96-13224. Tennessee Gas Pipeline Company; Notice of Request Under Blanket Authorization
[Federal Register Volume 61, Number 103 (Tuesday, May 28, 1996)]
[Notices]
[Page 26512]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 96-13224]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
[Docket No. CP96-524-000]
Tennessee Gas Pipeline Company; Notice of Request Under Blanket
Authorization
May 21, 1996.
Take notice that on May 17, 1996, Tennessee Gas Pipeline Company
(Tennessee), Post Office Box 2511, Houston, Texas 77252, filed a
request with the Commission in Docket No. CP96-524-000 pursuant to
Sections 157.205 and 157.212 of the Commission's Regulations under the
Natural Gas Act (NGA) for authorization to establish a delivery point
for Nashville Gas Company (Nashville) authorized in blanket certificate
issued in Docket No. CP82-413-000, all as more fully set forth in the
request on file with the Commission and open to public inspection.
Tennessee proposes to install a new delivery point on Tennessee's
system in Cheatham County, Tennessee which would be used for the
delivery of natural gas to Nashville, a division of Piedmont Natural
Gas Company. Tennessee states that it would install, own, operate and
maintain two two-inch hot taps, approximately 60 feet of two-inch
interconnect piping, one two-inch turbine meter with bypass, and
electronic gas measurement equipment. The hot tap and interconnect pipe
would be located on Tennessee's existing right-of-way. The meter
station would be located on a site adjacent to Tennessee's existing
right-of-way provided by Nashville. The estimated cost of the meter
station would be $102,024.00, which would be reimbursed by Nashville.
Any person or the Commission's staff may, within 45 days after the
Commission has issued this notice, file pursuant to Rule 214 of the
Commission's Procedural Rules (18 CFR 385.214) a motion to intervene or
notice of intervention and pursuant to Section 157.205 of the
Regulations under the NGA (18 CFR 157.205) a protest to the request. If
no protest is filed within the allowed time, the proposed activity
shall be deemed to be authorized effective the day after the time
allowed for filing a protest. If a protest is filed and not withdrawn
within 30 days after the time allowed for filing a protest, the instant
request shall be treated as an application for authorization pursuant
to Section 7 of the NGA.
Lois D. Cashell,
Secretary.
[FR Doc. 96-13224 Filed 5-24-96; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 05/28/1996
- Department:
- Energy Department
- Entry Type:
- Notice
- Document Number:
- 96-13224
- Pages:
- 26512-26512 (1 pages)
- Docket Numbers:
- Docket No. CP96-524-000
- PDF File:
-
96-13224.pdf