99-11509. Northern Natural Gas Company; Notice of Request Under Blanket Authorization
[Federal Register Volume 64, Number 88 (Friday, May 7, 1999)]
[Notices]
[Page 24635]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 99-11509]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP99-337-000]
Northern Natural Gas Company; Notice of Request Under Blanket
Authorization
April 30, 1999.
Take notice that on April 26, 1999, Northern Natural Gas Company
(Northern), 1111 South 103rd Street, Omaha, Nebraska 68124-1000, filed
in Docket No. CP99-337-000 a request pursuant to Secs. 157.205, and
157.212, of the Commission's Regulations under the Natural Gas Act (18
CFR 157.205, 157.212) for authorization to relocate an existing
delivery point serving Northern States Power Company on the Faribault
Branchline located in Rice County, Minnesota under Northern's blanket
certificate issued in Docket No. CP82-401-000, pursuant to Section 7 of
the Natural Gas Act, all as more fully set forth in the request that is
on file with the Commission and open to public inspection. This filing
may be viewed on the web at http://www.ferc.fed.us/online/rims.htm
(call 202-208-2222 for assistance).
Northern states that the new delivery point will serve as a master
meter and provide a central measurement point on the Faribault
branchline and that no facilities are proposed to be retired or
abandoned. Northern states that the total estimated cost to install the
master meter is $228,000.
Any person or the Commission's staff may, within 45 days after
issuance of the instant notice by the Commission, file pursuant to Rule
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to
intervene or notice of intervention and pursuant to Sec. 157.205 of the
Regulations under the Natural Gas Act (18 CFR 157.205) a protest to the
request. If no protest is filed within the time allowed therefor, the
proposed activity shall be deemed to be authorized effective the day
after the time allowed for filing a protest. If a protest is filed and
not withdrawn within 30 days after the time allowed for filing a
protest, the instant request shall be treated as an application for
authorization pursuant to Section 7 of the Natural Gas Act.
David P. Boergers,
Secretary.
[FR Doc. 99-11509 Filed 5-6-99; 8:45 am]
BILLING CODE 6717-01-M
Document Information
- Published:
- 05/07/1999
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 99-11509
- Pages:
- 24635-24635 (1 pages)
- Docket Numbers:
- Docket No. CP99-337-000
- PDF File:
-