the completion of the BLN units along with 
    other generating options. The IRP process is presently scheduled for 
    completion in November 1995. Additional delays associated with the 
    above efforts to ensure that BLN meets regulatory requirements and 
    licensing commitments make it necessary for TVA to request extensions 
    of the expiration dates for Construction Permit Nos. CPPR-122 and CPPR-
    123.
    
    Environmental Impacts of the Proposed Action
    
        The environmental impacts associated with the construction of the 
    facility have been previously discussed and evaluated in the staff's 
    Final Environmental Statement (FES) issued in June 1974 for the 
    construction permit stage which covered construction of both units.
        The proposed extensions will not allow any work to be performed 
    that is not already allowed by the existing construction permit. The 
    only change is that the environmental impacts discussed and evaluated 
    in the FES will be gradual and extend to longer periods of time than 
    the construction periods considered in the FES. The probability of 
    accidents has not been increased and post-accident radiological 
    releases will not be greater than previously determined, nor do the 
    proposed extensions otherwise affect radiological plant effluents. 
    Therefore, the Commission concludes that there are no significant 
    radiological environmental impacts associated with the proposed 
    extensions.
        Based on the foregoing, the NRC staff has concluded that the 
    proposed action would have no significant environmental impact. Since 
    this action would only extend the period of construction activities 
    described in the FES, it does not involve any different impacts or a 
    significant change to those impacts described and analyzed in the 
    original environmental impact statement. Consequently, an environmental 
    impact statement addressing the proposed action is not required.
    
    Alternatives Considered
    
        A possible alternative to the proposed action would be to deny the 
    request. Under this alternative, the applicant would not be able to 
    complete construction of the facility. This would result in a denial of 
    the benefit of power production. This option would not eliminate the 
    environmental impacts of construction already incurred.
        If construction were halted and not completed, site redress 
    activities would restore some small areas to their natural states. This 
    would be a slight environmental benefit, but much outweighed by the 
    economic losses from denial of use of a facility that is nearly 
    completed. (Unit 1 is about 85% complete, and Unit 2 is about 45% 
    complete). Therefore, this alternative is rejected.
    
    Alternative Use of Resources
    
        This action does not involve the use of resources not previously 
    considered in the FES for Bellefonte.
    
    Agencies and Persons Contacted
    
        The NRC staff reviewed the applicant's request and applicable 
    documents referenced therein that support the extensions. The NRC did 
    not consult other agencies or persons.
    
    Finding Of No Significant Impact
    
        The Commission has determined not to prepare an environmental 
    impact statement for this action. Based upon the environmental 
    assessment, the staff concludes that this action will not have a 
    significant effect on the quality of the human environment.
        For details with respect to this action, see the request for 
    extensions dated April 19, 1994, which is available for public 
    inspection at the Commission Public Document Room, 2120 L Street, NW., 
    Washington, DC and at the Local Public Document Room, Scottsboro Public 
    Library, 1002 South Broad Street, Scottsboro, Alabama 37402.
    
        Dated at Rockville, Maryland this 19th day of May 1994.
        For the Nuclear Regulatory Commission
    Frederick J. Hebdon,
    Director, Project Directorate II-4, Division of Reactor Projects I/II, 
    Office of Nuclear Reactor Regulation.
    [FR Doc. 94-12859 Filed 5-25-94; 8:45 am]
    BILLING CODE 7590-01-M
    
    
    

Document Information

Published:
05/26/1994
Department:
Nuclear Regulatory Commission
Entry Type:
Uncategorized Document
Document Number:
94-12859
Pages:
0-0 (1 pages)
Docket Numbers:
Federal Register: May 26, 1994, Docket Nos. 50-438 and 50-439