-
Start Preamble
Take notice that on May 13, 2020, Golden Pass Pipeline LLC (Golden Pass Pipeline), 811 Louisiana Street, Houston, Texas 77002, filed an application pursuant to section 7 of the Natural Gas Act and part 157 of the Commission's regulations for authority to amend its order issued on December 21, 2016, granting Golden Pass LNG authority to site, construct and operate facilities for the exportation of liquefied natural gas and granting Golden Pass Pipeline authority to expand its existing pipeline system (Compression Relocation and Modification Project). The Compression Relocation and Modification Project consists of the following: (1) Relocation of an authorized compressor station from Milepost 66 to Milepost 69 on the Golden Pass Pipeline system; (2) additional compression at the relocated compressor station, (3) add a meter station near Milepost 69 to support an Interconnect with the proposed interstate pipeline to be constructed and operated by Enable Gulf Run Transmission, LLC, (4) remove any bi-directional piping modification to the Interconnect for Tennessee Gas Pipeline Company, L.L.C. (Tennessee Gas), (5) relocate looping facilities to reflect the relocation of the compressor station and the cancellation of Tennessee Gas as an input source to Golden Pass Pipeline, and (6) minor modifications to existing interconnections at Milepost 66 and Milepost 68, all as more fully described in their application.
Any questions regarding this application should be addressed to Blaine Yamagata, Vice President and General Counsel, Golden Pass LNG, 811 Louisiana Street, Suite 1500, Houston, Texas 77002; or to Kevin M. Sweeney, Law Office of Kevin M. Sweeney, 1625 K Street NW, Washington, DC 20006, by telephone at (202) 609-7709.
In addition to publishing the full text of this document in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page (http://ferc.gov) using the eLibrary link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission's Public Reference Room, due to the proclamation declaring a National Emergency concerning the Novel Coronavirus Disease (COVID-19), issued by the President on March 13, 2020. For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY, (202) 502-8659.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission's public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff's issuance of the EA for this proposal. The filing of the EA in the Commission's public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the EA.
There are two ways to become involved in the Commission's review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below file with the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 3 copies of filings made in the proceeding with the Commission and must provide a copy to the applicant and to every other party. Only parties to the proceeding can ask for court review of Commission orders in the proceeding.
However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission's rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest.
Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission's environmental mailing list and will be notified of any meetings associated with the Commission's environmental review process. Environmental commenters Start Printed Page 31774will not be required to serve copies of filed documents on all other parties. However, the non-party commenters will not receive copies of all documents filed by other parties or issued by the Commission and will not have the right to seek court review of the Commission's final order.
As of the February 27, 2018 date of the Commission's order in Docket No. CP16-4-001, the Commission will apply its revised practice concerning out-of-time motions to intervene in any new Natural Gas Act section 3 or section 7 proceeding.[1] Persons desiring to become a party to a certificate proceeding are to intervene in a timely manner. If seeking to intervene out-of-time, the movant is required to show good cause why the time limitation should be waived, and should provide justification by reference to factors set forth in Rule 214(d)(1) of the Commission's Rules and Regulations.[2]
The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the eFiling link at http://www.ferc.gov. Persons unable to file electronically should submit an original and 3 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426.
Comment Date: 5:00 p.m. Eastern Standard Time on June 10, 2020.
Start SignatureDated: May 20, 2020.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
Footnotes
1. Tennessee Gas Pipeline Company, L.L.C., 162 FERC ¶ 61,167 at ¶ 50 (2018).
Back to Citation[FR Doc. 2020-11328 Filed 5-26-20; 8:45 am]
BILLING CODE 6717-01-P
Document Information
- Published:
- 05/27/2020
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 2020-11328
- Dates:
- 5:00 p.m. Eastern Standard Time on June 10, 2020.
- Pages:
- 31773-31774 (2 pages)
- Docket Numbers:
- Docket Nos. CP20-454-000, CP14-518-000
- PDF File:
- 2020-11328.pdf