2023-09810. Transcontinental Gas Pipeline Company, LLC; Notice of Application and Establishing Intervention Deadline
-
Start Preamble
Take notice that on April 19, 2023 Transcontinental Gas Pipe Line Company, LLC, (Transco) P.O. Box 1396, Houston, Texas 77251–1396, filed an application under section 7(b) and 7(c) of the Natural Gas Act (NGA), and Part 157, Federal Energy Regulatory Commission's (Commission) requesting the authorization to construct, install, modify, operate and maintain its Alabama Georgia Connecter Project located at Marengo and Randolph Counties, Alabama and Coweta, Henry, and Walton Counties, Georgia which will provide an additional 63,800 dekatherms per day of firm transportation service to Transco's Station 85 to multiple existing delivery locations on the Transco Mainline and Transco's Georgia Extension Lateral.
Specifically, Transco is requesting approval to (1) re-wheel two existing compressor units at its Compressor station (CS) 90 in Marengo County, Alabama; (2) add 3,865 Horsepower (hp) by upgrading two existing compressor units at its CS 110 in Randolph County, Alabama; (3) re-wheel three existing compressor units at its Compressor station 115 in Coweta County, Georgia; (4) add 5,000 hp by replacing one compressor unit at its Compressor station 120 in Henry County, Georgia; (5) increase the certificated horsepower from 49,800 hp to 55,800 hp by increasing the currently certificated hp of an existing compressor unit, and an associated re-wheel at its CS 125 in Walton County, Georgia; and (6) various modifications to ancillary equipment and station piping at the previously listed compressor stations. The total estimated cost of the project is approximately $70.7 million, all as more fully set forth in the request which is on file with the Commission and open to public inspection.
In addition to publishing the full text of this document in the Federal Register , the Commission provides all interested persons an opportunity to view and/or print the contents of this document via the internet through the Commission's Home Page ( http://ferc.gov) using the “eLibrary” link. Enter the docket number excluding the last three digits in the docket number field to access the document. At this time, the Commission has suspended access to the Commission's Public Reference Room. For assistance, contact the Federal Energy Regulatory Commission at FERCOnlineSupport@ferc.gov or call toll-free, (886) 208–3676 or TYY, (202) 502–8659.
Any questions regarding the proposed project should be directed to Jordan Kirwin, Director, Rate & Regulatory, Transcontinental Gas Pipeline Company, LLC, Post Office Box 1396, Houston, Texas 77251–1396; by phone at (346) 439–0447 or by email to Jordan.Kirwin@Williams.com.
Pursuant to section 157.9 of the Commission's Rules of Practice and Procedure,[1] within 90 days of this Notice the Commission staff will either: complete its environmental review and place it into the Commission's public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff's issuance of the final environmental impact statement (FEIS) or environmental assessment (EA) for this proposal. The filing of an EA in the Commission's public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff's FEIS or EA.
Public Participation
There are three ways to become involved in the Commission's review of Start Printed Page 29904 this project: you can file a protest to the project, you can file a motion to intervene in the proceeding, and you can file comments on the project. There is no fee or cost for filing protests, motions to intervene, or comments. The deadline for filing protests, motions to intervene, and comments is 5:00 p.m. Eastern Time on May 24, 2023. How to file protests, motions to intervene, and comments is explained below.
Protests
Pursuant to section 157.205 of the Commission's regulations under the NGA,[2] any person [3] or the Commission's staff may file a protest to the request. If no protest is filed within the time allowed or if a protest is filed and then withdrawn within 30 days after the allowed time for filing a protest, the proposed activity shall be deemed to be authorized effective the day after the time allowed for protest. If a protest is filed and not withdrawn within 30 days after the time allowed for filing a protest, the instant request for authorization will be considered by the Commission.
Protests must comply with the requirements specified in section 157.205(e) of the Commission's regulations,[4] and must be submitted by the protest deadline, which is May 24, 2023. A protest may also serve as a motion to intervene so long as the protestor states it also seeks to be an intervenor.
Interventions
Any person has the option to file a motion to intervene in this proceeding. Only intervenors have the right to request rehearing of Commission orders issued in this proceeding and to subsequently challenge the Commission's orders in the U.S. Circuit Courts of Appeal.
