95-10902. Office of Civilian Radioactive Waste Management; Nuclear Waste Acceptance Issues  

  • [Federal Register Volume 60, Number 85 (Wednesday, May 3, 1995)]
    [Notices]
    [Pages 21793-21798]
    From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
    [FR Doc No: 95-10902]
    
    
    
    =======================================================================
    -----------------------------------------------------------------------
    
    DEPARTMENT OF ENERGY
    
    
    Office of Civilian Radioactive Waste Management; Nuclear Waste 
    Acceptance Issues
    
    AGENCY: Office of Civilian Radioactive Waste Management, Department of 
    Energy.
    
    ACTION: Department of Energy final interpretation of nuclear waste 
    acceptance issues.
    
    -----------------------------------------------------------------------
    
    SUMMARY: This Notice responds to public comments on the Department of 
    Energy (DOE) Notice of Inquiry on Waste Acceptance Issues published on 
    May 25, 1994 (59 FR 27007). After analyzing public comments received in 
    response to the Notice, DOE has concluded that it does not have an 
    unconditional statutory or contractual obligation to accept high level 
    waste and spent nuclear fuel beginning [[Page 21794]] January 31, 1998 
    in the absence of a repository or interim storage facility constructed 
    under the Nuclear Waste Policy Act of 1982, as amended. In addition, 
    DOE has concluded that it lacks statutory authority under the Act to 
    provide interim storage.
    
    FOR FURTHER INFORMATION CONTACT: Mr. Robert Waxman of the Department of 
    Energy Office of General Counsel at (202) 586-6975.
    
    SUPPLEMENTARY INFORMATION:
    
    I. Background
    
        The Nuclear Waste Policy Act of 1982, as amended (Act or NWPA), 42 
    U.S.C. 10101 et seq., provides a comprehensive framework for disposing 
    of high level radioactive waste and spent nuclear fuel (SNF) generated 
    by civilian nuclear power reactors. In general, the Act sets forth 
    procedures for selecting a repository site and developing a repository 
    for disposal of high-level radioactive waste and SNF and for financing 
    the cost of such disposal. Section 302(a) of the Act authorizes the 
    Secretary to enter into contracts with the owners and generators of SNF 
    of domestic origin (utilities) for the acceptance and disposal of 
    SNF,1 and stipulates that the contracts provide that the Secretary 
    shall take title to the SNF as expeditiously as practicable following 
    commencement of operation of a repository. In return for the payment of 
    fees, section 302(a) also stipulates that the contracts provide that 
    the Secretary, beginning not later than January 31, 1998 will dispose 
    of such SNF.
    
        \1\ In this notice, we limit our discussion to SNF, because that 
    is the primary concern of the utilities with whom DOE has executed 
    the Standard Contract.
    ---------------------------------------------------------------------------
    
        DOE implemented the provisions of section 302(a) through 
    rulemaking. Following notice and comment, DOE promulgated the Standard 
    Contract for Disposal of Spent Nuclear Fuel and/or High Level Nuclear 
    Waste (Standard Contract), which set forth the contractual terms under 
    which the Department would make its disposal services available. 48 FR 
    16590 (April 18, 1983), codified at 10 CFR part 961. Under the terms of 
    the final rule promulgating the Standard Contract, all civilian nuclear 
    utilities desiring to dispose of SNF signed individual versions of the 
    Standard Contract.
        Although the Act originally envisioned that a geologic repository 
    would be in operation, and DOE would be prepared to begin acceptance of 
    SNF by January 31, 1998, it since has become apparent that neither a 
    repository nor an interim storage facility constructed under the Act 
    will be available by 1998. DOE currently projects that the earliest 
    possible date for acceptance of waste for disposal at a repository is 
    2010.
        Accordingly, DOE published the Notice of Inquiry on Waste 
    Acceptance Issues (NOI) to elicit the views of interested parties on: 
    (1) DOE's preliminary view that it does not have an obligation to 
    accept SNF in the absence of an operational repository or interim 
    storage facility constructed under the Act; (2) the need for interim 
    storage prior to repository operation; and (3) use of the Nuclear Waste 
    Fund to offset a portion of the financial burdens that may be incurred 
    by utilities in continuing to store SNF at reactor sites beyond 1998. 
    Written comments were initially due on or before September 22, 1994. 59 
    FR 27007 (May 25, 1994). DOE extended the comment period on the NOI 
    until December 19, 1994 to permit additional public comment. 59 FR 
    52524 (October 18, 1994).
    
