E7-8408. Clark Canyon Hydro, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests  

  • Start Preamble April 26, 2007.

    Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection.

    a. Type of Application: Major License.

    b. Project No.: 12429-001.

    c. Date filed: August 1, 2006.

    d. Applicant: Clark Canyon Hydro, LLC.

    e. Name of Project: Clark Canyon Dam Hydroelectric Project.

    f. Location: On the Beaverhead River, 18 miles southwest of the Town of Dillon, Beaverhead County, Montana. The project would occupy 3.5 acres of federal land administered by the Bureau of Reclamation.

    g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).

    h. Applicant Contact: Brent L. Smith, Northwest Power Services, Inc., P.O. Box 535, Rigby, ID 83442, (208) 745-0834 or Dr. Vincent Lamarra, Ecosystems Research Institute, Inc., 975 South State Highway, Logan, UT 84321.

    i. FERC Contact: Dianne Rodman, (202) 502-6077, dianne.rodman@ferc.gov.

    j. Deadline for filing motions to intervene and protests: 60 days from the issuance date of this notice.

    All documents (original and eight copies) should be filed with: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426.

    The Commission's Rules of Practice and Procedures require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency.

    Motions to intervene and protests may be filed electronically via the Internet in lieu of paper. The Commission strongly encourages electronic filings. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site (http://www.ferc.gov) under the “e-Filing” link.

    k. This application has been accepted for filing, but is not ready for environmental analysis at this time.

    l. The proposed project would utilize the Bureau of Reclamation's existing Clark Canyon dam, and would consist of the following new facilities: (1) A steel liner in the existing 9-foot-diameter concrete outlet conduit; (2) a new outlet gate structure; (3) a 9-foot-diameter steel penstock bifurcating into an 8-foot diameter and a 6-foot diameter steel penstock directing flow to the turbine units about 70 feet from the bifurcation; (4) a powerhouse containing two generating units with a combined capacity of 4.75 megawatts; (5) a 300-foot-long access road; (6) a switchyard; (7) a substation; and (8) about 0.3 mile of transmission line connecting the project to the local utility's existing transmission system. The average annual generation is estimated to be 16.5 gigawatthours.

    m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission's Web site at http://www.ferc.gov using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-866-208-3676, or for TTY, (202) 502-8659. A copy is also available for inspection and reproduction at the address in item h above.

    You may also register online at http://www.ferc.gov/​docs-filing/​esubscription.asp to be notified via e-mail of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support.

    n. Any qualified applicant desiring to file a competing application must submit to the Commission, on or before the specified deadline date for the particular application, a competing development application, or a notice of intent to file such an application. Submission of a timely notice of intent allows an interested person to file the competing development application no later than 120 days after the specified deadline date for the particular application. Applications for preliminary permits will not be accepted in response to this notice.

    A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant named in this public notice.

    Anyone may submit a protest or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission's Rules may become a party to the proceeding. Any protests or motions to intervene must be received on or before the specified deadline date for the particular application.

    When the application is ready for environmental analysis, the Commission will issue a public notice requesting comments, recommendations, terms and conditions, or prescriptions.

    All filings must (1) Bear in all capital letters the title “PROTEST” or “MOTION TO INTERVENE,” “NOTICE OF INTENT TO FILE COMPETING APPLICATION,” or “COMPETING APPLICATION;” (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR Start Printed Page 24581385.2001 through 385.2005. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application.

    o. Procedural schedule: The application will be processed according to the following Hydro Licensing Schedule. Revisions to the schedule will be made as appropriate.

    Date
    Issue Scoping Document 1 for commentsMay 2007.
    Issue Scoping Document 2August 2007.
    Additional information dueDecember 2007.
    Notice of application is ready for environmental analysisJanuary 2008.
    Notice of the availability of the EAJuly 2008.
    Ready for Commission's decision on the applicationOctober 2008.
    Start Signature

    Kimberly D. Bose,

    Secretary.

    End Signature End Preamble

    [FR Doc. E7-8408 Filed 5-2-07; 8:45 am]

    BILLING CODE 6717-01-P

Document Information

Published:
05/03/2007
Department:
Federal Energy Regulatory Commission
Entry Type:
Notice
Document Number:
E7-8408
Pages:
24580-24581 (2 pages)
Docket Numbers:
Project No. 12429-001
EOCitation:
of 2007-04-26
PDF File:
e7-8408.pdf