To intervene, you must submit a motion to intervene to the Commission in accordance with Rule 214 of the Commission's Rules of Practice and Procedure [5] and the regulations under the NGA [6] by the intervention deadline for the project, which is May 24, 2023. As described further in Rule 214, your motion to intervene must state, to the extent known, your position regarding the proceeding, as well as your interest in the proceeding. For an individual, this could include your status as a landowner, ratepayer, resident of an impacted community, or recreationist. You do not need to have property directly impacted by the project in order to intervene. For more information about motions to intervene, refer to the FERC website at https://www.ferc.gov/how-guides.
All timely, unopposed motions to intervene are automatically granted by operation of Rule 214(c)(1). Motions to intervene that are filed after the intervention deadline are untimely and may be denied. Any late-filed motion to intervene must show good cause for being late and must explain why the time limitation should be waived and provide justification by reference to factors set forth in Rule 214(d) of the Commission's Rules and Regulations. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies (paper or electronic) of all documents filed by the applicant and by all other parties.
Comments
Any person wishing to comment on the project may do so. The Commission considers all comments received about the project in determining the appropriate action to be taken. To ensure that your comments are timely and properly recorded, please submit your comments on or before May 24, 2023. The filing of a comment alone will not serve to make the filer a party to the proceeding. To become a party, you must intervene in the proceeding.
How To File Protests, Interventions, and Comments
There are two ways to submit protests, motions to intervene, and comments. In both instances, please reference the Project docket number CP23–194–000 in your submission.
(1) You may file your protest, motion to intervene, and comments by using the Commission's eFiling feature, which is located on the Commission's website ( www.ferc.gov ) under the link to Documents and Filings. New eFiling users must first create an account by clicking on “eRegister.” You will be asked to select the type of filing you are making; first select General” and then select “Protest”, “Intervention”, or “Comment on a Filing”; or [7]
(2) You can file a paper copy of your submission by mailing it to the address below. Your submission must reference the Project docket number CP23–194–000.
To mail via USPS, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street NE, Washington, DC 20426.
To send via any other courier, use the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 20852.
The Commission encourages electronic filing of submissions (option 1 above) and has eFiling staff available to assist you at (202) 502–8258 or FERCOnlineSupport@ferc.gov.
Protests and motions to intervene must be served to the applicant by mail to: Jordan Kirwin, Director, Rates & Regulatory, Transcontinental Gas Pipe Line Company, LLC, Post Office Box 1396, Houston, Texas 77251–1396; or by email (with a link to the document) at Jordan.Kirwin@Williams.com.
Any subsequent submissions by an intervenor must be served on the applicant and all other parties to the proceeding. Contact information for parties can be downloaded from the service list at the eService link on FERC Online.
Tracking the Proceeding
Throughout the proceeding, additional information about the project will be available from the Commission's Office of External Affairs, at (866) 208–FERC, or on the FERC website at http://www.ferc.gov using the “eLibrary” link as described above. The eLibrary link also provides access to the texts of all formal documents issued by the Commission, such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. For more information and to register, go to https://www.ferc.gov/ferc-online/overview.
Intervention Deadline: 5:00 p.m. Eastern Time on May 24, 2023.
Start SignatureDated: May 3, 2023.
Kimberly D. Bose,
Secretary.
Footnotes
1. 18 CFR (Code of Federal Regulations) 157.9.
Back to Citation3. Persons include individuals, organizations, businesses, municipalities, and other entities.18 CFR 385.102(d).
Back to Citation7. Additionally, you may file your comments electronically by using the eComment feature, which is located on the Commission's website at www.ferc.gov under the link to Documents and Filings. Using eComment is an easy method for interested persons to submit brief, text-only comments on a project.
Back to Citation[FR Doc. 2023–09810 Filed 5–8–23; 8:45 am]
BILLING CODE 6717–01–P
Document Information
- Published:
- 05/09/2023
- Department:
- Federal Energy Regulatory Commission
- Entry Type:
- Notice
- Document Number:
- 2023-09810
- Pages:
- 29903-29904 (2 pages)
- Docket Numbers:
- Docket No. CP23-194-000
- PDF File:
- 2023-09810.pdf