    II. Written Comments
    
        DOE received 1,111 written responses to the NOI, representing 1,476 
    signatories, including utilities (38 responses), public utility 
    commissions and utility regulators (26 responses), Federal, state, and 
    local governments, agencies, and representatives (23 responses), 
    industry representatives and companies (30 responses), public interest 
    groups and other organizations (19 responses), and members of the 
    general public (975 responses). All written comments received by DOE in 
    response to the NOI were carefully reviewed and fully considered. The 
    majority of the responses to the NOI addressed the issue of DOE's legal 
    obligation to accept SNF beginning in 1998 and asserted that DOE has an 
    unconditional obligation to begin accepting SNF from the utilities by 
    January 31, 1998.
        DOE previously published a notice of the availability of DOE/RW-
    0462, ``Summary of Responses to the Notice of Inquiry on Waste 
    Acceptance Issues'' (March 1995). 60 FR 14739 (March 20, 1995). That 
    report contains a summary of all the comments received in response to 
    the NOI.
        This Notice sets forth DOE's conclusions with respect to the legal 
    issues involved in the NOI. Section III below discusses DOE's final 
    interpretation of its obligations with respect to the 1998 waste 
    acceptance issue, addresses the issue of DOE's authority under the Act 
    to provide interim storage, and also contains DOE's conclusions on the 
    legal availability of the Nuclear Waste Fund to offset the potential 
    financial burdens that may be incurred by utilities in storing SNF on-
    site beyond 1998.
    
    III. Final Interpretation of Agency Obligations and Authorities Under 
    the Act
    
        Most of the commenters on the NOI expressed the view that the 
    language in section 302(a)(5)(B) of the Act, which provides that ``in 
    return for the payment of fees established by this section, the 
    Secretary, beginning not later than January 31, 1998, will dispose of 
    the high-level radioactive waste or spent nuclear fuel as provided in 
    this subtitle,'' 42 U.S.C. 10222(a)(5)(B), creates an unconditional 
    legal obligation, beginning January 31, 1998, for DOE to initiate 
    acceptance of SNF from utilities under the Standard Contract. According 
    to these commenters, DOE's obligation is clear, non-discretionary, and 
    not inconsistent with DOE's duty to take title to SNF under section 
    302(a)(5)(A) of the Act following commencement of repository 
    operations. 42 U.S.C. 10222(a)(5)(A).
        However, some commenters contended that DOE does not have an 
    unconditional duty to dispose of SNF beginning in 1998 in the absence 
    of an operational repository. They asserted that the obligations to 
    take title and dispose of SNF established in subsections (5)(A) and (B) 
    of section 302(a) of the Act must be read together and ultimately are 
    dependent upon the existence of an operational repository. Based upon 
    the entire statutory scheme and the legislative history of the Act, 
    these commenters suggested that the January 31, 1998 date does not 
    create an obligation to initiate SNF disposal regardless of the 
    availability of a repository, but rather indicates the ``sense of 
    Congress'' concerning an appropriate target date for arriving at a 
    solution to the problem of accumulating high level nuclear waste and 
    spent nuclear fuel.
        After considering the views of the commenters, the provisions of 
    the Act and its legislative history, and the terms and conditions of 
    the Standard Contract, DOE has concluded that it does not have a legal 
    obligation under either the Act or the Standard Contract to begin 
    disposal of SNF by January 31, 1998, in the absence of a repository or 
    interim storage facility constructed under the Act.
    
    A. DOE's Final Interpretation of Its Obligations Under Section 
    302(a)(5)
    
        1. The Act does not impose a statutory obligation on DOE to begin 
    nuclear waste disposal in 1998 in the absence of [[Page 21795]] a 
    disposal or interim storage facility constructed under the Act.
        Section 302(a)(1) of the Act authorizes the Secretary of Energy to 
    enter into contracts for acceptance of title, transportation, and 
    disposal of SNF with any person who generates or holds title to spent 
    fuel of domestic origin. 42 U.S.C. 10222(a)(1). Section 302(a)(5) 
    states that such contracts shall provide that:
    
        (A) Following commencement of operation of a repository, the 
    Secretary shall take title to the high-level radioactive waste or 
    spent nuclear fuel involved as expeditiously as practicable upon the 
    request of the generator or owner of such waste or spent fuel; and
        (B) In return for payment of fees established by this section, 
    the Secretary, beginning not later than January 31, 1998, will 
    dispose of the high-level radioactive waste or spent nuclear fuel 
    involved as provided in this subtitle.
    
    42 U.S.C. 10222(a)(5). DOE's Standard Contract contains a provision 
    that reflects this statutory mandate. See 10 CFR 961.11.
        a. Section 302(a)(5)(A), the so-called ``take title'' provision of 
    the Act, requires that each contract executed by DOE under the Act 
    provide that ``the Secretary shall take title to the high-level 
    radioactive waste or spent nuclear fuel involved as expeditiously as 
    practicable upon request of the generator or owner of such waste or 
    spent fuel,'' but specifically provides that the obligation to take 
    title applies only ``following commencement of operation of a 
    repository.'' 42 U.S.C. 10222 (a)(5)(A). Thus, the Act is clear that 
    DOE is required to take title ``expeditiously,'' but only ``following 
    commencement of operation of a repository.'' 42 U.S.C. 10222 (a)(5)(A).
        Section 302(a)(5)(B), the so-called ``dispose'' provision of the 
    Act, requires that each contract shall also provide that ``in return 
    for payment of fees established by this section, the Secretary, 
    beginning not later than January 31, 1998, will dispose of the high-
    level radioactive waste or spent fuel involved as provided in this 
    subtitle.'' 42 U.S.C. 10222 (a)(5)(B). While the Act does not define 
    the word ``dispose,'' it does define ``disposal.'' DOE believes that 
    the words ``dispose'' and ``disposal'' are merely different grammatical 
    forms of the same word, and that the Act's definition of ``disposal'' 
    also defines DOE's obligation to ``dispose'' under section 302(a)(5)(B) 
    of the Act. The Act defines ``disposal'' to mean ``the emplacement in a 
    repository of spent nuclear fuel with no foreseeable intent of 
    recovery.'' 42 U.S.C. 10101(9). Thus, the mandate to dispose of SNF 
    beginning January 31, 1998, like the duty to take title to SNF, 
    requires the existence of an operating repository. See H.R. Rep. No. 
    491, Part 1, 97th Cong., 2d Sess. at 59 (1982).2
    
        \2\ DOE notes that the statutory language on disposal quoted 
    above uses ``will'' rather than the term ``shall'' in setting forth 
    the Secretary's duty to dispose of nuclear waste. DOE believes the 
    use of the predictive term ``will'' in the disposal provision of the 
    Act, rather than the mandatory term ``shall'' which is used in the 
    take-title provision, indicates that the January 31, 1998 date 
    expresses the sense of Congress as to when the Department should 
    strive to have a repository in operation, rather than an 
    unconditional legal obligation to initiate acceptance of SNF by a 
    date certain.
    ---------------------------------------------------------------------------
    
        The logic, language, and structure of section 302(a) require that 
    the mandate to dispose and the duty to take title must be read 
    together. Section 302(a)(1) of the Act, which authorizes the Secretary 
    to enter in contracts with utilities ``for acceptance of title, 
    subsequent transportation, and disposal of * * * (SNF)'', indicates 
    that the duty to accept title and the mandate to dispose are part of a 
    sequential process: The Act contemplates that ``taking title'' is a 
    predicate to ``disposal''. Similarly, section 123 of the Act provides 
    that ``[d]elivery, and acceptance by the Secretary, of any high-level 
    radioactive waste or spent nuclear fuel for a repository constructed 
    under this subtitle (42 U.S.C. 10131 et seq., the repository subtitle) 
    shall constitute a transfer to the Secretary of title to such waste or 
    spent fuel.'' 42 U.S.C. 10143. The ``delivery and acceptance'' 
    provision of section 123 implements the ``take title'' provision of 
    section 302(a)(5)(A), and again contemplates that DOE ``take title'' 
    prior to disposal in a repository.
        b. Sections 302(a)(5) (A) and (B) of the Act must not only be read 
    together, but also must be read in the context of the entire Act. When 
    read in conjunction with other provisions in the Act, these provisions 
    clearly do not contemplate nuclear waste disposal by DOE beginning 
    January 31, 1998, in the absence of an operational repository.
        The findings and purposes section of the Act states that ``the 
    Federal Government has the responsibility to provide for the permanent 
    disposal of nuclear waste,'' 42 U.S.C. 10131(a)(4), and that the 
    purpose of the Act is ``to establish a schedule for the siting, 
    construction, and operation of repositories that will provide a 
    reasonable assurance that the public will be adequately protected from 
    the hazards posed by high-level waste and such spent nuclear fuel as 
    may be disposed of in a repository.'' 42 U.S.C. 10131 (b)(1). As noted 
    above, the term ``disposal'' is defined in the Act to mean 
    ``emplacement of nuclear waste in a repository with no foreseeable 
    intent of recovery.'' 42 U.S.C. 10101 (9).
        However, the Act imposes numerous prerequisites on the Department's 
    ability to develop a repository and dispose of SNF that demonstrate 
    that the Act did not contemplate that DOE would have an unconditional 
    duty to begin disposing of SNF in 1998. For instance, the Act provides 
    that only Yucca Mountain, in Nevada, is to be characterized as a 
    potential repository site, 42 U.S.C 10172, and that DOE may not 
    commence construction of a repository at Yucca Mountain unless and 
    until the site been found suitable for a repository through the site 
    characterization process, 42 U.S.C. 10134. The Act specifically 
    recognizes that the Yucca Mountain site may be found unsuitable for 
    development of a repository, and states that ``if the Secretary at any 
    time determines the Yucca Mountain site to be unsuitable for 
    development as a repository, the Secretary shall terminate all site 
    characterization activities at such site * * * (and) reclaim the site 
    to mitigate any significant adverse environmental impacts caused by 
    site characterization at such site.'' 42 U.S.C. 10133(c)(3). Moreover, 
    even if Yucca Mountain proves suitable, the Act imposes additional 
    conditions on the actual development of the site as a repository. For 
    example, the Act provides that the Secretary must decide whether to 
    recommend approval of the site to the President; the President must 
    determine whether he considers the site qualified; and if the President 
    ultimately recommends development of the site to Congress, the host 
    state may disapprove that recommendation for any reason at all, in 
    which case an entirely new law must be enacted by Congress to override 
    the host state's disapproval. 42 U.S.C. 10134 and 10135. Assuming site 
    suitability, a favorable Presidential recommendation, and enactment of 
    a new law to override any state notice of disapproval, the Act further 
    requires DOE to obtain an NRC license to construct and operate a 
    repository. 42 U.S.C. 10134(b).
        Each of these statutory conditions for construction and operation 
    of a repository represents a Congressionally-created contingency that 
    could prevent or delay construction and operation of a repository. 
    Given the number of these contingencies, Congress could not have 
    intended to impose an unconditional obligation on DOE to take and 
    dispose of SNF by a date certain.3
    
        \3\ In addition, as discussed infra, beginning at page 19, the 
    Act contained only very limited authority for DOE to provide interim 
    storage in the event that a repository is not in 
    operation. [[Page 21796]] 
    ---------------------------------------------------------------------------
    
        2. The legislative history of the Act confirms that both the ``take 
    title'' and the ``dispose'' provisions of section 302(a)(5) require an 
    operating repository before their obligations attach.
        Subparagraphs (A) and (B) of Section 302(a)(5) were originally part 
    of section 124 of H.R. 3809. The House Report on H.R. 3809 stated that 
    ``Section 124 authorizes the Secretary to contract with utilities or 
    other agents requiring use of repositories constructed under this Act 
    to provide repository services in exchange for payments by repository 
    users to cover program costs.'' H.R. Rep. No. 491, Part 1, 97th Cong., 
    2nd Sess. at 58 (1982). The House Report further stated that ``[a]ll 
    persons desiring to dispose of high level waste or spent fuel in 
    repositories constructed under this subtitle are required to pay a 
    ratable portion of the costs of such disposal.'' H.R. Rep. No. 491, 
    Part 1, 97th Cong., 2d Sess. at 58 (April 27, 1982). As the quoted 
    language indicates, the focus of section 124 was on contracting for the 
    disposal of spent nuclear fuel in a repository.
        With regard to what emerged as subparagraph (A) of section 
    302(a)(5), the House Committee Report on section 124 of H.R. 3809 
    stated:
    
        Paragraph 4(A) requires that under such contracts the Secretary 
    will be required to take title to high level waste or spent fuel, at 
    the request of the generator, as expeditiously as practicable 
    following the commencement of operation of a repository.
    
    H.R. Rep. No. 491, Part 1, 97th Cong., 2d Sess. at 59 (1982). Thus, 
    subparagraph (A) in H.R. 3809, like subparagraph (A) in the Act, 
    clearly made commencement of operation of a repository a condition 
    precedent to taking title.
        Significantly, the House Committee Report on H.R. 3809 also 
    described the source of the current Act's subparagraph (B) in terms of 
    the existence of a permanent disposal facility:
    
        Paragraph 4(B) makes the Secretary responsible for disposing of 
    high level waste or spent fuel as provided under this subtitle in 
    permanent disposal facilities, beginning not later than January 
    1998, in return for the payment of fees established by this section.
    
    Id. at 59. ``This subtitle'' referred to Subtitle A, ``Repositories for 
    Disposal of High-Level Radioactive Waste and Spent Nuclear Fuel,'' of 
    which section 124 was then a part. Here too, as the underscored 
    language and reference to Subtitle A make clear, the obligation 
    contemplated depended upon the successful development of a repository.
        The conclusion that section 302(a)(5) of the Act was not intended 
    to create an obligation to dispose of SNF unless and until a repository 
    had been developed is also supported by a floor statement made during 
    the Senate's debate on the Act by the then Chairman of the Senate 
    Energy and Natural Resources Committee, a primary sponsor of the Act, 
    Senator James McClure. On December 13, 1982, Senators McClure, Simpson, 
    Jackson, Johnston and Domenici offered amendment number 4983, which 
    struck all the language after the enacting clause of H.R. 3809, and 
    replaced it with a Senate version of the proposed legislation. Section 
    302 of the Senate amendment would have required DOE to take title and 
    store or dispose of nuclear waste no later than December 31, 1996. 
    Unlike the House version of H.R. 3809, the Senate amendment made no 
    mention of an operating repository. See 128 Cong. Rec. S14,484, S14,501 
    (daily ed. Dec. 13, 1982). However, after proposing the Senate 
    amendment, Senator McClure then offered--and the Senate accepted--an 
    amendment to section 302(a)(5) of the substitute amendment which 
    brought the Senate version of that provision into conformity with the 
    House version contained in H.R. 3809. Senator McClure described the 
    effect of this amendment as follows:
    
        Mr. President, this amendment amends section 302(a)(5) of the 
    substitute amendment to provide that the Secretary of Energy take 
    title to high-level waste or spent fuel as expeditiously as 
    practicable upon the request of the generator of such waste. In 
    addition, this amendment directs the Secretary to begin, not later 
    than January 31, 1998, to begin to dispose of the high-level 
    radioactive waste or spent nuclear fuel from those generating such 
    waste. Under the substitute amendment, there was some concern that, 
    in directing the Secretary to take title to and dispose of such 
    wastes no later than December 31, 1996, we might not be giving the 
    Secretary enough flexibility to tailor his schedule for accepting 
    such wastes to the availability of a repository. This amendment 
    simply directs the Secretary to take title to such wastes as 
    expeditiously as practicable, upon the request of the generator of 
    those wastes, after commencement of repository operation.
    
    128 Cong. Rec. S15,657 (daily ed. Dec. 20, 1982). This summary of what 
    section 302(a)(5) ``directs'' indicates that Congress did not intend to 
    establish an inflexible schedule and that it intended to ``tailor'' 
    DOE's obligation for accepting SNF to the availability of a repository, 
    albeit that it intended for DOE to proceed ``as expeditiously as 
    practicable.''4
    
        \4\ A few commenters claimed that certain statements from the 
    legislative history of the monitored retrievable storage provisions 
    of the Act support their assertion that DOE has an unconditional 
    duty to accept SNF for disposal beginning in 1998. They cited the 
    following statement of Senator Bennett Johnston, made during the 
    floor debate on the 1987 amendments, as evidence of Congress' intent 
    that the Department has an unconditional obligation to begin 
    accepting waste in 1998:
        The MRS is not an alternative to at-reactor storage, and it is 
    not a substitute for a repository. Utilities are required to take 
    care of their own storage until 1998, but the Federal Government has 
    a contractual commitment to take title to spent fuel beginning in 
    1998. An MRS will better ensure that the Department is able to meet 
    this contractual commitment to accept spent fuel beginning in 1998.
        133 Cong. Rec. S16,045 (daily ed. Nov. 10, 1987). The following 
    statement of Senator James McClure from the same debate was also 
    relied upon by a commenter:
        Furthermore, we have an option to proceed with the construction 
    of a monitored retrievable storage (MRS) facility for receipt and 
    temporary storage of fuel by 1998 and thereby meet the Government's 
    statutory obligation to begin taking spent fuel by that date.
        133 Cong. Rec. S15,795 (daily ed. Nov. 10, 1987).
        DOE believes that these 1987 statements do not supplant the 
    foregoing analysis of what Congress intended when it enacted Section 
    302(a)(5), because they were not contemporaneous with passage of the 
    Act in 1982. Post-enactment views by individual legislators are 
    entitled to little weight in construing a statute enacted by a prior 
    Congress.
    ---------------------------------------------------------------------------
    
        3. The Standard Contract, which was promulgated through notice and 
    comment rulemaking, implements the provisions of section 302(a)(5) of 
    the Act.5 Article II of the Standard Contract, entitled ``Scope,'' 
    states that ``[t]he services to be provided by DOE under this contract 
    shall begin, after commencement of facility operations, not later than 
    January 31, 1998 and shall continue until such time as all (nuclear 
    waste from the contracting utilities) has been disposed of.'' 10 CFR 
    961.11, Art. II.
    
        \5\The U.S. Court of Appeals for the District of Columbia 
    Circuit has held that the Standard Contract should be treated as 
    more akin to a regulation, rather than a traditional contract, since 
    its terms were established by rulemaking following notice and 
    comment. Commonwealth Edison Co. v. United States Department of 
    Energy, 877 F.2d 1042, 1045 (D.C. Cir. 1989).
    ---------------------------------------------------------------------------
    
        Some commenters asserted that the language in Article II of the 
    Standard Contract that ``(t)he services to be provided by DOE under 
    this contract shall begin * * * not later than January 31, 1998,'' 
    either represents DOE's recognition of, or itself creates, an 
    unconditional legal obligation to begin accepting nuclear waste by 
    1998. However, the Standard Contract contains the specific condition 
    that the services to be provided by DOE ``shall begin after 
    commencement of facility operations.'' 10 CFR 961.11, Art. II.6 
    One of the recitals in the preamble to [[Page 21797]] the Standard 
    Contract similarly indicates that the Department's obligations are 
    conditioned upon the existence of an operational storage or disposal 
    facility constructed under the Act:
    
        \6\ Under the Standard Contract, the term ``DOE facility'' is 
    defined to mean either a disposal or interim storage facility 
    operated by or on behalf of DOE. See 10 CFR 961.11, Art. I.
    ---------------------------------------------------------------------------
    
        Whereas, the DOE has the responsibility, following commencement 
    of operation of a repository, to take title to the spent nuclear 
    fuel or high-level radioactive waste involved as expeditiously as 
    practicable upon the request of the generator or owner of such waste 
    or spent nuclear fuel.
    
    10 CFR 961.11, Preamble. The Standard Contract, like the Act, thus 
    predicated DOE's obligation on the development of a facility under the 
    Act.
        This reading of the Standard Contract was confirmed by a statement 
    of former Secretary Donald Hodel in 1984, the year following the 
    promulgation of the Standard Contract. In a written response to a 
    question posed in a letter from Senator Bennett Johnston, Secretary 
    Hodel stated:
    
        The Department is authorized to implement the Act through 
    contractual commitments. To this end, the Department plans to 
    incorporate into its contracts provisions which specify the minimum 
    amount of spent fuel and waste which the Department will be 
    obligated to accept, not later than January 31, 1998. Since these 
    contracts have not yet been modified, it would be premature for the 
    Department to speculate on particulars that might ultimately be 
    incorporated in any or all of the contracts. However, it is my 
    intention that this commitment in the Contracts, together with the 
    overall thrust of the Act, will create an obligation for the 
    Department to accept spent fuel in 1998 whether or not a repository 
    is in operation.
    
        Although former Secretary Hodel stated that he intended for DOE to 
    assume an unconditional obligation to begin accepting SNF in 1998, he 
    also recognized that the terms of the Standard Contract would have to 
    be changed in order to create such an unconditional obligation. 
    However, the Department never undertook a rulemaking to modify the 
    Standard Contract. Thus, this essentially contemporaneous construction 
    of the Standard Contract reinforces the conclusion that the Contract 
    did not and does not create, or recognize, an unconditional 
    obligation.7
    
        \7\One commenter on the NOI criticized DOE's denial of an 
    obligation to begin accepting SNF from domestic utilities on the 
    ground that DOE has accepted ``foreign SNF'' for storage at its own 
    facilities. However, the authority for acceptance of foreign SNF 
    arises under the Atomic Energy Act, as amended, not under the 
    Nuclear Waste Policy Act. The foreign fuel in question, which is not 
    commercial SNF from domestic utilities but much smaller fuel 
    elements from research reactors, contains highly enriched uranium 
    that must be controlled for nuclear nonproliferation purposes. It is 
    because of these nonproliferation concerns that the United States 
    government has in some circumstances received foreign SNF under the 
    Atomic Energy Act in order to remove it from international commerce. 
    No Nuclear Waste Fund monies are (or could be) used for this storage 
    activity.
    ---------------------------------------------------------------------------
    
    B. Interim Storage Authority
    
        The Department recognizes that some utilities are running out of 
    on-site storage capacity and will have to provide additional storage 
    capacity until a repository or interim storage facility is available. 
    In response to the NOI, a number of comments stated that DOE should 
    provide interim storage. However, DOE has concluded that it has no 
    authority under the Act to provide interim storage in present 
    circumstances.8
    
        \8\DOE's multi-purpose canister program is part of DOE's overall 
    transportation strategy for disposal of SNF, and the use of Nuclear 
    Waste Fund monies to support this work is authorized by Section 
    302(d)(4) of the Act, which provides that the Secretary may make 
    expenditures from the Nuclear Waste Fund for any costs incurred in 
    connection with the transportation of SNF.
    ---------------------------------------------------------------------------
    
        Interim storage by DOE was contemplated by the Act in only two 
    situations, neither of which currently applies. Under the Act, DOE had 
    authority to offer a limited interim storage option. See 42 U.S.C. 
    10156. However, that authority has, by its express terms, expired. 
    Under the Act, DOE also has authority to provide for interim storage in 
    an MRS. That authority also is inapplicable, however, because the Act 
    ties construction of an MRS to the schedule for development of a 
    repository. See 42 U.S.C. 10165, 10168. Because these are the only 
    interim storage authorities provided by the Act, and because the Act 
    expressly forbids use of the Nuclear Waste Fund to construct or expand 
    any facility without express congressional authorization (42 U.S.C. 
    10222(d)), DOE lacks authority under the Act to provide interim storage 
    services under present circumstances.
    
    C. Use of Nuclear Waste Funds to Offset Financial Burdens to Utilities 
    of Storing Nuclear Waste Beyond 1998
    
        Section 302(d) of the Act states that the Nuclear Waste Fund may be 
    used only for radioactive waste disposal activities under titles I and 
    II of the Act, including a number of enumerated activities.9 42 
    U.S.C. 10222(d). Paying for the costs of on-site storage is not 
    enumerated in that provision.
    
        \9\Section 302(d) further provides that no funds may be spent on 
    construction or expansion of any facility unless expressly 
    authorized.
    ---------------------------------------------------------------------------
    
        Although the Act thus does not provide for use of the Nuclear Waste 
    Fund to help utilities defray costs of on-site storage, if the Act were 
    construed unconditionally to require DOE to begin providing disposal 
    services in January of 1998 notwithstanding DOE's inability to do so, 
    utilities might be entitled to financial relief under the terms of the 
    Standard Contract. Since the Act itself does not address the 
    consequences of a failure by DOE to perform its obligations under the 
    Act, it has fallen to DOE as the administering agency to fill the gap 
    left by Congress. DOE has done so through the Standard Contract, which 
    expressly addresses the situation in which performance by either party 
    to the contract is delayed.
        Under Article IX, entitled ``DELAYS,'' the Standard Contract 
    provides that neither party shall be liable for damages in the case of 
    unavoidable delay and that the parties will adjust their schedules, as 
    appropriate, to accommodate such delay. Art. IX, A. In the case of an 
    avoidable delay, however, the Standard Contract provides that the 
    ``charges and schedules specified by this contract will be equitably 
    adjusted to reflect any estimated additional costs incurred by the 
    party not responsible for or contributing to the delay.'' Art. IX, B. 
    Were DOE deemed to have an unconditional obligation to begin providing 
    disposal services in 1998, we have concluded that the Delays Clause 
    would be applicable in the event of a failure to perform. Were the 
    Delays Clause to be invoked, Article XVI of the Standard Contract 
    establishes the process for resolving disputed questions of fact (e.g., 
    whether a delay has occurred and, if so, whether it was avoidable or 
    unavoidable). Article XVI provides for initial resolution of disputed 
    facts by the designated Contracting Officer, with a right of appeal to 
    the DOE Board of Contract Appeals. In sum, it is the Department's view 
    that, were the Act to be construed to impose an unconditional 
    obligation to begin to provide disposal services in 1998, the 
    appropriate remedy would be the contractual remedy under the Delays 
    Clause and Article XVI.
    
    D. Availability of Alternative Dispute Resolution Procedures
    
        The Department believes that important public and private interests 
    are implicated by the need for orderly financial and technical planning 
    with respect to the Department's inability to accept SNF in 1998. There 
    are also equitable considerations that may argue for some form of 
    relief to help offset costs incurred as a result of the Department's 
    inability to begin acceptance of SNF in 1998. The Department recognizes 
    that these equitable and public interest considerations may be better 
    addressed [[Page 21798]] and resolved through settlement discussions 
    than through litigation or through the process established by Article 
    XVI of the Standard Contract. Therefore, in accordance with the 
    Department's commitment to increased use of alternative dispute 
    resolution procedures, the Department is prepared to discuss with 
    utilities and other parties to the pending litigation (Northern States 
    Power Company v. U.S. Department of Energy, Nos. 94-1457, 94-1458, 94-
    1574 (D.C. Cir., 1994)) financial or other assistance that may be 
    appropriate in light of the Department's inability to begin providing 
    disposal services in 1998.
    
        Issued in Washington, D.C., April 28, 1995.
    Daniel A. Dreyfus,
    Director, Office of Civilian Radioactive Waste Management.
    [FR Doc. 95-10902 Filed 5-2-95; 8:45 am]
    BILLING CODE 6450-01-P
    
    

Document Information

Published:
05/03/1995
Department:
Energy Department
Entry Type:
Notice
Action:
Department of Energy final interpretation of nuclear waste acceptance issues.
Document Number:
95-10902
Pages:
21793-21798 (6 pages)
PDF File:
95-10902.pdf